SCIENCE ADDITION

June 19, 2000 Update

Science/Math:
Multiple, simultaneous activities are underway with the Science/Math addition. The west addition has had the upper housing framed, with roofing to begin this week. Steel stud framing on the 1st floor is approximately 85 % complete and work proceeds on mechanical systems housed in the ceiling of the 1st floor.

Within the current Science building, demolition work has begun by contractors as power circuits have been cut out and walls dismantled. Contractors were able to begin work in isolated areas of the building as Science personnel completed their move.

The Bond Management Team extends thanks and appreciation to the entire Science staff and the Bond Moving Team for their outstanding, collaborative efforts in clearing the building.

Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
CURRENT PROJECT PICTURES


2011 Site Archive