Construction Updates: All Bond Projects
(links marked with * are .pdf and require Adobe Reader)
ALL PROJECTS
PROJECT UPDATES
September 27, 2011
BUILDING 10 AND 11 REMODELS
Construction of the new RTEC and Art building, and the remodel of Building 11 is in the final stages of completion. FMP landscape crews are working on the outside of the building while Hyland Construction completes a list of touch-up items inside the building. These touch-up items are expected with every project and always take time to complete. One of these items is the audiovisual for the classrooms. Due to a late order of hardware, these rooms will not be completed until the end of this week. Contact Mark Richardson, 3456.
September 20, 2011
BUILDING 10 REMODEL
“Building 10 can now be occupied.” This is the authorization statement made by the Lane County building inspector last week. Building 10 has been granted a temporary occupancy permit that will allow the college to open for the fall term. This permit also allows Lane to make some last minute modifications to the exhaust system for the Art Department. The main item now is clean up. With the project moving along at a fast pace, the focus week is working on touch up items and cleaning around the outside of the building. Contact Mark Richardson, 3456.
BUILDING 11 REMODEL
This project is still in the completion phase in some areas of the building. Specialized Support Services has moved into their newly remodeled space. The Art Gallery and Art History classroom have been completed but there is some minor touch up work left to do. Hyland crews are finishing the touch up work and expect to have it completed by Wednesday, September 21. Contact Mark Richardson, 3456.
TRACK AND INNER FIELD RESURFACING PROJECT
The project will be completed by the end of the day, Tuesday, September 20 and will reopen for general use on Wednesday, September 21. Contact Mark Richardson, 3456.
September 13, 2011
BUILDING 10
This project is moving forward on its goal for a completion date of September 15. The project has had some challenges but will be finished and ready for the fall term. Hyland Construction and staff are working six days a week to make sure the project is completed. Classrooms inside the new building are designed and planned with smart technology that will allow the programs to offer the most advanced information technology available to all students. The open industrial design of the building is intended to inspire students of all ages to get involved with the professional technical programs scheduled in this building. In the final phases of the project, many staff members have been assisting each other in a team effort to make sure the classrooms and labs are ready for the fall term. Construction clean up and touch up to work is expected to last for a while after the project is completed. Some last minute changes in the design of the building have caused some tasks to overlap into the first part of the fall term. These alterations are small in nature and will not affect the college’s ability to get a certificate of occupancy or the opening of classes in the new building.
A special thank you has been expressed to Andy Salzman and Jeffery Hanson for their help and hard work on this project. Andy and Jeff have put in long hours on this project to make sure the new building is ready for students. Andy has supported this project with valuable information and hours of dedication in relocating the Art Division. In addition, Mark Richardson has done a wonderful job coordinating this project from the start to this point and plans to continue working extended hours to make sure the punch lists are thorough and that every needed task stays on schedule. Contact Mark Richardson, 3456.
BUILDING 11 REMODEL
This building project is a result of three separate projects that are going together to occupy and function from Building 11. The first project will have Hyland Construction working on the new offices for the SSS team. Next, a new Art Gallery for student artwork displays will be assembled, the last part of the project is to renovate the Art-history classrooms and add two more classrooms on the north side of the building. Another part of the project is being completed by FMP trades on the second floor of the buildings. The project coordinator Heath, along with the other leads is working hard to complete this project by the start of the fall term. Contact Mark Richardson, 3456.
TRACK AND SOCCER BOWL ENHANCEMENT
This fast-paced task being performed by Atlas is scheduled to be completed by September 22. Applying the new color coating on the track surface is a six-step process. The weather for applying the materials has been great and this week is forecasting overcast skies but no rain. The installation of the new material used to complete this project is only adversely affected by rain. Since we have had sunny warm weather, the installation is moving along on schedule. This week the final coatings will be applied to the track and lane striping will follow. After the striping has been completed the track will be ready for use. All of this work is being done under the original warrantee of the manufacturer and at no cost to the college. This work corrects color inconsistencies between manufactured product “lots” or “batches” and provides the college with the highest possible track surface. The track surface will be ready for the upcoming track event on September 24. Contact Mark Richardson, 3456.
August 30, 2011
BUILDING 10 REMODEL
Hyland Construction and their crews are now working overtime to make sure the project is completed. The classrooms on the second floor are not at a point where tables and furniture can be installed. Furniture for the building was scheduled to arrive on August 29 and will be placed in offices. Classroom tables and chairs are expected to arrive soon as well. Cabinetry for the classrooms is being installed, and the finished product looks great. This week Hyland construction will be focusing on the outside of the building. All the office trailers will be removed this week and the area around Building 10 will be cleaned. Now that the building is secure, all the temporary fences will be removed from the site. Along with disassembling temporary fence, Island Fence will remove the permanent fence from around the trash compactor and will reinstall it in its new location. After the fence has been reassembled, the trash compactor will be moved, and its old concrete pad will be removed. Contact Mark Richardson, 3456.
BUILDING 11 REMODEL
Several project tasks in and outside of Building 11 are going strong. Hyland Construction has completed the walls and painting at the new student support department offices, and the final step will be installing the new floor covering. The Art History classroom is close to being complete. After a final coat of paint and the concrete floor has been waxed, LCC staff can start installing the classroom furniture and electronics. Final touches inside the Art gallery are expected to be completed this week and final floor preparation will begin. This building is expected to be completed around September 16. Contact Mark Richardson, 3456.
TRACK AND INNER FIELD RESURFACING PROJECT
Delta Construction, in a joint effort with Atlas, was scheduled to start working on the track resurfacing on August 29. During this time, the track will remain closed and no one will be allowed its surface. After the coating has been applied, the entire track will be restriped with a fresh coat of paint. As a reminder, the paint and coatings used for this process are expected to give off strong odors in the immediate and possibly surrounding areas. Walkers that are sensitive to strong odors are encouraged to alter their walking route away from the area for the next few weeks until the project is completed. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS PROJECT
Contractor continues to pour Level 1 concrete columns and shear walls. There are three more shear walls to pour on Level 1. The first slab on grade pour has been done at the northeast corner of the building. The next slab pour is scheduled for Tuesday, August 30; it will be at the north side of the building. Three geothermal manifolds have been completed and tested. The mechanical, electrical and plumbing lines below slab are nearly complete at the north side of the building.
There is a lot of work going on in a very tight site. Workers, vehicles, and material vie for enough space to quickly perform their assigned tasks. Take a moment to imagine how to keep carpenters, earth movers, electricians, concrete trucks, plumbers, and stacks of materials from getting in the way and obstructing work from being done. Efficient site management is under appreciated but absolutely necessary to meet the construction schedule. Happily, the contractor is managing the site very well. Watch the Downtown Campus construction - updated hourly between 8 a.m. and 8 p.m. at http://2011sitearchive.lanecc.edu/dc/video.html Contact Bob Mention, 5747.
August 23, 2011
BUILDING 10 REMODEL
Crews are working to complete the building’s interior. The completion date for Building 10 is now being projected at September 15. Lane’s Housekeeping staff will complete floor preparation and sealing inside the building beginning Saturday, August 27. While this work is being completed, access inside the rooms will not be allowed. Office furnishings are scheduled to arrive on site on August 29 and crews will begin assembly and installation on August 30. The first week of September, Hyland Construction will remove its construction trailers and clean up debris on the outside of the building. Be informed that when this operation begins, the site will become dusty around the outside of the building until the cleanup work is complete and the dust is able to settle. Contact Mark Richardson, 3456.
BUILDING 11 REMODEL
The task of replacing the worn-out aged roof is almost complete. Umpqua Roofing and Smith’s Sheet Metal have teamed up to make sure this project is successful. On the first level, Hyland Construction has completed replacing some of the interior finishes and lighting fixtures. This project is expected to be completed the week of September 12. Contact Mark Richardson, 3456.
TRACK AND INNER FIELD RESURFACING PROJECT
Crews have begun cleaning in preparation for the track restripe and resurface work. During the week of August 29, crews will be completing a final cleaning and then will apply a spray sealer on the track surface. This sealer is used to provide a better wear surface and allows the material to last longer. This work is expected to take two weeks to complete. During this time, the track, inner field, and the surrounding areas are closed to all. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS PROJECT
Design: Architects continue to respond to questions, changes and submittals as construction proceeds.
Bids: Contractor is still reviewing subcontractor bids for Bid Package No. 5.
Construction: Crews have poured about 90 percent of the foundations and are pouring level one concrete columns. Several shear walls have been poured and more will be poured this week. Note: Shear walls are walls designed to resist horizontal forces, e.g. wind, from pushing a structure over. Concrete slab on grade pours are scheduled to begin late this week.
Watch the Downtown Campus construction webcam, updated hourly between 8 a.m. and 8 p.m., at http://2011sitearchive.lanecc.edu/dc/video.html Contact Bob Mention, 5747.
August 16, 2011
BUILDING 10 REMODEL
Building 10 is now in the beginning of the move-in phase and subcontractors hired by Lane begin installing classroom furnishings this week. Many unforeseen tasks caused this project to lag behind schedule in some areas, but with a combination of determination and overtime, Hyland has recovered most of their lost time and is expected to have the building open by the start of fall term. Painting, floor covering, doors, and cabinets are now the task at hand. The remaining six weeks of the project will be fast pace for both Hyland Construction and Lane staff, so traffic in and around the project site is expected to be heavy at times. Contact Mark Richardson, 3456.
BUILDING 11 REMODEL
Last minute changes in Building 11 have caused work to fall behind schedule, requiring crews to work overtime to complete the project in time. Most of the interior work has been completed for the remodeled areas and painting is scheduled to begin this week. Installation of the new roof is on schedule and is expected to be completed by August 30. Contact Mark Richardson, 3456.
BUILDINGS 10 AND 11 CONSTRUCTION SAFETY REQUIREMENTS
Buildings 10 and 11 will remain closed until the projects are complete. No access inside the fenced area is permitted, unless accompanied by a member of the bond staff. These rules are in place to ensure proper safety for everyone entering these buildings. For those interested in requesting a tour, please remember that safety equipment must be worn at all times. A limited quantity of safety equipment is available and will be provided by FMP, however, due to a limited number of hard hats on hand, Bond staff encourage those who can to bring their own hard hats for any scheduled tour. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS PROJECT
Design: The architects continue to respond to queries from the contractors, material suppliers and others as construction proceeds.
Bids: Bids for the work noted in Bid Package No. 5 were received last Thursday, August 11. A lot of bids were submitted. The contractor has to review each bid to ensure its scope of work; this will be time consuming since so many bids were submitted.
Construction: Work on the shallow utility lines is proceeding, the geo-wells are being connected, and reinforced concrete columns and walls at the first floor level are being formed and poured. Watch Downtown Campus construction on our web cam, updated hourly between 8 a.m. and 8 p.m. at http://2011sitearchive.lanecc.edu/dc/video.html Contact Bob Mention, 5747.
August 9, 2011
BUILDINGS 10 AND 11 REMODEL
Bond moving crews and art department staff are moving equipment from Building 11 into the remodeled Building 10. This is a huge milestone for the project and the Advanced Technology and Art department as the completely remodeled building transforms into classroom spaces and more that will be ready for students this year. Transformation inside Building 11 is now picking up speed in all areas of the building. All interior walls in the new Specialized Support Services (SSS) area are finished and crews are now completing the final coat of interior paint. Hyland Construction is on the site long hours along with their subcontractors in both buildings to bring this project to completion. Contact Mark Richardson, 3456.
August 2, 2011
DOWNTOWN CAMPUS PROJECT
Design: Architects have completed Addendum 1 to Bid Package No. 5 and it's been sent to the contractor. The contractor will review the addendum and decide if the bid period needs to be extended for a few days. Robertson Sherwood Architects has been hired by the city to design the Public Safety Station interior space in the Downtown Campus.
Construction: Contractor is working on foundations. This work includes excavation, forming of foundation mats and pads, placing steel reinforcing bars, pouring concrete and removing forms. Contractor is also excavating trenches and laying utility (electrical and waste) lines beneath the ground floor slab. Contact: Bob Mention, 5747.
July 26, 2011
BUILDING 10
Painting crews have completed the second-level classrooms and are now installing cabinets and floor covering. This is the final step in converting the open space into well-designed state of the art classrooms. The area has open ceilings that contain most of the original design of the building. On the first floor of the building, crews are working hard to complete painting. Once complete, Lane staff will begin installing equipment for the Art Department, which will transform the once open space into a new first class learning environment. Contact Mark Richardson, 3456.
July 19, 2011
BUILDING 10
This project is progressing quickly. Hyland Construction is working several crews on overtime to achieve their expected completion date in September. The second floor is nearing completion. Painting crews have completed their work inside the classrooms on the second level, and cabinets will be installed this week. Then the focus will shift to completing the painting and preparing areas for the installation of cabinets on the first floor. Contact Mark Richardson, 3456.
July 12, 2011
BUILDINGS 10 AND 11 REMODELS
Buildings 10 and 11 will remain closed until the construction projects are complete. Unless accompanied by a member of the bond staff, no access inside the fenced area is permitted. Access modification into the campus on the South side of Building 10 is nearly complete. The steep ramp area is closed and a new ADA access ramp has opened. New steps are being formed replacing the steep ramp. Between buildings 10 and 11, final concrete placement is complete. On Friday, July 15, sections of the north parking lot N will be closed and will reopen on Wednesday, July 20. This closure is needed to allow for crane access to the project site. On Monday, July 18, the crane will begin lifting large pieces of equipment and placing them on the roof of Building 10. Contact Mark Richardson, 3456.
July 5, 2011
BUILDINGS 10 AND 11 CONSTRUCTION SAFETY REQUIREMENTS
Buildings 10 and 11 will remain closed until the construction projects are complete. No access inside the fenced area is permitted, unless accompanied by a member of the bond staff. These rules are in place to ensure proper safety for everyone entering these buildings. For those interested in requesting a tour, please remember that safety equipment must be worn at all times. A limited quantity of safety equipment is available and will be provided by FMP, however, due to a limited number of hard hats on hand, Bond staff encourage those who can to bring their own hard hats for any scheduled tour. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS PROJECT
Design: The architects will complete the construction documents on July 11 as scheduled. Congratulations to the design team (architects, engineers and other consultants) on completing this massive task on schedule. The sheer volume of the drawings and specifications is huge.
Construction: Thirty-nine of the geo-thermal wells have been drilled. The remaining 11 wells are scheduled to be completed by the end of this week. The tower crane base has been installed and the footing is scheduled to be poured this week with installation of the crane to follow next week. Piping and conduit installation and excavation for the structural footings will begin this week. The layout for the underground MEP (mechanical, electrical and plumbing) utilities has begun.
Other: The contractor has been asked to present a guaranteed maximum price (GMP) for the project to the Board for consideration at its July meeting.
Finally, congratulations to everyone at LCC who has been involved and assisted with getting this project to this milestone. This is the largest single construction project under undertaken by the college since its beginning. Contact Bob Mention, 5747.
June 28, 2011
DOWNTOWN CAMPUS BUILDING
Design work: Architects and engineers are racing to complete the construction documents (drawings and specifications) for the last major package of bids (Bid Package No. 5) by Friday, July 11th. Achieving this goal will keep the project on schedule.
Construction work: The geo-thermal well casings have been completed. The well driller has mobilized a second drill rig to complete the remaining wells on schedule. The rain water storage tanks have been installed. The mechanical, electrical and plumbing subcontractors will mobilize and begin installing underground conduit and piping at the end of the week. The contractor will put the construction documents for Bid Package No. 5 out for bids shortly after they receive the complete documents in mid-July.
Other work: The entire team of consultants (Project Manager, Architects, Engineers and CMGC) have been reviewing the results of Early Bid Package No. 4 and updating the estimated cost of the remaining work. The results were presented to the college management team at a meeting last Thursday. The result is that the project remains within budget. Contact Bob Mention, x5747
April 12, 2011
BUILDINGS 10 AND 11 REMODEL
Construction work on the inside of Building 10 is scheduled to continue and will be increasing. Crews are installing large duct work and roof supports for the new HVAC equipment. Interior wall construction began last week and is expected to continue throughout the remainder of the project. During activities such as this, odd smells and loud noises throughout the day are expected. A separate project to relocate the trash compactor is scheduled to start with-in the next two weeks. This will cause further traffic congestion on the east side of the Building 10 project. Lane’s project management staff requests that traffic be limited in this area to student activities and deliveries only. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
The jet grouting subcontractor has mobilized on site and drilled a test hole last Friday. If the results from the test hole meet standards, the jet grouting should begin today. The grouting process is scheduled to be completed by April 26. Amendment two was executed. It includes several tasks among which are demolition of existing asphalt, filing the pit with structural fill (crushed rock), and drilling Geo-wells. The management team meets with the design team to discuss a variety of issues on Thursday, April 14. The CM/GC expects to set up its project office in an existing building on the north side of the alley. Contact Bob Mention, 5747.
April 5, 2011
DOWNTOWN CAMPUS BUILDING
In summary, the design development phase has been completed, the project is within budget and on schedule, and site preparation activities are planned to start this week.
Completion of design development phase means that all of the major building components have been identified and addressed in a satisfactory manner. The Construction Document phase comes next. This is where the architects and engineers draw up the details of how the contractor is to construct the building and specify what materials, equipment and products are to be incorporated into the building. The contract documents for the site preparation activities have been completed, bid and subcontractors have been identified.
The site preparation activities include soil stabilization by the jet-grouting method, demolition of the existing asphalt paving, filling the pit with compacted crushed rock, installing the rain-water storage tank, drilling the geo-wells, and miscellaneous site utility work. Contact Bob Mention, 5747.
March 29, 2011
BUILDINGS 10 AND 11 REMODEL
Concrete placements continue today, March 29. This is the last of the large concrete placement for this project. The grueling task of installing the HVAC ducts will start on Wednesday, March 30 and will continue throughout the remainder of the project. With this task brings frequent deliveries to the project, odd smells, and loud echoing noises; none of which is expected to be harmful or consistent throughout the day. Following installation of the HVAC ducts is steel wall framing. This work is expected to create the same smells and noises as encountered during the installation of the duct work. Equipment used for the installation of the wall framing is a powder operated nail gun used for setting nails in concrete. Loud popping noises are normal when using this equipment. Contact Mark Richardson, 3456.
March 22, 2011
BUILDINGS 4 AND 5 ADDITION AND REMODEL
The remaining tasks to close out the projects in Buildings 4 and 5 will be completed this week. During spring break, Lease Crutcher Lewis will have construction crews working in all areas of Buildings 4 and 5, and locker rooms and showers will be closed. Contact Mark Richardson, 3456.
BUILDINGS 10 AND 11 REMODEL
The four major concrete placements for the Building 10 project begin this week and are scheduled to be completed by Tuesday, March 29. All areas around Building 10 including between Buildings 9 and 10, 10 and 12, and the test cells will have large diesel equipment on location from 5 a.m.-7 p.m. Monday, March 21 and Tuesday, March 22. The open area between Buildings 10 and 12 will have restricted access at times and using an alternate access route to the center of campus is encouraged. The final concrete placement for the project is scheduled for 5 a.m.-7 p.m., Monday, March 28 and Tuesday, March 29. This final concrete placement will not block access to the campus, and will be contained inside the immediate construction area. Truck traffic is still expected to be heavy and caution will be encouraged when using the north parking lot. As a reminder, Hyland Construction will be working on the heating water lines, which means there will be no heat in buildings 4, 5, 6, 7, 11, and 30 starting 6 a.m. on Wednesday, March 23 through the day and possibly, to noon on Thursday, March 24. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
The management team met with the architects and contractor last Thursday, March 17, to discuss several issues, e.g. the furnishings layout in the student interaction area between the CML and the classrooms on the first floor, the type and location of window coverings, and the question of operating the windows manually or with motorized options. The next management team meeting is scheduled for March 31. Bids for the first work package (soil stabilization) came in on target and mobilization for that work is scheduled to begin this week. Bids for the second work package (site civil and utilities, geothermal well drilling, and public right of way improvements) are due on March 22. That work is scheduled to begin with well drilling in mid-April. Contact Bob Mention, 5747.
March 15, 2011
DOWNTOWN CAMPUS BUILDING
Hooray! The groundbreaking ceremony was very successful and construction is about to begin! The first work package for the Downtown Campus building includes improving some subsurface ground conditions. Bids for the package have been submitted by subcontractors and the college has approved awarding a contract for the work. The successful subcontractor will mobilize on site and commence work in the near future. Meanwhile, the second work package is out to bid. The second package concerns site demolition, foundations, geo-wells and structural fill. Bids for the second package are due late March.
The "fast-tracking" process has started. Basically, fast-tracking means that after the overall design of the building has been established, the architects and contractor divide the overall design into a logical sequence of work packages, i.e., site preparation and foundations, structural frame, exterior envelope, interiors, etc. Then, as soon as the architects have completed the detail drawings and specifications for the first work package (for example site and foundations) it can be bid and, if the bids are acceptable, construction can begin. This process permits construction to start while the architects are working to complete the drawings and specs on the following work package. Employing the fast-track process is the most economical and promising project delivery system to complete the project within the time schedule. Contact Bob Mention, 5747.
March 8, 2011
BUILDINGS 10 AND 11 REMODEL
Hyland Construction is operating on schedule and is expected to complete the project by August 2011. Steel construction inside the building is complete and the placement of the second floor concrete begins this week which will take two weeks to complete. Mechanical and electrical contractors have increased work force and production has started on the installation of infrastructure for the project. Contact Mark Richardson, 3456.
BUILDING AUTOMATION SYSTEM
Building Automation System (BAS) Phase 1 project commissioning efforts continue to be a top priority. BAS Phase 1 system commissioning is expected to close mid March. On Wednesday, March 2 Lane staff and technicians from TraneOregon began what has resulted in a successful testing of the BAS alarming and mass messaging capacity. Tests for the trending equipment performance were finalized and set up on February 25. Next, the commissioning goals include verifying graphics and continuing to test the equipment scheduling programming.
Purchasing for contracted services is in progress for Building 19 controls and programming to address long term ongoing issues discovered while working in the BAS equipment level network at the CML. Additional controls work planning continues for the Workforce Training areas. Several locations in building 19 are being operated manually and will continue to be until these issues have been addressed.
BAS Phase 1 upgrades work has involved coordinating staff and student concerns in multiple buildings on main campus with two control contractors, the college energy analyst, and Facilities’ Trades staff. Lane staff continues to track affected areas with the latest BAS trending tools. To report any HVAC issues or concerns to the Facilities office, please e-mail facilitiesoffice@lanecc.edu or call extension 5216 as work to complete the system integration process is finalized. Contact Anna Scott, 5805
DOWNTOWN CAMPUS BUILDING
Several noteworthy events happened last week: A meeting with the neighbors who live or work around the project site, the Groundbreaking ceremony, and a "make-up" meeting of the management team and project consultants.
The meeting with the neighbors was attended by people who live nearby and others who own or represent nearby businesses. The meeting was convened to give the neighbors some general information about the building, its occupants and use, and to assure the neighbors that the college and contractor will do everything possible to minimize disruption caused by the operation of the building and/or its construction. Helen Garrett and Brett Rowlett presented information about the operation and schedule of the building and Andy Dykeman (the contractor's Superintendent) spoke about the project schedule and the impact of construction activities on the adjacent streets, Broadway alley, and sidewalks. He gave everyone his contact information and urged them to let him know if they experienced any disruption.
An overflow audience attended the Groundbreaking ceremony on Friday, March 4. Everyone was excited about the project itself and the prospect of its playing a pivotal role in rejuvenating the downtown. The theme of the ceremony was that it takes all of us, working together, to make this project a success.
The management team heard proposals from the architects to make various refinements to the academic building (such as manually operated windows or automatic operators) and to make adjustments to the student housing building to better accommodate occupants. Contact Bob Mention, 5747.
March 1, 2011
BUILDINGS 10 AND 11 REMODEL
Hyland Construction is operating on a tight schedule and is expected to complete the project as scheduled by August 2011. Steel construction inside the building will be complete March 2. Mechanical and electrical contractors will increase work force and production beginning this week and will start installation of the infrastructure for the project. Kicking off this part of the project is exciting and progress will be easily identified as the project moves closer to completion. First and second floor concrete placements are scheduled in March and will take two weeks to complete. Contact: Mark Richardson, 3456.
BUILDING AUTOMATION SYSTEM
Building Automation System (BAS) Phase 1 project commissioning efforts are continuing and expected to close mid March. Lane staff, SOLARC, and technicians from TraneOregon met during the week of February 22-25 to verify the project's data migration and trending capabilities. Due to the snow day Thursday, testing of the BAS alarming and staff messaging capacity was scheduled and will occur on Wednesday, March 2. Please be aware that some minor interruptions to building equipment may occur as alarm conditions are simulated in order to test the system. Next, commissioning goals include verifying graphics and continued testing of the equipment scheduling programming. Contact: Anna Scott, 5805.
ENERGY EFFIEICNCY AND RENEWABLE ENERGY INCENTIVES
The Sustainability office is in the process of rounding up more than $500,000 in Oregon state tax credits, utility incentives, and grants for their work in conserving electricity and natural gas in Lane Community College's new buildings and renovation projects. The process for incentive/grant/rebate collection is 50 percent complete. Approximately $300,000 of this funding comes from the Oregon Department of Energy - Business Energy Tax Credit program for energy conservation and renewable energy generation at the newly constructed Health and Wellness Center and the Solar Station. Over $90,000 comes from the Eugene Water and Electric Board's energy efficiency rebates for lighting upgrades in Buildings 2, 4, 5, and 10, energy conservation measures in the Health and Wellness Center and the Native American Longhouse, and solar electric generation at the solar station. This is in addition to EWEB's $100,000 Green Power Grant awarded to the college for the solar station project. The college plans to receive approximately $31,000 from the Energy Trust of Oregon for its work in reducing natural gas usage at Building 5 and the Laundry facilities by installing a solar thermal array atop the Health and Wellness Center and installing efficient natural gas appliances in the Native American Longhouse and the Building 10 renovation.
On Monday, February 28, TraneOregon will be working at the Center building to help Lane staff resolve recently identified equipment level communications issues.
Work plans are in progress for Building 19 controls and programming to continue work at the CML and Workforce Training areas in March. Primarily this is work to address long term ongoing issues discovered in the BAS equipment level network in Building 19 that has resulted in temperature concerns. Several locations in Building 19 are being operated manually and will continue to be until these issues have been addressed.
BAS Phase 1 upgrades work has involved coordinating staff and student concerns in multiple buildings on the main campus with two control contractors, college energy analyst, and Facilities trade staff. FMP continues to track affected areas with the latest BAS trending tools. Please continue to report any HVAC issues or concerns to the Facilities office by submitting an e-mail to facilitiesoffice@lanecc.edu or by calling extension 5216 as work to complete the system integration process is finalized. For questions, please contact Anna Scott, 5805
COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEM
FMP has researched and is in the process of selecting a new computerized maintenance management system (CMMS) to replace MPulse. Staff training and implementation of the new system is planned to begin in June. Contact: Angela Fazio, 3428.
DOWNTOWN CAMPUS BUILDING
The snow-caused campus closure last Thursday preventing the project design/management team from meeting with the college managers. The meeting is to be rescheduled. The architects have completed the design development phase of the project and have moved into the contract documents phase.
The contractor has issued bid documents for stabilizing the soil on a portion of the site. The bids are due March 8. Actual work to stabilize the soil will not begin until after the college approves the bid. The contractor plans to issue another set of bid documents next week. This set will be for site demolition, geo-wells and structural fill.
The official Downtown Campus building groundbreaking ceremony is scheduled for March 4. Contact Bob Mention, 5747.
February 22, 2011
DOWNTOWN CAMPUS BUILDING
The project contractor, Lease Crutcher Lewis (LCL), started work mid-January. Since then, LCL has been working with the design team to provide constructability reviews, time schedules and cost estimates. Construction cost estimates are still above budget and the design team continues to work with the contractor to find opportunities to bring them into budget.
The first physical work needing to be done on the project is to stabilize the subsurface soil at the west side of the pit. This will be done by a process called "Jet Grouting." The process involves injecting a cementitious grout into ground below the surface. This will reinforce and stabilize the soil. The contractor let contract documents for doing this work out for bid on February 17. Bids are due on March 4. Physical work will commence shortly thereafter. Contact Bob Mention, 5747.
February 15, 2011
BUILDINGS 10 AND 11 REMODEL
Steel construction has started in the interior of building 10. Much of the steel connections are bolted together and will not require welding equipment to be running. However, setting steel into place can be noisy at times when fitting pieces together. Most of the interior and exterior block walls are complete. Construction is expected to continue this week on the west side of building 10. Concrete placement is scheduled for Friday, February 18, and will be pumped into place with equipment staged on the south side of the construction fence in order to prevent trucks from running between buildings 10 and 11. Access between buildings 10 and 12 will be congested but will remain open for central campus access.
DOWNTOWN CAMPUS BUILDING
Planning for the ground breaking ceremony is moving ahead and all the parts that will come together for the March 4 event. The contractor will begin mobilizing on the site shortly after March 4 and plans are to issue the first bid package on or about February 21. The first bid package will be for soil grouting and it is a large contract. The bids will be due later in March and the contractor will need to get the successful subcontractor started as soon as possible. Consequently, the Board of Education authorized President Spilde to award the contract for "soil grouting" to the lowest qualified bidder instead of waiting until the April board meeting.
The architects and engineers continue to reconcile the estimates and refine the design to meet the schedule of completing the design development phase by March 1. Contact Bob Mention, 5747
February 8, 2011
BUILDING AUTOMATION SYSTEM (BAS)
Lane staff continues to track affected areas with the latest BAS trending tools. Please continue to report any HVAC issues or concerns to the Facilities office at facilitiesoffice@lanecc.edu or call extension 5216 as work to complete the system integration process is finalized. Contact Anna Scott, 5805
DOWNTOWN CAMPUS BUILDING
The design team continues to work on developing the design of the interior and exterior of the building and the cost estimators continue to refine their estimates. The college has hired a consultant to assist the architects to minimize "accessibility" issues in the building design. The design team is scheduled to make a status report to the management team on Thursday, February 10. Contact Bob Mention, 5747.
February 1, 2011
BUILDINGS 10 AND 11 REMODELS
Masonry work for the structure is almost complete. Excavation work continues between buildings 10 and 11. While excavating last week, contractors discovered clogged up underground drainpipes that will have to be removed and replaced. This activity will extend the underground work in that area for another week. Although the use of bio-diesel powered equipment in this area will be reduced, it is recommended to keep the doors closed on both floors of building 11 as much as possible for the remaining duration of the project.
Structural steel for building 10 is scheduled for delivery beginning this week. The delivery is expected to cause some traffic congestion on the east side of building 10 during the times the trucks are being unloaded. Staff and students are encouraged to use the campus entrance between buildings 10 and 12 if parking in the east lots. Contact Mark Richardson, 3456.
BUILDING AUTOMATION SYSTEM
During the week of January 24-28, technicians from TraneOregon, Controls Contractor Inc., and Lane staff worked at building 19 on the previous system programming and Building Automation System (BAS) equipment level network issues. Building 19 controls and programming work will continue this week. Primarily this is work to address issues discovered in the previous BAS equipment level network in building 19 that has resulted in temperature variation concerns. Several locations in building 19 are being operated manually and will continue to operate in manual mode until these issues have been addressed.
On Monday, January 24, Lane staff and BAS Phase 1 commissioning agent SOLARC received more intensive training from TraneOregon to improve skills in using the Niagara AX trending tools. Due to the great strides made in the last couple of weeks to resolve the trending, scheduling , and alarming issues with the BAS Phase 1 project as well as resolutions to equipment level communications issues, SOLARC can now begin to verify the project goals and complete commissioning of the BAS Phase 1 project.
BAS Phase 1 upgrades work has involved coordinating staff and students’ concerns in multiple buildings on the main campus with two control contractors, the college energy analyst and facilities trades’ staff. Lane staff continues to track affected areas with the latest BAS trending tools. Please continue to report any HVAC issues or concerns to the Facilities office at facilitiesoffice@lanecc.edu or call extension 5216 as work to complete the system integration process is finalized. Contact Anna Scott, 5805.
DOWNTOWN CAMPUS BUILDING
The CMGC and an independent cost estimator continue to work on revising cost estimates. A value engineering process has started that should help identify changes that can be made to reduce costs while maintaining the overall instructional programming of the project. Cost revisions are fairly common on large projects during the design development process. The contractor is preparing to occupy the site and mobilize for work on March 1. The official groundbreaking ceremony is scheduled for March 4. Contact Bob Mention, 5747.
January 25, 2011
BUILDING 5 REMODEL AND ADDITION
LCL continues to complete punch list items inside the dance studio and Fitness Education Center addition. Designers and FMP have developed a plan to work with a contractor to make repairs to the HVAC controls. The repairs are scheduled to start this week and are not expected to cause disruption to class schedules. Contact Mark Richardson, 3456.
BUILDINGS 10 AND 11 REMODELS
Construction of the concrete entrance ramp has started and this work is expected to continue until January 31. FMP staff requests that students and staff keep the doors on the outside of the building on both floors closed as much as possible. This will help prevent odors, dust, and noise from entering the building during the day. Contact Mark Richardson, 3456.
BUILDING AUTOMATION SYSTEM
Technicians from TraneOregon, Controls Contractor Inc. worked four days on site from January 17-20 to address issues discovered in the previous Building Automation System (BAS) equipment level network in the Center building. TraneOregon has found and verified several existing equipment level network communications issues that have affected temperature caused concern in the Center building. Working with Lane staff, the contractors have made great strides to resolve the Center building equipment level communications and temperature issues.
Later this week, TraneOregon and Lane staff will be working on building 19 on the previous system programming and BAS equipment level network issues uncovered. Several locations on campus are being operated manually and will continue to be until these issues have been addressed.
Work also continues with the commissioning process of the building equipment in the new addition to Building 5. BAS Phase 1 upgrades work has involved coordinating staff and students concerns in multiple buildings on the main campus with two control contractors, college energy analyst, and facilities trades staff. Lane staff continues to track affected areas with the latest BAS trending tools. Please continue to report any HVAC issues or concerns to the Facilities office at facilitiesoffice@lanecc.edu or call 5216, as work to complete the system integration process is finalized. Contact Anna Scott, 5805.
ENERGY CONSERVATION - STUDENT FIELD WORK
On Tuesday, January 18 Energy Management students from the Commercial Energy Analysis class studied existing building conditions in Buildings 16 and 17 continuing a tradition of using the college’s facilities as a learning lab. Students and their instructor, Suzanne Marinello, avoided disrupting classes and staff during their visits. Please be aware that from time to time students may be "in the field" to look at existing classroom, office, and restroom areas as a part of the learning process in conducting energy audits. Facilities staff assists the Commercial Energy Analysis class by providing access to architectural drawings, building energy information, and access to building equipment. Contact Anna Scott, 5805.
DOWNTOWN CAMPUS BUILDING
Work on the project is racing ahead to meet schedule. Among the most important things happening this week is a meeting scheduled for Thursday, January 27. The Project Manager, Design Team and Contractor will present the latest plans and construction estimates to the project management team. Contact Bob Mention, 5747.
January 18, 2011
BUILDING 5 REMODEL AND ADDITION
The addition and remodeling in building five projects are complete. Some heating and ventilation issues in certain areas have been reported and a collaborated effort with FMP/bond staff and engineers continue the tedious work to locate and identify the source of the problem and then priority work to correct the issue will be performed. Contact Mark Richardson, 3456.
BUILDINGS 10 AND 11 REMODELS
Construction of the interior walls and stair cases inside the building has begun. Excavation crews will be moving to the west side of the project site between Buildings 10 and 11 soon to start working on the new concrete ramp and access to Building 10. Steel for the interior of the building is expected to start arriving the first week of February. With this activity, additional equipment and noise will be introduced into the area. On Friday, January 14, construction of the new entry began between Buildings 10 and 11. The contractor is removing large amounts of dirt from the area and this work will continue for up to three weeks. Lane is asking students and staff in Building 11 to keep the doors closed as much as possible on both floors of the entire east side of the building in order to help prevent noise and various odors from entering the building. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
At its January meeting the Board of Education approved a financing plan to and awarded a contract to the firm of Lease Crutcher Lewis (LCL) to provide Construction Management/General Construction services. LCL provided CM/GC services for the recently completed Health and Wellness Center. The management team discussed a wide range of topics at its last meeting: 50 percent Design Development (DD) drawings, a schedule update, the process update, the status of sustainability incentives, a soils/geotech report, good faith effort to subcontract with women and minority owned businesses and emerging small businesses, comfort criteria, and summer classroom use. Work in all of those areas continues. LCL is preparing a construction cost estimate based on the 50 percent DD drawings and is scheduled to present the estimate to the management team at a meeting on January 27. Contact Bob Mention, 5747.
January 11, 2011
BUILDING 5 REMODEL
Construction of the building five addition project is complete and the general contractor is on the site completing final punch list items of the project. Other repairs to the HVAC system that were discovered during the construction phase of the project will be ongoing over the next 45 days. This work is expected to help to improve air flow in the second level of the building. Punch list items are expected to last for another 30 days and is work is expected to be scheduled around class schedules to minimize disruption. Painting and floor sealing will be scheduled for after hours and weekends. Contact Mark Richardson, 3456.
BUILDINGS 10 AND 11 REMODEL
Hyland Construction has completed the underground plumbing and most of the foundation system for the project. Footing installation on the south side of building 10 is scheduled to start in two weeks. This activity will require large equipment to complete the work. Much of the shear wall for the building has started. This work is expected to be noisy at times. The general contractor is working around program class schedules to complete work activity known to cause the most noise to minimize disruption. Contact Mark Richardson, 3456.
The project is in the design development phase which means in general that the design team (architects and engineers) is working on details. On the architectural side these include such things as the design of counters in department offices, cabinets in workrooms and how doors and windows integrate with walls. The engineers are working on such things as getting electrical power and communication components into every room and connecting the equipment proposed for the Energy Management program lab. The mid-point of this phase is scheduled to be reached in the next week or so which will trigger another cost estimate. The Board of Education is expected to award a contract for CM/GC services at its January meeting. Adding a contractor to the team will bring another dimension to the project. The CM/GC will provide services such as constructability reviews, value engineering and cost estimating to the project. The Management Team is scheduled to meet Thursday, January 13 to review the work accomplished by the design team since late December. Contact Bob Mention, 5747.
Delta Construction and their subcontractors have been on the site the last few days working on completing punch list and warranty items. Some of the outstanding tasks are weather related and cannot be completed until later this year. Contact Mark Richardson, 3456.
January 4, 2011
BUILDING 5 REMODEL
Construction of the building five addition project is complete and the general contractor is on the site completing final punch list items of the project. Other repairs to the HVAC system that were discovered during the construction phase of the project will be ongoing over the next 45 days. This work is expected to help to improve air flow in the second level of the building. Punch list items are expected to last for another 30 days and is work is expected to be scheduled around class schedules to minimize disruption. Painting and floor sealing will be scheduled for after hours and weekends. Contact Mark Richardson, 3456.
Hyland Construction has completed the underground plumbing and most of the foundation system for the project. Footing installation on the south side of building 10 is scheduled to start in two weeks. This activity will require large equipment to complete the work. Much of the shear wall for the building has started. This work is expected to be noisy at times. The general contractor is working around program class schedules to complete work activity known to cause the most noise to minimize disruption. Contact Mark Richardson, 3456.
The project is in the design development phase which means in general that the design team (architects and engineers) is working on details. On the architectural side these include such things as the design of counters in department offices, cabinets in workrooms and how doors and windows integrate with walls. The engineers are working on such things as getting electrical power and communication components into every room and connecting the equipment proposed for the Energy Management program lab. The mid-point of this phase is scheduled to be reached in the next week or so which will trigger another cost estimate. The Board of Education is expected to award a contract for CM/GC services at its January meeting. Adding a contractor to the team will bring another dimension to the project. The CM/GC will provide services such as constructability reviews, value engineering and cost estimating to the project. The Management Team is scheduled to meet Thursday, January 13 to review the work accomplished by the design team since late December. Contact Bob Mention, 5747.
TRACK AND SOCCER BOWL
Delta Construction and their subcontractors have been on the site the last few days working on completing punch list and warranty items. Some of the outstanding tasks are weather related and cannot be completed until later this year. Contact Mark Richardson, 3456.
December 15, 2010
DOWNTOWN CAMPUS BUILDING
A snapshot of some of the things that are currently underway:
The architects/engineers and cost estimator continue to work on aligning the design with the budget.
The Board of Education approved adding a fifth floor to the student housing which reduces the cost per bed and thus reduces overall ongoing costs.
Five proposals were received in response to the Request for Proposals for CM/GC services. The selection committee is processing the proposals.
The leads and others from each of the programs that will occupy the academic building will meet with the architects this week to discuss what furniture, equipment and casework is needed in each of the rooms to be occupied.
Contact: Bob Mention, 5747.
December 7, 2010
BUILDING 4 IEQ REMODEL
Demolition began Monday, December 6 on the Building 4, Rm. 107, Dental Lab remodel. All contents of the room will be cleaned and removed to storage. Flooring and most cabinets in this room will be replaced. All mold and asbestos containing materials will be abated. The lab's exhaust system will be upgraded to help ensure a clean and safe work environment. Ceiling tiles will be cleaned or replaced in this room and throughout the entire dental lab workspace. This project will also include flooring replacement in the adjacent reception area and offices. Work will be completed the week of December 27 with offices available to staff on December 28. Contact Brian McMurray, 5829.
BUILDING 5 REMODEL AND ADDITION
Construction continues to push forward in both areas of the building 5 additions. Multipurpose addition will allow for greater flexibility and will be furnished with new equipment, a better sound system, and a lot of natural lighting and ventilation. The second half of the new addition is a dance studio that will be a highlight of new classroom standards here at Lane. Over winter break, Buildings 4 and 5 are scheduled to go through one more fast paced renovation that is expected to cause some noise from construction activities. The fitness center will be open with very limited access and the locker rooms will be closed. Construction of the addition and fast paced remodeling project is scheduled to be completed by January 2, 2011. Contact Mark Richardson, 3456.
BUILDING 10 AND 11 REMODEL
Hyland Construction is working through some issue with rock to complete the underground plumbing and new wall footings for the project. Wall construction is scheduled to start the week of December 6 and will be a mile stone for the project. Following wall construction, the steel frame will be erected to support the second floor. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
The three events scheduled in the CML on December 6 went well. The architects presented the schematic designs to the steering committee, the "open house" for everyone to review the designs, and the meeting with the management team all happened on that day.
The first draft of the construction cost estimate has been completed and the design team is answering questions and clarifying issues raised by the estimators. The design team is confident that the final version of the estimate will meet the budget.
Proposals in response to RFP 10/11-04 CMGC services must be submitted by 2 p.m., Tuesday, December 7. The selection committee plans to get a recommendation to the board at its January meeting. Contact Bob Mention, 5747.
November 30, 2010
DOWNTOWN CAMPUS MEETINGS NOTICE
Design work on the Downtown Campus project is moving very quickly. Four important upcoming events are scheduled:
- 1. Schematic Design presentation. The Steering Committee is invited to the Center for Meeting and Learning, Room 102, on Monday, Dec. 6, from 1-2 p.m. The architects will present the schematic design for the building and respond to your questions and comments.
- 2. All college personnel are invited to the Center for Meeting and Learning, Room 102, between 2-3 p.m. on Monday, Dec. 6, to review the schematic design of the Downtown Campus building. This is your chance to catch up on the status of the project.
- 3. The Management Team is invited to meet with the architects in the Center for Meeting and Learning, Room 102 from 3-5 p.m. on Monday, Dec. 6 to discuss recommendations for Value Engineering.
- 4. Design Development meetings: The architects will meet with the leads (and others) of the occupying programs at various times on Tuesday and Wednesday, Dec. 14 and 15, in Building 7, Room 212K. The purpose of the meetings is to tell the architects what casework you need in the rooms you will be occupying. Contact: Bob Mention, 5747.
November 16, 2010
BUILDING 5 REMODEL AND ADDITION
Construction of the FEC addition and dance studio is scheduled to be completed on Dec. 15. Exterior site work began Monday, Nov. 8. This activity will require diesel powered equipment to be brought back to the site to remove areas of the landscaping on the east side of Building 5. Contact Mark Richardson, 3456.
BUILDING 10 AND 11 REMODEL
The Building 10 and 11 remodel project has been awarded to Hyland Construction. The project construction began Nov. 8 and will be completed in two phases. The first phase is the reconstruction of Building 10 only. The second phase includes remodeling most areas of the first floor of Building 11 and this construction will begin in the spring of 2011. Contact Mark Richardson, 3456.
BUILDING AUTOMATION SYSTEM STRATEGIC IMPROVEMENTS
Heating, ventilation, and air conditioning (HVAC) controls have been upgraded in all buildings on our LON based centralized building automation system (BAS) at the 30th Avenue campus. We are now commissioning the system with assistance from SOLARC Architecture and Engineering to assure that the system is functioning according to our specifications. Facilities staff have completed the basic and intermediate training on the BAS web interface. We are utilizing the BAS system interface to assist in commissioning the system as well diagnosing and resolving issues that arise concerning HVAC. During last week facilities staff and contractor efforts have been concentrated on resolving temperature issues in approximately 10 rooms on the second floor of Building 19. This work has involved coordinating staff and students concerns in the Building 19 areas with two control contractors, college energy analyst, and facilities trades staff. Progress has been made towards balancing out temperature fluctuations and our staff is keeping track of the effected areas with our BAS trending tools. Please continue to report any HVAC issues or concerns to the Facilities Office at facilitiesoffice@lanecc.edu or call 5216 as we complete the system integration process. Commissioning for the project is expected to be complete at the end of November. Contact Anna Scott, 5805.
DOWNTOWN CAMPUS BUILDING
The architects presented the latest floor plans, exterior elevations and descriptive information about the building to the management team last week for review and comment. This information has also been sent to the construction cost estimators. If their estimate is within the budget the design will move forward. If the estimate is greater, the design will have to be adjusted to align it with the budget. Leads and project user groups who represent all of the occupying programs will have an opportunity to review and comment on the building design before the schematic phase is complete. Final schematic design drawings will be posted online at 2011sitearchive.lanecc.edu/bond/buildingdcindex.html Contact Bob Mention, 5747.
TRACK AND SOCCER BOWL
The infield of the track and the new soccer field is ready for use. The general contractor will be on site for the next 30 days completing the punch list of corrections created by the architect. The fence around the construction site has been removed. Contact Mark Richardson, 3456.
November 9, 2010
MOTOR POOL RESERVATIONS
As the fall term progresses, reservations for Motor Pool vehicles are increasing. In an effort to serve as many people as possible, we kindly request that when reserving a vehicle, that details such as the date needed, time of pick up, time of return, and calculated time of actual vehicle usage are as accurately portrayed as possible. If you find the reservation for a vehicle is no longer needed, or the date and/or time of usage has changed, please call the FMP office at extension 5216 or e-mail at MotorPool@lanecc.edu to update the details of the reservation. An additional reminder: According to Lane's policy, no motor pool vehicles are to be parked at the user's home overnight. Vehicles must be returned to the main campus when not in use. Contact Russ Pierson, 5727.
HOUSEKEEPING
The Housekeeping team will be preparing the Longhouse for its grand opening ceremony that is scheduled on Friday, December 3, at 11 AM. Contact Katherine Vos, 5561.
BUILDING 5 REMODEL AND ADDITION
Construction of the FEC addition and dance studio is scheduled to be completed on December 15. Exterior site work begins Monday, November 8. This activity will require diesel powered equipment to be brought back to the site to remove areas of the landscaping on the east side of building 5. Contact Mark Richardson, 3456.
BUILDING 10 AND 11 REMODEL
The Building 10 and 11 remodel project has been awarded to Hyland Construction. The project construction is scheduled to begin Monday, November 8 and will be completed in two phases. The first phase is the reconstruction of Building 10 only. The second phase includes remodeling most areas of the first floor of Building 11 to begin in the spring of 2011. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
Correction: The architects are scheduled to present the schematic design of the project next Wednesday, November 10, not on November 4 as previously stated. The management team met on November 4 to discuss a number of "housekeeping" issues including the arrangements for presenting the schematic design to the "leads" and PUGs of the occupying units and other interested parties, the status of third party solar energy providers, enclosed and partially enclosed offices and the schedule of meetings for the design development phase. Contact Bob Mention, 5747.
TRACK AND SOCCER BOWL
The infield of the track and the new soccer field is ready for use. The general contractor will be on site for the next 30 days completing the punch list of corrections created by the architect. The fence that is currently around the construction site will be removed soon. Contact Mark Richardson, 3456.
FACILITIES TRADES
FMP Trades have been working to complete construction at the Longhouse: carpenters (audio-visual, kitchen and display cabinets, fence, and door hardware), electricians (lights, electrical supplies), grounds, painters, in additional to a number of contractors trades. Contact Angela Fazio, 3428.
SUSTAINABILITY IN BUILDING 2 REMODEL
The Building 2 remodel was designed to meet the U.S. Green Building Council's Leadership in Energy and Environmental Design (LEED) certified standards. Green features of the building include water saving fixtures that reduce water use by 35 percent compared to a code compliant building and energy saving features that reduce energy use by 20 percent compared to a code compliant building. One of the more unique and successful energy efficiency features in Building 2 is a heat recovery system in which heat generated by the servers in the data center is used to heat the rest of the building. Jennifer Hayward, 5594.
CURRENT CONSTRUCTION NOTICES-
* TEMPERATURE CONTROL ISSUES FOR OCCUPANTS OF BUILDINGS 1, 3, 4, 5, 6, 7, 9, 11, 12, 15, 16, 17, 18, 19 AND CENTER
Over the past few weeks, many occupants have reported being affected by temperature control issues in offices and classrooms in buildings 1, 3, 4, 5, 6, 7, 9, 11, 12, 15, 16, 17, 18, 19 and Center. This is due to the major renovation bond project work in progress to convert from one Building Automation System to another. During the course of data migration, many points did not transfer correctly and many other undocumented points were discovered. This has resulted in the inability to view and control numerous HVAC controls systems in multiple buildings. The FMP planning team is attempting to work a way through these control problems with an anticipated completion in early December.
In the meantime, we sincerely regret your discomfort. Please continue to report issues to the facilities office at extension 5216 or e-mail facilitiesoffice@lanecc.edu. We appreciate your patience as we respond as quickly as possible to urgent needs. Angela Fazio, 3428.
November 2, 2010
BUILDING 10 REMODEL
Hyland Construction has started to mobilize for construction. They've moved their construction trailer onto the site, and will hook up temporary power to the project. The last of the asbestos abatement was completed last week, and Lane staff has begun demolishing the last existing sections of walls and slabs. Contact Mark Richardson, 3456 or David Amundson, 3455.
DOWNTOWN CAMPUS BUILDING
The design team is scheduled to present schematic design level drawings (plans and elevations) of the project to the management team on Nov. 4. The major elements of the design will be the same as what was shown to the board at its October meeting. Since then the landscape architects have proposed designs for the two inside courtyards and the exterior of the building and the architects continue to refine the interior room layouts. Most people pay attention to the architectural elements - the floor plans, elevations, materials and colors. Few show interest in the engineering elements - the structure, electrical, communications and mechanical that permit the building to function. Rest assured that the engineering is moving ahead also. Contact Bob Mention, 5747.
FLORENCE CENTER HVAC
Systems West Engineers has submitted options for schematic design of the new system to upgrade the Florence Center mechanical system, and Lane staff will provide feedback to them for the next phase of design. Contact David Amundson, 3455.
SOLAR STATION
The bollards to protect the new transformer have been installed by Lane trades staff. The Level 2 Charging Stations will be installed before the end of November. Contact David Amundson, 3455.
October 26, 2010
Motor Pool COPPS Procedure and Services Update
Many people use our college motor pool vehicles every year. The procedure for motor pool vehicle use is located at: http://2011sitearchive.lanecc.edu/cops/veh.htm . Once a reservation for a vehicle is made on 25Live or through our facilities office, we prepare packets for each specific vehicle for you to pick up in building 7. We do ask, however, for at least a 24 hour pre-use notice. We have had several people "drop-in" at the last minute lately requesting vehicles for important college use. We were able to provide vehicles so we were lucky. These vehicles are provided on a first-come, first-served basis. There are three Toyota hybrid vehicles in our motor pool fleet. If you have never driven one, it is a great opportunity for you to have the experience of driving a high-tech hybrid that gets over 45 mpg while providing a smooth and comfortable driving experience. An older motor pool Toyota Prius was recently transferred to the college's automotive technology program to allow students to gain valuable experience working on a hybrid. We were also successful this past summer in replacing this older Toyota Prius hybrid with a newer 2007 Toyota Prius hybrid at below wholesale pricing. Partnering in a sustainable way with both the needs of college staff and students, reinforces our commitment to sustainability as a viable and strategic college core value. By using our college motor pool Toyota Prius hybrid vehicles you are demonstrating your personal commitment to sustainability. Contact Dave Willis, 5566.
Fall Wet Weather
As we enter the fall wet weather season, we often discover leaking roofs and storm drains that can back-up and create standing water. Leaking roofs can become evident by a small pool of water on the floor or a wet ceiling tile. Although the FMP trades staff have cleaned out roof gutters, inspected existing roofs, and made repairs already this fall, it is very easy to miss some potential leaking spots. Please give the facilities office a call if you see any signs of roof leaks in your area. A work request is also encouraged to be written by your department administrator. The facilities office can be reached at extension 5216 or by sending an e-mail to: facilitiesoffice@lanecc.edu . Contact Dave Willis, 5566.
New Landscaping and Walking Paths
Just a reminder to please use new walking paths rather than taking a "short-cut" resulting in walking through new landscape areas on campus. During the wet fall season, it is easy to track mud and leaves into our buildings. We do hope you will partner with us in this request. Contact Dave Willis, 5566.
PUBLIC SAFETY NOTICES
Key approval update: a designated email address for all keyless access card requests has been created so there's one centralized location that captures all requests. Please send all keyless access card approvals and requests to keycard@lanecc.edu We ask that you no longer send requests directly to a PS employee. All employees trained to create keycards are part of the "keycard" email group and will receive the request. Note: hard keys require a work order request sent to FMP.
Public Safety
Buildings are locking down via the 25Live schedule. If you need access after scheduled hours, please make sure you carry your key card. If you forget your key card please call Public Safety at 5558 for access. Contact Katherine Vos, 5561.
Housekeeping Equipment
Housekeeping has purchased riding equipment to allow for cleaning of the new floors in lower building 5. Contact Katherine Vos, 5561.
Housekeeping Reminder
Did you know that those with personal office spaces are responsible to empty their office trash? There should be an assigned receptacle near your office area for your personal garbage. If you cannot locate your receptacle or if it is missing, please contact Housekeeping at 5578. Building 30 and 4 have new built-in recycle stations. Please use these stations to empty personal office garbage.
Two ways to partner with custodians to help maintain clean classrooms:
1. Remind students that food and drink are not allowed in classrooms.
2. Encourage students to utilize non-spiral notebooks. Here's why: spiral notebooks are messy. Each time a page is torn out, numerous confetti paper pieces fall to the floor. Cleaning up these pieces adds additional workload to custodians. Contact Katherine Vos, 5561.
BUILDING 2 REMODEL
Project Manager, Jeff Durmaj of John Hyland Construction completed the building 2 remodel early and under budget in spite of being faced with a complicated project and a very short time frame for construction. The most technically-challenging part of the project, moving and upgrading the Lane data center, was started at the beginning of spring term, but the bulk of the remodel didn't start until school was out for the summer. Hyland completely remodeled the second floor in time for FMP trades and IT staff to install the equipment for enhanced classrooms and computer labs and for staff to move into the ground floor before fall term began. The building has an upgraded HVAC system that includes recovery of the heat generated by the data center, and multiple redundancies for the data center cooling. The upgrade to building 2 is putting Lane on the map as having a model data center and IT services. Contact David Amundson, 3455.
BUILDING 5 REMODEL AND ADDITION
The remodeling phase of Building 5 is complete. LCL is still working on several correction items and are expecting work to take up to 30 days to complete due to having to complete the work after hours in order avoid disrupting classes. The FEC and dance studio additions piece of the project are on schedule to will be completed by December 15. Contact Mark Richardson, 3456.
BUILDING 6 ELEVATOR
The new elevator was approved by the State Elevator Inspector. The elevator will provide accessibility to the restrooms for the Performance Hall patrons as well as by building users during the day. Contact David Amundson, 3455.
BUILDING AUTOMATION SYSTEM
Commissioning service work (systems verification and check out) for the upgraded heating, ventilation, and air conditioning (HVAC) controls begins this week. Formal training for our college staff on the new Web interface for the upgraded HVAC controls begins on Friday, October 29. Controls have been upgraded in all buildings on our LON based centralized building automation system (BAS) at the 30th Avenue campus. Buildings Center, 1, 3, 4, 5, 6, 7, 9, 11, 12, 15, 16, 17, 18, and 19 are functioning with the Fall term occupancy schedules. Please continue to report any HVAC issues or concerns to facilitiesoffice@lanecc.edu or call extension 5216 as we complete the system integration process. Work to update floor plans including the new system installed in main campus buildings has been completed by FMP staff with assistance from cooperative education students in drafting. These updated floor plans have been integrated by TraneOregon with HVAC equipment zone information and are the foundation of our new web-based system. The project is expected to be complete early December. Contact Anna Scott, 5805.
DOWNTOWN CAMPUS BUILDING
A "Downtown Campus Update" was presented to the board of education at its October 13 meeting. The Project Manager updated the board about the progress made to date and the architect showed a PowerPoint presentation of the preliminary floor plans. The floor plan presentation can be viewed at http://2011sitearchive.lanecc.edu/bond/downtowncampus-board10-13-10.html . Board members had questions about the housing plans - size of units, number of beds, furniture, etc. which the presenters responded to. Overall, the board seemed favorably impressed with the direction the project is going in.
The board awarded a contract for commissioning services for the project to Interface Engineering in Portland. Interface was one of five firms that submitted proposals. None of the five were from local firms.
Copies of the preliminary floor plans have been distributed to the management team and steering committee for further review and comment. The architects continued working on the exterior elevations and interior concepts and presented their work to the management team last week on October 21. The architects presented some interior concepts and the landscape architects presented some preliminary designs for the landscaping of the building perimeter and the two courts on either side of the CML. A representative from Interface engineering (the commissioning firm) was present and discussed scope of work and process. Contact Bob Mention, 5747.
TRACK AND SOCCER BOWL
The soccer field was completed and ready to be used by staff and students on October 4. Delta Construction is working on completing the concrete walkways and track surfacing. Track surfacing was completed Saturday, October 16. Scoreboard installation began on Friday, October 22. This activity is expected to cause delays with anyone wanting to use the jogging trail. Contact Mark Richardson, 3456.
FACILITIES TRADES
FMP Trades are back into a more normal routine of operations, maintenance, and responding to work orders after three very hectic weeks of completing projects and preparing the campus to welcome students and staff back for fall term. This past month, FMP received 420 work orders and completed 510, slowly whittling into our backlog of outstanding requests. Some notable projects completed this week include office remodels for STEM grant (Building 12), roof leak repairs (Building 11 and Florence), laundry boiler repair (Building 7), light repairs (Florence), fabrication of podium and cabinets (Longhouse), mold remediation and duct cleaning (Building 4), investigation and rectification of temperature problems throughout campus due to transition of the new Building Automation System. To submit facility work orders, please see your department Administrative Coordinator. Contact: Angela Fazio, 3428.
CURRENT CONSTRUCTION NOTICES -
TEMPERATURE CONTROL ISSUES
Over the past few weeks, many occupants have reported being affected by temperature control issues in offices and classrooms in buildings 1, 3, 4, 5, 6, 7, 9, 11, 12, 15, 16, 17, 18, 19 and Center. This is due to the major renovation bond project work in progress to convert from one Building Automation System to another. During the course of data migration, many points did not transfer correctly and many other undocumented points were discovered. This has resulted in the inability to view and control numerous HVAC controls systems in multiple buildings. The FMP planning team is attempting to work a way through these control problems with an anticipated completion in early December. In the meantime, we sincerely regret your discomfort. Please continue to report issues to the facilities office at extension 5216 or e-mail facilitiesoffice@lanecc.edu . We appreciate your patience as we respond as quickly as possible to urgent needs. Angela Fazio, 3428.
October 12, 2010
HOUSEKEEPING
Housekeeping would appreciate staff and faculty partnering with custodians to ensure that all classrooms stay food and drink free. Contact Katherine Vos, 5561.
PUBLIC SAFETY
Please make sure that all events and classes are scheduled in 25 Live. Instructors may need their keyless access cards updated to ensure they can access a building or smart classroom. This update requires a manager sending an email to Jim Harris at Public Safety informing him of the modification.
Thanks to all staff and mangers who assisted with parking lot control. You all did an outstanding job! During the first week, lots were at capacity by 9:30 a.m. most days. Over the second week, parking eased up and spaces were available in overflow lots. Until notice is otherwise provided, anybody may park at the solar station.
Public Safety encourages all staff to review the employee emergency plan and evacuation plan provided by the Health and Safety Department. As a reminder, please report suspicious containers, packs, etc. to Public Safety and follow all safety instructions provided. Contact Katherine Vos, 5561.
PROJECT UPDATES-
BUILDING AUTOMATION SYSTEM STRATEGIC IMPROVEMENTS
Heating, ventilation, and air conditioning (HVAC) controls have been upgraded in all buildings on our LON based centralized building automation system (BAS) at the 30th Avenue campus. Buildings Center, 1, 3, 4, 5, 6, 7, 9, 11, 12, 15, 16, 17, 18, and 19 are functioning with the fall term occupancy schedules. Facilities and TraneOregon staff have responded to a small number of temperature concerns that relate to the transfer of data from our old BMS system to the new system. Please continue to report any HVAC issues or concerns to the facilities office at facilitiesoffice@lanecc.edu or call extension 5216, as we complete the system integration process. Work continues to create the graphical access to all the BAS data. Floor plans for the main campus buildings have been field checked by FMP staff for accuracy and are being updated with assistance from FMP fall AutoCAD interns. These updated floor plans will be integrated by TraneOregon with HVAC equipment zone information and will be the foundation of our new web-based system. The project is expected to be complete at the end of October. Contact Anna Scott, 5805.
DOWNTOWN CAMPUS BUILDING
Architectural work on both the academic and student housing portions of the building is on schedule and going well. The affected college personnel are to be congratulated for their timely work.
Over the last two weeks the architects have presented the preliminary floor plans to the management team and the leads and faculty of the occupying programs. All were very impressed with the plans and think they will meet the functional needs of their programs. The architects have started work on the exterior elevations of the building and will present those within the following weeks. The schematic design phase is nearing completion and this means that the major elements of the design (the floor plans, elevations, passive design elements, basic structure, etc.) are in place and a preliminary cost estimate can be started. The design development (DD) phase comes next. In DD the architects work with each of the occupants to design the interiors of each room. This includes cabinets, door locations, office, classroom and lab layouts, etc.
The board is expected to award a contract for commissioning services at its meeting on Oct. 13. Contact Bob Mention, Bond Project Manager, 5747.
SOLAR STATION
Bond trades staff will begin work this week at the Solar Station to install two bollards at the Parking Lot B electrical transformer required by the Lane County. Please be aware that there may be minor impact to parking in the two adjoining spaces in front of the transformer. The first five Level I charging stations are installed. These produce 120-volt electricity and will be converted to dual Level I/II charging stations (dual voltage levels of 120 or 208 volts). Five additional dual level stations will be installed in late Nov. or early December. Contact Anna Scott, 5805.
October 5, 2010
BUILDING AUTOMATION SYSTEM STRATEGIC IMPROVEMENTS
Coordination continues between the building automation system (BAS) phase one contractor, TraneOregon, the bond construction teams, IT, and FMP staff to assist the integration of the new and existing heating, ventilation, and air conditioning (HVAC) controls at buildings at the 30th Avenue campus into an upgraded campus system. The goals of phase one project include replacement of the building HVAC information routing equipment and upgrading the BAS network interface to a web-based system. Router equipment enclosures have been completed. IT and FMP staff have the computer server installed and TraneOregon has installed the new BAS control software. Heating, ventilation, and air conditioning (HVAC) controls have been upgraded in buildings Center, 1, 3, 4, 5, 6, 7, 9, 11, 12, 15, and 16 and are functioning with the fall term occupancy schedules. Work to extract information from buildings 17, 18, and 19 began Sept. 30. The team's focus on next two weeks will be on the work to create the graphical access to all the BAS data. The project is expected to be complete at the end of October 2010. Contact Anna Scott, 5805.
BUILDING 2 REMODEL
Classroom equipment was installed and operating in time for classes to start last week, the Information Technology staff has moved into the new offices, and the new data center is operating smoothly. Miscellaneous loose ends i.e. permanent room numbers, window blinds, and adjustments to the HVAC system, will be completed without disturbing class schedules or office use. Contact David Amundson, 3455.
BUILDING 6 ELEVATOR
All work in Building 6 was completed ahead of schedule and elevator was approved for public use before classes began on Sept. 27. The piano lab was completely wired and ready for use and is hosting a full schedule of keyboarding classes. Contact David Amundson, 3455.
DOWNTOWN CAMPUS BUILDING
The architects continue meeting with the leads and faculty from various programs to show them preliminary designs of their space and its location in the building. Representatives from Facilities, Public Safety and Housekeeping have also met with the architects to discuss their needs. As noted previously the design process is iterative. The architects are also continuing to explore housing unit designs, common spaces and options for trash removal and recycling. Preliminary exterior design concepts are scheduled to be presented to the management team on Wednesday, Oct. 6. Contact Bob Mention, 5747.
FLORENCE HVAC REPLACEMENT
College staff is reviewing the schematic design report for the mechanical system replacement at the Florence campus. Earlier this summer, college staff, Systems West engineers, and PIVOT Architecture worked together at the first public user group (PUG) meeting to give input for the creation of the schematic design. College staff is beginning the hiring process for a commissioning agent who will help the college to ensure that we meet our mechanical system replacement design objectives. Contact Anna Scott, 5805.
SOLAR STATION
The solar station commissioning agent, EESI, has been hired and is beginning its work with FMP staff and the construction team to verify that our project requirements have been met. As of noon on Sept. 29, and a total of 183 hours of operation, the solar station has generated 2,002 kilowatt hours of AC power back to the Lane electrical grid. That is the equivalent of 1.5 months of power for an average Lane county residential house in a little over a week. The first five Level I charging stations have been installed. These produce 120-volt electricity and will be converted to dual Level I/II charging stations (dual voltage levels of 120 or 208 volts). Five additional dual level stations will be installed in late November or early December. Contact Anna Scott, 5805.
September 28, 2010
BUILDING 4 REMODEL
The project is now in its final stages of being completed. Staff members have been moved back into the new office spaces and are nearly ready for the fall term. Lease Crutcher Lewis (LCL) is still on the site working on minor punch list items, finishing some small details, and making sure staff members have what they need. Punch list items that require using chemicals or paint will be completed after hours and will be well ventilated after the work has been completed. Access control hardware is installed in all areas in building 4 but programming issues are still being worked on and all doors may intermittently become non-operational throughout the day, Monday, Sept. 27. Contact Mark Richardson, 3456.
BUILDING 5 REMODEL AND ADDITION
This project will complete in two phases. The remodeling portion of the project is completed and ready to occupy. The first phase includes a complete remodel of the check out area and a new classroom addition. Many of the areas still need to have a final coat of paint, and some additional cleaning will be on going for two more weeks. Deep cleaning that requiring the use of chemicals will be completed after hours as done in the past by the Lane janitorial staff. Areas inside the remodeled area will be painted after 9 PM and will be completed in a well-ventilated location. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
Schematic design work continues. Two significant meetings happened last week: the architects presented preliminary plans for all four floors of the academic building to the Management Team and the engineers discussed building control concepts with Energy Management program representatives and FMP personnel. Both meetings were very productive. A meeting is being arranged for Thursday, Sept. 30 for the steering committee and others to review the preliminary floor plans and make comments.
A topographical survey of the site has been completed and the Geotechnical investigation of the site is about to begin. Contact Bob Mention, 5747.
TRACK AND SOCCER BOWL UPGRADES
Delta Construction with the help of Field Turf has completed the infield surface of the track. Atlas Track Surfacing has been on the site since Sept. 23 and started applying the first layer of track coating on Saturday, Sept. 24. Because of the amount time to complete the task, this work will be completed in mid-Oct. . The new score board delivery is on schedule and plans are that we will be installing it the third week of Oct. . Heavy rains have delayed the project by a few days, but the crews remain confident they can be completed by Oct. 1. Contact Mark Richardson, 3456.
September 21, 2010
BUILDING AUTOMATION SYSTEM STRATEGIC IMPROVEMENTS
Router equipment enclosures have been installed in Buildings 4, 6, 7, 12, and 16. New routers have been installed in Buildings 4 and 7. Coordination continues between the building automation system (BAS) phase one contractor, TraneOregon, the bond construction teams, IT, and FMP staff to assist the integration of the new and existing heating, ventilation, and air conditioning (HVAC) controls at Buildings 4, 5, and 7 into an upgraded campus system. Work to extract information from Buildings 1, 3, 6, 9, 11, 12, 15, 16, 17, 18, and 19 will begin in the coming weeks. The goals of phase one project include replacement of the BAS information routing equipment and upgrading the BAS network interface to a web-based system. Contact Anna Scott, 5805.
BUILDING 2 REMODEL
Inspections by building officials and the State Fire Marshal were successful, and Lane received a certificate of occupancy for the completely remodeled building. IT staff continue to move into their offices and Lane moving crews, carpenters, electricians and IT staff are installing furniture, wiring, teaching podiums, screens, white boards, projectors, computers and other equipment into the enhanced classrooms and Distance Learning classrooms. The newly remodeled data center on the ground floor provides upgraded routers and servers for better communication at peak use hours. The equipment is housed in racks that supply cooled air directly to the electronics from an updated HVAC system. The data center cooling is expected to be more effective and uses only half the energy. Redundant HVAC systems will automatically switch on in the event of a cooling system failure to protect the equipment from overheating. Contact David Amundson, 3455.
BUILDING 4 REMODEL
The building 4 project was one of the most challenging projects completed this year. A joint effort with Lane staff, GBD Architecture, and Lease Crutch Lewis made this project a success. The entire HVAC system constructed below ground in the 1960s was abandoned and a new HVAC (Heating, Ventilation, and Air-Conditioning) system was installed. The new duct system has a sealed air supply and return air system makes the indoor air quality the highest quality possible. The new floor design added six new classrooms and a new computer lab with new computers. An open floor plan and large windows will provide a comfortable environment for students to enhance their education. Most staff members will be returning this week to a new office space that is larger, with better indoor lighting, and in an environment constructed to LEED standards. Large exterior windows and indoor glass provide day lighting inside the building giving staff a natural well-lit working environment. Contact Mark Richardson, 3456.
BUILDING 5 REMODEL AND ADDITION
As the addition portion of this project to this building continues, most of the remodel work to this area is complete. The addition of the dance studio is scheduled to be completed by December 15. Several features have been designed into the floor plan that better defines access to the lower floor. The main entry doors were replaced with new storefront glass doors exposing the lobby area as a central relaxing environment of both buildings. From the second floor, the concrete walls have been cut open to allow staff and students to see the stairs leading to the lower level and the display of the new checkout counter and the new state of the art storage system. This centrally located checkout area will provide better access and is designed to reduce congestion during busy class times. The women's shower facilities have been expanded to allow room for more lockers which are scheduled to be installed during the winter break. The Fitness Center has been renovated providing an enhanced natural airflow from the glass doors installed as part of the new design. Two large fans have been added to the ceiling of the fitness center that will draw air from the outside and will exhaust through vents placed on the roof. Contact Mark Richardson, 3456.
BUILDING 6 ELEVATOR
The new elevator was approved by the State Elevator Inspector. The elevator will provide accessibility to the restrooms for the Performance Hall patrons as well as by building users during the day. The new piano lab is equipped with new electronic pianos for group keyboard classes. Contact David Amundson, 3455.
BUILDING 19 BUSINESS OFFICES
This project is complete and this week staff will finish moving into their new office spaces. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
Architects and engineers continue working on the schematic design of the building. The schedule shows the schematic design phase wrapping up by late October. There's much to accomplish before then.
The second student housing charrette was held last Friday. The conversation focused on sustainable design options and floor plan arrangements. The architects received a lot of good input that will influence the next design iteration.
Last week the selection committee interviewed two firms that proposed commissioning services. The committee is currently deciding which firm to recommend to the board for awarding the contract.
Two meetings are scheduled for this week. One will be for the management team to review and comment on some floor plan proposals and the other is planned for some of the energy management program faculty and a few FMP staff to discuss building control systems.
At its September meeting, the Board of Education accepted CMGC findings and directed administration to move to a public hearing. Contact Bob Mention, 5747.
FLORENCE HVAC REPLACEMENT
This week FMP staff received the schematic design report for the mechanical system replacement at the Florence CLC. Earlier this summer, college staff, Systems West Engineers, and PIVOT Architecture worked together at the first public user group (PUG) meeting to give input for the creation of the schematic design report. College staff will review the report in the next several weeks and begin the hiring process for a commissioning agent who will help the college to ensure that we meet our mechanical system replacement design objectives. Contact Anna Scott, 5805.
SOLAR STATION
The Solar Station photovoltaic array system was started up this week and it is generating AC power. After a total of only 19 hours of operation, the solar station has generated 290 kilowatt hours of electricity back to the Lane electrical grid. The first five Level I charging stations have also been installed. These produce 120-volt electricity and will be converted to dual Level I/II charging stations (dual voltage levels of 120 or 208 volts) and five additional dual level stations will be installed in late November or early December. Contact Dave Smith, 4633.
TRACK AND SOCCER BOWL UPGRADES
Track: Delta Construction and Field Turf have been working long hours to reach the goal of having the project completed. Although the entire project will not be completed until November, the new track and field surfaces will be ready to be used by the fall term. This was a huge hurdle for all the construction crews to complete such a large project in a very short amount of time. Upgrades made to the new outdoor area are a new synthetic field, long jump spaces, shot put areas, and concrete sidewalks for easy access. The new asphalt track will need to be covered with a two-tone rubber coating that is expected to last for over 10 years. The new score board that is to be installed mid October will be completely digital and will allow track officials to display results for all lanes at one time. With the Titan name displayed on the top, other proud sponsors will be able to display their information on the other three panels that surround the scoreboard. Contact Mark Richardson, 3456.
Soccer Bowl: This field is an exciting addition for the physical education and sports programs. The new design allows for better access and outdoor spectator seating. In the past, this area was often wet and standing water was always an issue. With the newly engineered draining system and gravel parking, the water will now drain into an underground storm-drain system keeping the area dry and useable year round. An access road has been added to the southeast corner of the field so those with limited physical ability will be able to park next to the field making their time more enjoyable. After the field is completed, the old baseball scoreboard will be replaced with a new, larger, double-sided digital scoreboard that is used for the new soccer and baseball fields. Surrounding the new scoreboards reaching twenty feet high will be a protective netting system allowing both fields to be used at the same time and provides protection from flying balls on both playing fields. Contact Mark Richardson, 3456.
September 14, 2010
DOWNTOWN CAMPUS BUILDING
The Board of Education took important steps at its September meeting to move the Downtown Campus building project forward. They awarded a contract for project management services to the firm of Gerding Edlen. This is the same firm that provided those services for the feasibility report. They approved the construction management general contractor (CMGC) method of project delivery, and decided that the college would build and own the student housing part of the project instead of turning it over to a private developer. Also discussed were some options for financing the whole project.
The architects prepared some design options for the first floor of the academic building and the student housing units. These were reviewed and commented on by the management team and the housing subgroup respectively. The next iteration of the housing design will be brought back for review on September 17 and the next iteration of the academic building design will be reviewed on September 22.
Building controls, commissioning and geotechnical investigation, and a other work is underway. Contact Bob Mention, 5747.
SOLAR STATION
The electrical contractor continues to install PV panels and necessary components for the first five Level I charging stations and expects to complete this work this week. In November, the components of the first five dual Level I stations will be replaced and converted to dual Level I/II stations. In addition, five more stations will be installed that will bring the total of dual Level I/II stations to 10 which will complete this project. Parking and passage impacts immediately around the Solar Station work area will continue throughout the week. Contact Dave Smith, 3433.
September 7, 2010
BUILDING AUTOMATION SYSTEM (BAS) STRATEGIC IMPROVEMENTS
Coordination work has started between the building automation system (BAS) phase one contractor, TraneOregon, the Building 4 and 5 construction team, and FMP staff to assist the integration of the new and existing heating, ventilation, and air conditioning (HVAC) controls at Buildings 4 and 5 into an upgraded campus system. Work to extract information from Buildings 1, 3, 6, 7, 9, 11, 12, 15, 16, 17, 18, and 19 will begin in the coming weeks. The goals of phase one project include replacement of the BAS information routing equipment and upgrading the BAS network interface to a web-based system. Phase one of this project is expected to be complete at the end of October. Contact Anna Scott, 5805.
BUILDING 4 REMODEL
General contractor LCL and its subcontractors are working seven days a week cleaning all areas getting ready for the moving crews to start moving staff into their new office the week of September 13. This fast paced time in the project has heightened the awareness for safety, and LCL is requiring safety equipment be used by all staff and construction employees until the project is completed. Exterior painting of Building 4 started this week and will be on going through S FMP will be working with the contractor to complete parts of the building that were touched during the remodeling. On September 2 the new HVAC system was put into operation allowing the system to flush all the new smells out of the building before staff is moved in. Contact Mark Richardson, 3456.
BUILDING 5 REMODEL AND ADDITION
Crews are working seven days a week making upgrades to the first floor. Building 5 is taking shape with the new rounded and open design on the first floor. The new glass doors located on the east side of the fitness center were installed on September 1. The new addition is going strong with an expected completion of December 15. Openings have been cut and crews installed the new steel stairs the week of September 6. Remodeling of this section of the building is on schedule to be completed by December 15. Crews are working at an accelerated pace to make sure parts of Building 5 are open and ready for the fall term. The fitness center floor has been refinished, and crews will be moving in equipment starting September 15. Through the holiday weekend, a new floor covering system was installed in the first floor that is especially designed to resist high traffic while being very low maintenance. A specialized floor surfacing company was on site working through the weekend to install a system on the first level of Building 4. The materials used in this process emit a strong odor during installation and will be noticeable for up to seven days after installation. Demolition crews will be back on the site this week cutting larger holes in the concrete tower to allow larger vents to be installed allowing additional air flow to the HVAC units. Contact Mark Richardson, 3456.
BUILDING 19 BUSINESS OFFICE REMODEL
This project is in the final cleaning stages. Final inspection is scheduled for this week, and office staff will be moving in during the week of September 13. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
In general, the design team continues its preliminary work. Several firms submitted proposals for commissioning services and project management services for the project. Selection committees evaluated proposals and the project management selection committee will recommend a firm for board action at the September 8 meeting. A land survey of the downtown site has been completed. The architects are scheduled to meet with the project management team on Friday, September 10.
The college has hired a firm to prepare a topographical survey of the site. That survey was completed and the maps were delivered to the college on September 3.
Architects are continuing to design options that fit programs and support functions into the academic building. A student housing charette occurred at the college last Friday where the architects presented some diagrams of different apartment options. Students and administrators responded with their thoughts. The architects will incorporate the responses into the next iteration. Another housing charette is scheduled for September 17. Contact Bob Mention, 5747.
KEYLESS ENTRY
Keyless entry access cards are available now. If your responsibilities require you to access 30th Avenue campus buildings outside of normal business hours, a keyless entry access card should be requested. Your division dean or administrative coordinator should be able to tell you if you have been approved for a card. Keyless access requires the approval of your division dean, in certain cases, a member of the Executive Team. If approved, you are encouraged to obtain a keyless entry card from the Public Safety office, Building 13, as soon as possible. To make arrangements to pick up your card (it must be picked up in person), please contact Public Safety at extension 5558 (541-463-5558). They will be able to confirm if you have been approved for a card. Cards are being issued between 8 AM and 1 PM, Monday through Friday and it takes only minutes to obtain. No paperwork, no forms, and no hassle to complete. Prepare to have your picture taken, so look your best. Contact Dave Smith, 3433, for information on the keyless entry system, or Public Safety, 5558, to make arrangements to pick up your card.
SOLAR STATION
The framework to support the PV panels was installed and the first PV panels were mounted last week. A group of students gained valuable experience installing a number of the PV panels as part of a solar installation certification class. The electrical contractor is continuing with the installation of the PV panels and is expected to be complete early next week. Once all the panels and necessary electrical components have been installed, the solar station will be brought online and begin generating AC power. The first five Level I charging stations are expected to be installed mid-September. These will be converted to a dual Level I/II and five additional dual level stations will be installed in late November or December. Please be aware of continued parking and passage impacts immediately around the solar station work area. Project completion of the first phase is expected September 13. Contact Dave Smith, 4633.
TRACK AND SOCCER BOWL UPGRADES
Beginning Tuesday, September 9 the gravel area "berm" between the fields will be closed to all motorized traffic. Field T for the track and soccer field will be delivered to the site and installation will begin on Tuesday, September 7. The asphalt paving process is expected to increase truck traffic in the areas around the north parking lot and will continue to be heavy during the paving process, which will last three days. Contact Mark Richardson, 3456.
August 31, 2010
BUILDING 2 REMODEL
Carpets are completely installed on the first floor and almost complete on the second floor. Lighting, doors, paint, casework and wiring are getting final touches. The HVAC system is being started up and commissioned, and all is running smoothly. The data center shutdown was successful, and most of the equipment has been moved to the new location and services restored. Furniture and equipment is being moved in starting this week. Contact David Amundson, 3455.
BUILDING 4 REMODEL
Classrooms and offices are on schedule to be completed by September 17. Crews have painted the classrooms, and carpet was installed last week. Carpet was installed in the new offices and cabinet installation started on Friday, August 20. Exterior windows and siding are ongoing and are expected to be completed by August 31. Contact Mark Richardson, 3456.
BUILDING 5 REMODEL AND ADDITION
Remodel of the first floor and the fitness center is going strong and will be completed by September 17. Crews were scheduled to complete the last round of demolition and saw cutting on Monday, August 23. LCL placed temporary wall in the main lobby of building 5 in anticipation of removing the concrete area next to the stairs. Block walls in the new dance studio addition have been completed and crews will install the steel supports next week. Please note that due to the construction of the first floor of building 5, entire first floor will be closed until September 20. Access will be restricted to construction staff only. All showers, the fitness center, dance studio, weight room, and all other areas on the first floor will not be accessible during this time. Contact Mark Richardson, 3456.
BUILDING 6 ELEVATOR
The new pianos have been moved into the Piano Studio, and they're being wired together. The shaft and the elevator machine room are ready for the installation of the new elevator, which is scheduled to be delivered on September 3. The remodel of the old piano studio space is underway. Contact David Amundson, 3455.
BUILDING 10 REMODEL
Demolition of the concrete slab is almost complete. After the old transformer and other electrical gear are disconnected and removed, the abatement company will remove all the remaining asbestos in one final effort and then final demolition of the electrical room can be completed. Contact David Amundson, 3455.
BUILDING 19 BUSINESS OFFICE REMODEL
The general contractor will be installing the cabinets and carpet this week. The painting has been completed, and the temporary wall will be removed during the week of August 30. Contact Mark Richardson, 3456.
BUILDING AUTOMATION SYSTEM
Phase one of the building automation system (BAS) campus network team consisting of Lane staff and contractor, Train Oregon, completed site visit and orientation. Work will begin with extracting information from existing database and convert to an upgraded web-based system of controls. Work to extract information from buildings 1, 3, 4, 5, 6, 7, 9, 11, 12, 15, 16, 17, 18, and 19 will begin in the coming weeks. Contact Anna Scott, 5805.
DOWNTOWN CAMPUS BUILDING
The design team continues to work with different groups at the college to learn and address their needs. Last week the design team met with people from Facilities including the sustainability coordinator, energy analyst, and Energy Management program representatives to present and receive feedback concerning the sustainability performance, passive design strategies, and maintenance and operating criteria for the building. The design team is a pretty large group that includes three architectural firms, three engineering firms and eight consulting firms that provide expertise in the areas of lighting, acoustics, landscaping, sustainability and audio/visual services. The college has issued RFPs for commissioning services and project management services. The deadlines for submitting proposals was Monday, August 23 for commissioning and Tuesday, August 24 for project management. Selection committees will process the proposals and work toward making recommendations to the board at its September meeting. Contact Bob Mention, 5747.
HEALTH AND WELLNESS CENTER
Instructional equipment and office and classroom furniture move in is underway. Faculty and staff begin moving in on August 23. Plantings around the building have been completed. Expect the job office and fencing to be gone by August 24. Contact Brian McMurray, 5829.
KEYLESS ENTRY
Keyless entry access cards are available now. If your responsibilities require you to access 30th Avenue campus buildings outside of normal business hours, a keyless entry access card should be requested. Your division dean or administrative coordinator should be able to tell you if you have been approved for a card. Keyless access requires the approval of your division dean, in certain cases, a member of the Executive Team. If approved, you are encouraged to obtain a keyless entry card from the Public Safety office, Building 13, as soon as possible. To make arrangements to pick up your card (it must be picked up in person), please contact Public Safety at extension 5558 (541-463-5558). They will be able to confirm if you have been approved for a card. Cards are being issued between 8 a.m. and 1 p.m., Monday through Friday, and it takes only minutes to obtain. No paperwork, no forms, and no hassle to complete. Prepare to have your picture taken, so look your best. Contact Dave Smith, 3433, for information on the keyless entry system, or Public Safety, 5558, to make arrangements to pick up your card.
NATIVE AMERICAN LONGHOUSE
Carpenters are swinging doors and completing interior trim work. Exterior doors should be hung by August 26. Electricians are nearing completion on installation of light fixtures. Installation of the wood flooring system begins on August 23. A concrete floor pattern and stain in the Hall of Honor room has been decided and should be completed by August 30. The bathroom tile work is complete, and the kitchen floor installed. Kitchen equipment will arrive August 23. Landscaping is underway on the north end of the building. The AV contractor is on board and has begun purchasing equipment. Parking lot asphalt has been patched. Expect final inspections over the next two weeks. Project completion expected Sept 10. Contact Brian McMurray, 5829.
SOLAR STATION
The steel framework for the photovoltaic (PV) panels was painted over the weekend and the installation of the brick pavers was completed. The project electrician continued wiring the invertors that will convert the direct current (DC) generated by the PV panels into alternating current (AC) suitable for use in residences and offices. This week the framework to support the PV panels will be fabricated and the first PV panels will be mounted. Once all the panels and necessary electrical components have been installed, the solar station will be brought online and begin generating AC power. Please be aware of continued parking and passage impacts immediately around the solar station work area. Project completion is expected August 31. Contact Dave Smith, 4633.
SUSTAINABILITY - GREENING THE BOND
Lane's new Health and Wellness Center is still on target to become a certified green building through the U.S. Green Building Council's Leadership in Energy and Environmental Design rating system. The building is expected to use 50 percent less water and 43 percent less energy than a traditional building. "Low-emitting" paints, adhesives, carpets, and other materials have been used to help improve indoor air quality and operable windows will allow occupants to have more control over fresh air supply and temperature. Contact Jennifer Hayward, 5594.
TRACK AND SOCCER BOWL UPGRADES
Construction of the track project is moving forward with an expected completion date of October 4. Soft soils found under the track surface have created some scheduling challenges for the project, but were removed over the weekend. Contact Mark Richardson, 3456.
August 17, 2010
BUILDING 4 REMODEL
Lease Crutcher Lewis, the general contractor, has increased work forces and project supervision on the Building 4 project. Despite the many hidden setbacks to the construction schedule, the project will be completed on time and ready for fall term. During this phase of the construction, contractors will be painting the exterior of the building. Power washing and painting of the exterior of the building is scheduled to start this week and will continue through the remainder of August. The dental lab that was temporally located in Springfield for the summer will be returning to the campus the week of September 13. Contact Mark Richardson, 3456.
BUILDING 5 REMODEL AND ADDITION
This project was set up in two different phases. The first phase is the interior remodeling of the fitness center and check out station on the first floor. This phase of construction is scheduled to be completed by September 17. A lot of the work that starts this week will be very noisy and will be moving at a fast pace for the next 30 days. The first activity that started Monday is to cut out and removed large openings in the wall of the fitness center. This work is expected to be loud throughout the day and should only last one week.
The second phase of construction is the addition on the north end of the building. This project is on schedule to be completed by January 2011. The concrete floor and CMU walls have been built, and Lease Crutcher Lewis is expecting their first load of steel for the framing next week. An office trailer is now located on the north side and will be staffed with the construction crews for the remainder of the project. Contact Mark Richardson, 3456.
BUILDING 19 BUSINESS OFFICE REMODEL
Painting contractors have started painting on interior walls and painting will be completed this week. The interior finish will begin the week of August 23 with the installation of the new cabinets, lights and carpet for the new office spaces. During construction, two large data conduits were discovered inside a wall that had to be removed. The electrician will start this week to remove and reroute the wires so the conduits can be removed. This is likely going to cause a shutdown of data services for several areas east of the culinary classrooms. A notification will be sent 48 hours in advance to prepare employees of the data service interruption that is expected to last for three days. The remodeling project is scheduled to be complete September 1 and staff will be moving into the new spaces the week of September 13. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
The college issued two Requests For Proposals on August 9. One was for commissioning services and the other was for project management services. The deadline for submitting proposals for commissioning services is August 19 and the deadline for the project management services is August 24.
The college is also moving ahead with hiring consultants to do several things at the site: a topographical survey, a geotechnical investigation, an environmental assessment survey, and a geo-thermal test well.
Meanwhile, on August 18, the architects and engineers will meet with several staff in the Facilities Management and Planning Department to review the mechanical, electrical, plumbing and building management systems they are proposing for the new building. Contact Bob Mention, 5747.
SOLAR STATION
Pavers have been laid on both sides of the solar station. The installation of the steel framework to support the PV panels is in progress and was completed Friday, August 13. The electrical contractor has mounted the invertors in the block enclosure and will continue wiring them during the next week. The invertors convert the direct current power generated by the PV panels into alternating current power to be fed back into the campus electrical system. The contractor has repaired the asphalt drive and the structural steel was painted over the weekend. The educational component will begin August 23. A request for proposal for commissioning services was due on August 13. On August 20, the solar station will be electrically connected into the LCC electrical distribution center during a power outage planned for building 5. Please be aware of continued parking and passage impacts immediately around the solar station work area. Project substantial completion is expected September 7. Contact Dave Smith, 4633.
TRACK AND SOCCER BOWL UPGRADES
Construction of the soccer field has kicked off to a great start. Crews will be working for the next two weeks preparing the sub grade to place rock on the surface. The track project is picking up speed and crews are working hard to make sure the project is completed by October 4. 2-G construction, the structural contractor has been forming and placing concrete for the project an average of every two days. 2-G has engaged an additional crew to help form and place concrete for the track project. Part of the effort to collaborate with the general contractor, LCC bond crews are working with the electrical contractor to form and place larger concrete pads for the transformer and electrical control boxes. This effort will help make up for some of the lost scheduled days during the heavy rains in June this year. Contact Mark Richardson, 3456.
August 10, 2010
BUILDING 2 REMODEL
Progress continues at a fast pace, and everything is still on schedule for completion in early September. Walls have been painted, ceiling grid and lights have been installed, tile in the restrooms is installed, and doors are ready to be hung. The shutdown of the power and the data center over the weekend was executed successfully. The data center is now running on the new transformer. The migration of the data center equipment will continue after the cooling system has been completed and installed. Contact: David Amundson, 3455.
BUILDING 4 REMODEL
Installation of the new air system is on schedule and is expected to be completed by September 15. Classrooms on the second level have been framed out and have received the final coat of paint. Installation of doors and windows is scheduled to start later this week followed by the installation of floor covering the week of August 23. Once installation of the floor covering is complete, the interior finished will begin. The classrooms are schedule to be completed by the first week of September. Contact: Mark Richardson, 3456.
BUILDING 5 REMODEL AND ADDITION
Remodeling work of the fitness center and checkout counter is scheduled to increase on Friday, August 13. Summer classes are completed in the fitness center and moving crews will be removing the fitness equipment right away to make room for construction activities. Demolition crews will start saw cutting sections of the block wall on the east side of the fitness center this week. This work is expected to be noisy and might cause some dust drift into Bristow square. Contact: Mark Richardson, 3456.
BUILDING 6 ELEVATOR AND REMODEL
Finishes in the second floor office, the piano studio and the restroom are almost complete. The elevator machine room and elevator shaft will be ready for the equipment when it is delivered on September 3. After the piano studio gets moved upstairs, the contractor will begin work on the new first floor workroom. Contact: David Amundson, 3455.
BUILDING 10 REMODEL
Bidding for the Building 10 remodel work for Art and RTEC was postponed to August 11. Contact: David Amundson, 3455.
BUILDING 19 BUSINESS OFFICE REMODEL
The project to remodel offices for the Business department staff is on schedule and will be completed by September 1. Wall construction is complete and painting is scheduled to begin this week. After painting is completed, crews will be back on site to complete the work remaining on the door, lights, and cabinetry. Contact: Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
The design team continues to work on space programming and engineers are working on passive design strategies to conserve energy. To date there have been two rounds of meetings between the architects and representatives of the units that will occupy the academic portion of the building. The architects have presented space diagrams to the representatives for review and comment. These diagrams include the sizes and relationships of reception areas, offices, meeting rooms, work rooms, break rooms, etc. So far, the representatives have been pleased with the architects work. This work will continue for several more weeks.
A kick-off meeting with architects and the Student Housing Committee occurred last week to outline the general criteria for the apartments. The architects will do some preliminary diagramming work and present the results for review and comments. Contact: Bob Mention, 5747.
SOLAR STATION
The masons finished wall construction of the CMU enclosure housing the electrical equipment. Pavers were placed on both sides of the solar station. The installation of steel framework to support the PV panels began on Friday, August 6, and work is expected to continue into the week of August 9. On Friday, August 13, the contractor will repair the asphalt drive and the structural steel will be painted over the weekend on August 14 and 15. The educational component of this project will begin August 23. A request for proposal was sent to commissioning firms this week with proposals due on August 13. Please be aware of continued parking and passage impacts immediately around the solar station work area. Project substantial completion is expected September 7. For more information, visit http://2011sitearchive.lanecc.edu/bond/index.html . Contact: Dave Smith, 3433.
On Saturday, August 14 and Sunday, August 15, parking lot B will be closed to allow the contractor for the solar station to paint the solar panel framework currently being erected in parking lot B. This work requires the use of spray painting equipment and depending upon wind direction and intensity, this could cause paint over spray in the vicinity. Public Safety will barricade parking lot B and traffic from the west entrance will be directed to the adjacent parking lots C and D. We apologize for any inconveniences this closure may cause. Contact: Dave Smith, 3433.
TRACK AND SOCCER BOWL UPGRADES
Construction of the new track is on schedule to be completed by October 4. Crews are working longer day shifts to make up for lost time due to the excessive rainfall earlier in the year. Starting this week, truck traffic will start to increase in the north parking lot area as crews work to complete the soccer field. Contact: Mark Richardson, 3456.
August 3, 2010
BUILDING 2 REMODEL
In order to transfer power to the new transformer and to put all the data center equipment on the permanent power source, there will be a shutdown of power to buildings 1, 2 (data center), 3, 18, 19, 24, 25, 26, 27, the lighting in SW parking lots, and the greenhouse by the Child and Family Education complex on August 6, 6 p.m. to August 7, 12 p.m. All telephone and data services (Moodle, GroupWise, wireless access, the website, myLane/ExpressLane, etc.) will be unavailable during this outage. Contact David Amundson, 3455.
BUILDINGS 4 AND 5
Concrete placement for the dance studio is completed and steel for the building is being erected this week. Building 4 classrooms are 80 percent complete and HVAC system installation is on going and is expected to be completed on time. The building 5 project wall board installation will begin this week. Contact Mark Richardson, 3456.
BUILDING 19 BUSINESS FACULTY OFFICES
Wall framing is complete and wall board is being installed. Project is schedule to be completed the first week of September. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
Three significant matters were addressed last week: The contract between the architects and the college is close to completion; the process to select both a commissioning agent and a project manager were set in motion; and the Board of Education favors the college building the student housing portion of the Downtown Campus building project.
This week the architects continue to process the programming information they received from the leads of the various programs that will occupy the building. Another round of meetings to review the revised program will be scheduled when the architects have completed their work. Contact Bob Mention, 5747.
SITE IMPROVEMENT AND CONCRETE REPLACEMENT
Concrete designs are completed and the first project is underway with construction at Parnell Loop. The second project, replacement of the concrete entrance stairs, ramp and sidewalk in front of building 6, Performing Arts is scheduled to begin mid August. Contact Mark Richardson, 3456.
SOLAR STATION
The contractor poured concrete for the center island and for the footings around the paved areas. The concrete forms were stripped and gravel backfill was placed in the center island. The five caps were placed at the top of support columns. The contractor will start installing the paver stones next week and building the block wall. The installation of the steel framework to support the PV panels is expected to begin on Thursday, August 5 and continue into the week of August 9. The educational component will begin August 23. Please be aware of continued parking and passage impacts immediately around the solar station work area. Project completion is expected August 31. For more information, visit http://2011sitearchive.lanecc.edu/bond/index.html. Contact Dave Smith, 4633.
On Saturday, August 14 and Sunday, August 15, parking lot B will be closed to allow the contractor for the solar station to paint the solar panel framework currently being erected in parking lot B. This work requires the use of spray-painting equipment and depending upon wind direction and intensity, this could cause paint overspray in the vicinity. Public Safety will barricade parking lot B and traffic from the west entrance will be directed to the adjacent parking lots C and D. We apologize for any inconveniences this closure may cause. Contact Dave Smith, 3433.
TRACK AND SOCCER BOWL UPGRADES
The soccer field project work is picking up is scheduled to be completed by October 4. The drain system is at 50 percent and widening of the track is complete. The project work is picking up and is expected to be completed by October 4. Completed design has been received and the contractor is in the process of providing a final price. Construction is expected to start soon and be completed by November 4, 2010. Contact Mark Richardson, 3456.
July 27, 2010
BUILDING 2 REMODEL
Progress continues at a fast pace on the Building 2 project. In classrooms, offices, and meeting rooms, drywall is almost complete and painting has begun. Roofing is almost finished, and the HVAC systems are being readied for startup test over the next several weeks. The data center remodel is progressing smoothly. In order to transfer power to the new transformer and to put all the data center equipment on the permanent power source, there will be a shutdown of power to buildings 1, 2 (data center), 3, 18, 19, 24, 25, 26, 27, the lighting in southwest parking lots, and the greenhouse by the Child and Family Education complex on August 6, 6 p.m. to August 7, 12 p.m. All telephone and data services (Moodle, GroupWise, wireless access, the website, myLane/ExpressLane, etc.) will be unavailable during this outage. Contact David Amundson, 3455.
BUILDING 4 REMODEL
The project is on schedule and will be completed by mid September. Conflicts with the HVAC installation are now in the past and the project is progressing smoothly. Final finishes on the second level has started this week with painting the classrooms and new offices. Contact Mark Richardson, 3456.
BUILDING 5 REMODEL AND ADDITION
The concrete floor supporting the new addition is scheduled to be placed on Wednesday, July 28. Once concrete is set, contractors will then be able to install the steel framework that will support the new addition. Steel installation is noisy at times and will require air powered equipment to complete the connections. Steel installation is not expected to start until mid August. Contact Mark Richardson, 3456.
BUILDING 6 PERFORMING ARTS ELEVATOR AND REMODEL
Masonry and roof carpentry for the elevator shaft is complete. Roof installation was performed on Monday, July 26. The second floor office, restroom and piano studio are on schedule to be complete by mid August. The schedule for the elevator installation has been moved up and is expected to be complete by September 16. Contact David Amundson, 3455.
BUILDING 10 ART AND RTEC REMODEL
Construction bids for the Building 10 remodel are due August 4. Lane crews continue demolition of the interior and have begun removal of the concrete floor slab. The entire building has been fenced and all area inside the fence is considered a hardhat-required construction zone. Contact David Amundson, 3455.
BUILDING 19 BUSINESS FACULTY OFFICES
Wall framing is complete and sheet rock installation begins this week. Interior painting is scheduled for August 6 and will take four to five days to complete. This project is progressing on schedule and is expected to be completed by September 1. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
Programming work on the academic part of the building has started. Confirming the space needs of each of the occupying units is the first phase of the architects' work. Are the space needs listed in the feasibility report still valid? Two full days of meetings between the architects and representatives of the units occurred last week to review this matter. This week the architects will prepare diagrams and other material that reflects what they heard in the meetings. When ready, this material will be presented to the units. The architects will not do any work on the housing part of the project until the Board of Education gives further direction about how it wants the housing to be developed. The board has scheduled a work session on Wednesday, July 28 to discuss this matter further. Contact: Bob Mention, 5747.
FIRE ALARM AND MASS COMMUNICATION SYSTEM
The fire alarm system for the Modular buildings 13, Public Safety and SES, was successfully tested on Friday, July 23. This completes the scheduled testing of the fire alarm upgrades for much of the campus. The contractor, SecureCom, will be continuing to work on several building renovation projects, including buildings 2, 4, 5, 6, and 10. Contact Dave Smith, 3433.
KEYLESS ENTRY
The contractor, Allied Fire and Security, will be working next week on electronic and hardware installations on Gate 9 near the Public Safety office and in the Enrollment and Student Financial Services Building 1. They will also be returning to several buildings to make changes or to add additional doors into the system. Much of the installation on campus has been completed. They are also working on various renovation projects, including buildings 2, 4, and 6, and on new construction projects, the Longhouse and Health and Wellness Center. Contact Dave Smith, 3433.
SITE IMPROVEMENT AND CONCRETE REPLACEMENT
Two projects will be completed this summer. The first project will be a sidewalk replacement in the front of performing arts. The project will start in mid August and will be completed using LCC staff. The second project is removing the sidewalk and planter area on the north end of the LTD bus station and replacing the sidewalk with a new design. This design will have a new raised walkway to provide safer access to the dental clinic. This work is expected to start in the coming weeks and will be completed by Lease Crutcher Lewis.
SOLAR STATION
The contractor began backfilling and compacting the excavated areas with gravel fill. Forms have been set for the concrete islands and the steel caps for the pipe columns were received. One cap has been installed temporarily. Rebar and formwork is being installed for concrete footings. The contractor will pour the concrete for the footings and islands late next week, and will begin installing the paver stones the week after. The steel framework to support the PV panels is expected on Friday, August 6, with erection to begin the week of August 9. The educational component will begin August 23. Please be aware of continued parking and passage impacts immediately around the solar station work area. Project completion is expected August 31. Contact Dave Smith, 4633.
TRACK AND SOCCER BOWL UPGRADES
Excessive rainfall this year caused the construction crews to work 60 hours a week to make sure the project is completed by the fall term. The soccer field design is in the field review stages and a final design was presented Monday, July 26. Contact Mark Richardson, 3456.
June 15, 2010
BOND UPDATES
BUILDING 2 REMODEL
The classrooms and offices in building 2 have been moved out, and asbestos abatement, demolition and construction on the second floor will begin on June 14. Construction on the first floor data center continues. The construction zone around building 2 will be restricted on both levels. Contact David Amundson, 3455.
BUILDING 4 REMODEL
The general contractor will start installing fences and temporary walls on the second level of building 4 and select locations on the first floor. Access into certain areas is restricted to anyone not part of the construction and/or moving crews. The dental lab will be moving to their temporary location the week of June 21. The general contractor will be accessing room 130 and removing part of the concrete floor on Monday to install a temporary air system for the dental board exams on June 18, 19, and 20. Light demolition began on the first floor on Monday June 14. This activity will be in a selected area only to ensure the areas used for the dental board exams are not affected. Contact Mark Richardson, 3456.
BUILDING 5 REMODEL/ADDITION
Foundation work continues on the north side of building 5. Equipment was mobilized this week, beginning Monday, June 14, to start installing the foundation piles for the new addition. This work caused noise and ground vibration throughout the day. Also on Monday, demolition started on building 5, west side, lower level, of walls, ramps, and exterior doors. Contact Mark Richardson, 3456.
FIRE ALARM/MASS COMMUNICATION
The fire alarm contractor, SecureCom, is complete with the installation and most of the testing. Much of the fire alarm system was tested over winter break; however, additional testing will be performed on June 18 in the presence of the Oregon state fire marshal. Communication to the campus community regarding this testing was sent via e-mail last week. Testing will not impact dental boards testing scheduled June 19 and 20. Contact Dave Smith, 3433.
BUILDING 6 PERFORMING ARTS ELEVATOR
Construction of the new elevator will begin this week. There will be noise and limited access in the construction areas for the entire summer. Contact David Amundson, 3455.
BUILDING 10 REMODEL
Demolition of mezzanines is continuing, and construction documents are being completed for bidding. Contact David Amundson, 3455.
BUILDING 19 BUSINESS FACULTY OFFICES
Lane crews are removing existing equipment from the area of the remodel, and the contractor will begin work on June 21. Contact David Amundson, 3455.
KEYLESS ENTRY
The contractor, Allied Fire and Security, is finishing up the keyless entry installation in building 1 (Enrollment and Student Financial Services) this week and will be moving to Child and Family Education next week. The installation at the Florence campus was scheduled and began on Monday, June 14. Contact Dave Smith, 3433.
TRACK AND SOCCER BOWL UPGRADES
The project has been on hold waiting for the rain to subside and the fields to dry out before equipment can access the area. Accessing the fields when the ground is to wet will cause damage to the surface of the fields making it more difficult to provide a smooth and even playing surface. The newly developed master plan has triggered some redesigning work on the soccer bowl. The general contractor is relocating the temporary fence that surrounds the soccer field next week. This is being done to allow the soccer field to be used this summer while a new location is being determined. Contact Mark Richardson, 3456.
SOLAR STATION
Essex, contractor for the solar station at Lane, began work in parking lot B on Monday, June 14. Fencing is expected to enclose area around immediate construction and will affect parking and passage through the lot. Project completion is expected August 31, 2010. For information, visit http://2011sitearchive.lanecc.edu/bond/updates.html. Contact Anna Scott, 5805.
June 8, 2010
BOND UPDATES
BUILDING 2 REMODEL
The data center is being upgraded and moved to its new location. Asbestos abatement and demolition will begin after spring term finals week ending Friday, June 11. Contact David Amundson, 3455.
BUILDING 4 REMODEL
Most of the demolition is complete on the second level of the building. More demolition will have to be completed but will not start until after the dental board exams scheduled later in June. The second level of the building will no longer be accessible to staff and students until construction completes. Contact Mark Richardson, 3456.
BUILDING 5 REMODEL AND ADDITION
Excavation for the foundation will continue at the north side of the building. Foundation piles are scheduled for installation the end of June, which is expected to cause some vibration inside the fitness center and might be noticeable throughout the building. Construction demolition is scheduled to start on June 12 on the first floor and is expected to continue through the summer and up to the beginning of fall term. The northwest stair access to the lower level of building 5 will be closed June 12-17. Contact Mark Richardson, 3456.
BUILDING 6 PERFORMING ARTS ELEVATOR
Vik Construction will begin construction after spring term finals week ending Friday, June 11. Contact David Amundson, 3455.
BUILDING 10 REMODEL
Lane crews continue with demolition of the interior walls and floors. Construction documents will be ready for bidding in July. Contact David Amundson, 3455.
BUILDING 19 BUSINESS FACULTY OFFICES
Construction will begin after spring term finals week ending Friday, June 11. Contact David Amundson, 3455.
CAMPUSWIDE CONCRETE REPAIR
Two projects for site improvements will be completed this year. The crosswalk on the northwest side of building 4 will be completed at the same time the site improvements are made at the new Health and Wellness Center. The second project will be replacing the damaged concrete on the south side of bldg 6. Both projects will be started this summer and will be completed by fall term. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
Friday, May 28, 2 p.m., was the advertised deadline for submitting proposals for architectural services in response to the request for proposals for the project. Two proposals were submitted, both from Eugene firms who had partnered with large Portland based firms. Following formal college requests for proposal (RFP) processes in alignment with the state of Oregon community college rules for procurement, the selection committee will process the submittals and recommend to the president and Board of Education that one of the firms be hired. This action should be completed by the July board meeting. Contact Bob Mention, 5747.
FIRE ALARM AND MASS COMMUNICATION SYSTEM
The fire alarm contractor, SecureCom, is complete with the installation and most of the testing. Much of the fire alarm system was tested over winter break; however, additional testing will be performed on June 18 in the presence of the Oregon state fire Marshall. Testing will not impact the dental boards testing scheduled on this day. Contact Dave Smith, 3433.
KEYLESS ENTRY
The contractor, Allied Fire & Security, is finishing up the door hardware installation in building 17 (Forum) this week and will be moving to building 18 next week. The installation in the Child and Family Education complex and at the Florence campus is scheduled to begin the week of June 14 with Enrollment and Student Financial Services, building 1, scheduled for late June. Contact Dave Smith, 3433.
June 3, 2010
BLT (Bond Leadership Team) Update
Track and Soccer Bowl Upgrades: I am pleased to report that there has been a very successful resolution to the athletic field design issue which emerged over the last couple of weeks. The Health/PE/Athletics project user group (PUG) has agreed to a proposal that maintains most of the original athletic field bond-funded upgrade plan with one change: the new turf soccer field will be located north of the current grass soccer field rather than replace it.
The Bond Leadership Team is recommending this solution to Lane's Executive Team for expected approval. As a result, Lane will have use of both the old and new soccer fields for the foreseeable future. The change keeps the project within budget, allows construction to proceed on schedule, and adds to capacity while allowing for future buildings.
Thanks to all involved parties including the Bond Leadership Team, Facilities Council, Bond Management Leadership Team, VP Sonya Christian, U of O Associate Professor Mark Gilham and his Urban Design Lab students, landscape architects Cameron, McCarthy, Gilbert and Sheibe and especially the PUG for their vision and flexibility. Alen Bahret, Bond Leadership Team Chair, 3347.
May 25, 2010
DOWNTOWN CAMPUS BUILDING
Proposals from architects who are interested in providing services for the Downtown Campus building are due on Friday, May 28 at 2 p.m. In the following weeks a selection committee will review and score the proposals, decide which firms (if any) to interview, conduct and evaluate interviews and make a prioritized list of firms to recommend to the board of education on June 9. For further information, contact Bob Mention, Project Manager, 5747; Bob Baldwin, Procurement, 5574; or visit the bond website at http://2011sitearchive.lanecc.edu/bond/updates.html.
May 18, 2010
BOND UPDATE
ASBESTOS ABATEMENT
Tunnel pipe insulation now 100 percent complete; and mechanical rooms 30 percent complete. Contact Angela Fazio, 541-463-3428.
BUILDING 2 REMODEL
On Wednesday morning, May 19, the sidewalk west of building 2 will be closed while the contractor delivers and installs a new transformer. The elevator at the northwest corner will be unavailable during this time. In addition, the new access floor at the Data Center is being installed. Next week, metal studs and drywall will be installed for the new walls. Contact David Amundson, 541-463-3455.
BUILDING 4 REMODEL
Contractors have mobilized to the site for demolition and to begin framing on the second level of the building. This activity is expected to cause loud noises at times and a burning metal smell when steel wall studs are cut to size will be noticed in the vicinity. This work is expected to last for the rest of the term. This week, contractors will be installing new air ducts for the new HVAC system in the open hallways and breezeways. The new ductwork will not be connected to the existing air system until the end of June. Contact Mark Richardson, 541-463-3456.
BUILDING 5 REMODEL AND ADDITION
No construction work is scheduled to begin inside building 5 until June 11. Contact Mark Richardson, 541-463-3456.
CAMPUSWIDE CONCRETE REPAIR
Drawings for the project are compete. The first project is expected to begin on the south side of building 10 with the construction of a new ADA access ramp and stairs for better campus access. In addition, crews will be reconstructing the stairs, sidewalks, and crosswalks on the north end of the Lane Transit bus depot with work extending along the north side of building 4. Contact Mark Richardson, 541-463-3456.
FIRE ALARM/MASS COMMUNICATION
The fire alarm contractor, SecureCom, is 99 percent complete with the installation and testing. Testing the system in the presence of the Oregon state fire marshall is scheduled for the third week of June between spring and summer terms. Contact Dave Smith, 541-463-3433.
KEYLESS ENTRY
The contractor, Allied Fire & Security, is working on door hardware installations in Building 16. Next week, they will return to Center building to finish their work there. Lane has contracted with an outside consultant to perform a wireless network survey on campus in order to determine areas that wireless network coverage is inadequate. Additional exterior wireless access points will be installed to allow wireless network coverage to all areas of the 30th Avenue campus and will facilitate Public Safety communications and the keyless entry system. Contact Dave Smith, 541-463-3433.
TRACK AND SOCCER BOWL UPGRADE
Mobilization of equipment will begin May 14, weather permitting. There will be an increased amount of truck traffic throughout the north parking lot and the access road on the south side of the soccer field. The access road, gravel-parking area between playing fields, and the parking area north of building 5 are now closed. Access to the lower part of the building is available by using the sidewalk on the north end of building 6. Special parking needs by permit only have been moved to the north parking lot. Contact Mark Richardson, 541-463-3456.
UTILITY METERING
Installation of meters on electrical, domestic hot and cold water, natural gas, chilled and heating water and irrigation will allow for utility monitoring, performance evaluation and energy maximization. Final mechanical inspections complete. Final electrical inspections passed on all campuses. System commissioning to be carried out by in-house personnel. Contact Angela Fazio, 541-463-3428.
May 11, 2010
DOWNTOWN CAMPUS BUILDING
The Request for Proposals (RFP) for architectural services is being prepared and is expected to be issued in the near future. Contact Bob Mention, 541-463-5747.
May 4, 2010
BOND UPDATE
ASBESTOS ABATEMENT
After removing all asbestos from pipes in the tunnels and mechanical room during Deferred Maintenance 2009, crews are currently working to install new insulation on the chilled, heating, and domestic hot water lines in the tunnel and mechanical rooms. Remaining tunnel work is 90% complete; and remaining mechanical room work 33% complete. Contact Angela Fazio, 3428.
BUILDING 4 REMODEL
Construction scheduled to begin May 3 with the contractor performing light demolition work in selected areas on both the first and second floors of the building. This activity is expected to be noisy at times, during the day and evening hours. At the beginning of the week of May 10, temporary fencing will be placed in and around the areas of Building 4 blocking access to the upper floor of the building. After fencing is installed, access to certain areas of the building will require advance notice to the general contractor before entering the area. Contact Mark Richardson, 3456.
BUILDING 5 REMODEL AND ADDITION
Limited demolition activities will begin in Building 5 on June 11. The northwest stair tower inside building 5 is scheduled to be closed from June 11-17 to remove material suspicious of containing asbestos. Contact Mark Richardson, 3456.
CAMPUSWIDE CONCRETE REPAIR
Drawings for the project are complete. The first project is expected to begin on the south side of Building 10 where a new ADA access ramp and stairs will be constructed which will allow better campus access. This summer, work will begin at the campus main entrance where crews will reconstruct the stairs, sidewalks, and crosswalks that extend from the north end of the Lane Transit bus station through the north side of Building 4. Contact Mark Richardson, 3456.
DOWNTOWN CAMPUS BUILDING
A Request for Proposals (RFP) for architectural services is expected to be issued in the near future. The schedule calls for the selection process to be completed and a firm recommended to the board at its June meeting. The successful architect will confirm the feasibility report program before starting the schematic design phase of the work. Contact Bob Mention, 5747.
FIRE ALARM/MASS COMMUNICATION
The fire alarm contractor, SecureCom, is 99% complete with the installation and testing of the alarm and communications system. Their work remaining is the testing of certain aspects of the system in the presence of the Oregon State Fire Marshall, providing site training on the computer operating software, and obtaining, and providing the final Operations and Maintenance manuals to the college. Contact Dave Smith, 3433.
KEYLESS ENTRY
The contractor, Allied Fire & Security, is working to complete door hardware installations on the fourth floor of the Center Building. Buildings 1 and 16 will be next. The contractor and Lane programmer/analysts are currently working on an interface between the R25 scheduling software and the keyless entry system so that scheduling a conference room or classroom via the R25 program will automatically unlock related outside doors. Contact Dave Smith, 3433.
TRACK AND SOCCER BOWL UPGRADE
Mobilization of equipment is going to start May 1 which means there is going to be an increased amount of truck traffic through the north parking lot. The access road, gravel parking area between playing fields, and the parking area north of Building 5 will be closed starting May 14 and will remain closed until September 20. This area will be limited to construction traffic only as well as very limited pedestrian access. Contact Mark Richardson, 3456.
UTILITY METERING
Installation of meters on electrical, domestic hot and cold water, natural gas, chilled and heating water and irrigation will allow for utility monitoring, performance evaluation and energy maximization. Final inspections are complete; final electrical inspections still to be completed. Underwriter Laboratory (UL) performed a site audit and has approved all documents provided by MeasureLogic. Contact Angela Fazio, 3428.
March 2, 2010
BOND UPDATE:
BUILDING 2 REMODEL
Construction Manager/General Contractor proposals will be submitted for consideration on March 2. Commissioning Agent proposals are expected to be submitted on March 5. Contact David Amundson, 3455.
BUILDING 6 PERFORMING ARTS ELEVATOR AND REMODEL
Architectural work to complete construction documents continues. Contact David Amundson, 3455.
BUILDINGS 10 & 11, RTEC, RECYCLE CENTER, ART & APPLIED DESIGN, AND SPECIALIZED SUPPORT SERVICES
Consultants are being contracted to do masonry testing, geotech research, asbestos survey, and utility locates as background to the construction documents. Contact David Amundson, 3455.
BUILDING 19 BUSINESS DEPARTMENT OFFICES REMODEL
Architectural work to complete construction documents continues. Contact David Amundson, 3455.
DOWNTOWN CAMPUS BUILDING
The feasibility report is nearly complete. The consultants will present the report to the project steering committee and management team on Wednesday, March 3 later in the afternoon. Contact Bob Mention, 5747.
FIRE ALARM/MASS COMMUNICATION SYSTEM
The fire alarm contractor, SecureCom, is currently installing the mass notification system in Administration, building 3, and the Public Safety annex, building 13. This will provide the capability to broadcast an emergency message campus wide from a centralized location. User training on the fire alarm is scheduled early March. Additional work remains in buildings 7, 12 and the Family and Child Education complex for the system to be completed. Contact Dave Smith, 3433.
KEYLESS ACCESS
The contractor, Allied Fire & Security, is installing hardware on building 6 and 19 this week. Four CCTV cameras were installed on Facilities, building 7, as part of a camera evaluation. The results of the test will help to arrive at a decision as to the most appropriate cameras to install as part of the Keyless Access project. Contact Dave Smith, 3433.
TRACK AND SOCCER BOWL UPGRADES
Work in the development phase continues. Contact Todd Smith, 5132.
February 23, 2010
BOND UPDATE:
ASBESTOS ABATEMENT
Crews continue work installing new insulation on the cold and hot water lines in the tunnel system and mechanical rooms. Contact Angela Fazio, 3428.
BUILDING 2 REMODEL
Construction documents are under review. Contact David Amundson, 3455.
BUILDING 4 REMODEL AND BUILDING 5 REMODEL/ADDITION
GDB architecture is working on completing construction documents so permits can be obtained from Lane County. Classroom construction is expected to start mid June and will be completed by the fall term. A meeting is being scheduled to work with the user group on plans for the relocation of the Dental Clinic for the summer. A few locations were identified and viewed for consideration, but none have selected at this time. Contact Mark Richardson, 3456.
BUILDING 6 PERFORMING ARTS ELEVATOR AND REMODEL
Work to complete construction documents continues. Contact David Amundson, 3455.
BUILDINGS 10 & 11, RTEC, RECYCLE CENTER, ART & APPLIED DESIGN, AND SPECIALIZED SUPPORT SERVICES
Design development work continues. Contact David Amundson, 3455.
BUILDING 19 BUSINESS DEPARTMENT OFFICES REMODEL
Review of the construction documents continues. Contact David Amundson, 3455.
BUILDING 19 FOUNDATION AND WORKFORCE DEVELOPMENT
Some furniture arrived for the Foundation office and have been installed. More furniture is expected to be delivered this week. Painting contractors will be working inside the Foundation office over the next two weeks completing items on the punch list. Contact Mark Richardson, 3456.
COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEM
Data collection continues. PUG webinars to be scheduled. Contact Angela Fazio, 3428.
DOWNTOWN CAMPUS BUILDING
The project manager and architects presented a design concept, estimate of project expenses, and anticipated sources of funds to the steering committee on February 17. While the steering committee liked the design concept very much, there was concern and discussion about how to align the scope of the project with the anticipated level of funds.
This week the consultants will continue to develop the design concept, investigate ways to reduce the project scope, refine the cost estimates, and explore other potential sources of funds. There is no on-campus meeting scheduled this week. The next and final presentation to the steering committee is scheduled on March 3. Contact Bob Mention, 5747.
FIRE ALARM/MASS COMMUNICATION SYSTEM
The fire alarm contractor, SecureCom, is currently installing the mass notification system in Administration, building 3 and the Public Safety annex, building 13. This will provide the capability to broadcast an emergency message campus wide from a centralized location. User training on the fire alarm is scheduled early March. Additional work remains in buildings 7, 12 and the Family and Child Education complex for the system to be completed. Contact Dave Smith, 3433.
FLORENCE CENTER UPGRADES AND SCIENCE LAB ADDITION
Bineham construction will be working all next week to complete the final stages of the siding work and FMP bond crews have been sent to Florence to complete some minor repairs needed before painting the building can begin. The minor repairs include replacing damaged vents on the outside of the building, removing and replacing an old damaged door, and other small items. Open house is scheduled for March 5, 2009 and a large number of visitors including the local media are expected to attend.
KEYLESS ACCESS
The contractor, Allied Fire & Security, is installing hardware on building 6 this week. Various rough in work continues in building 16 including the mounting of electronic enclosures in the crawlspace and basement locations. Four CCTV cameras were installed on Facilities, building 7, as part of a camera evaluation. The results of the test will help to arrive at a decision as to the most appropriate cameras to install as part of the Keyless Access project. Contact Dave Smith, 3433.
SOLAR LAB STATION
Conceptual designs are under review by FMP and program staff. Contact Mark Richardson, 3456.
TRACK AND SOCCER BOWL UPGRADES
Work in the development phase continues for the track and soccer bowl project. Contact Todd Smith, 5132.
UTILITY SUBMETERING
Final mechanical inspections are complete; final electrical inspections still to be conducted upon resolution of an Underwriter Laboratory (UL) certification of monitoring devices. UL performed a site audit and when made available, the testing reports will be reviewed. MeasureLogic is to provide requested information for UL evaluation. Contact Angela Fazio, 3428.
February 16, 2010
BOND UPDATE:
AMTF IMPROVEMENTS
The Aviation Maintenance training facility paint booth airflow modifications completed this week. An independent testing company to measure air profile. Rohner will be on site this week to complete exterior finishes. Final electrical and plumbing inspections passed and final building inspection is expected next week. Contact Angela Fazio, 541-463-3428.
ASBESTOS ABATEMENT
Crews continue work installing new insulation on the cold and hot water lines in the tunnel system and mechanical rooms. Remaining tunnel work 28 percent complete; remaining mechanical room work 19 percent complete. Contact Angela Fazio, 541-463-3428.
BUILDING 2 REMODEL
Construction documents are under review. Contact David Amundson, 541-463-3455.
BUILDING 4 REMODEL AND BUILDING 5 REMODEL/ADDITION
Soils testing is scheduled for February 17 at 8 a.m. The testing agency will be sectioning off small areas north of building 5 where they will remove large amounts of soil to obtain samples. When soil sampling is complete, the holes will be backfilled and all sectioned areas will be reopened. Contact Mark Richardson, 541-463-3456.
BUILDING 6 PERFORMING ARTS ELEVATOR AND REMODEL
Work to complete construction documents continues. Contact David Amundson, 541-463-3455.
BUILDINGS 10 & 11, RTEC, RECYCLE CENTER, ART & APPLIED DESIGN, AND SPECIALIZED SUPPORT SERVICES
Design development work continues. Contact David Amundson, 541-463-3455.
BUILDING 19 BUSINESS DEPARTMENT OFFICES REMODEL
Review of the construction documents continues. Contact David Amundson, 541-463-3455.
BUILDING 19 FOUNDATION AND WORKFORCE DEVELOPMENT
Furniture ordered for the Foundation office is scheduled to arrive February 17. FMP carpenters will be on site to assemble and install the furniture and this work is expected to cause some dust and noise at times. Contact Mark Richardson, 541-463-3456.
COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEM
Two of three vendor site visitations planned were completed. Data collection continues. PUG webinars to be scheduled. Contact Angela Fazio, 541-463-3428.
DOWNTOWN CAMPUS BUILDING
Work on the Phase 1 Feasibility Report is fast approaching the finish line - the March meeting of Lane’s Board of Education. Work sessions with the project steering committee and management team are scheduled for Tuesday and Wednesday this week. College consultants have continued to develop budget options and concept designs. The cost estimate for the concept designs will be
presented to the committee at the Tuesday work session. Contact Bob Mention, 541-463-5747.
FIRE ALARM/MASS COMMUNICATION SYSTEM
The fire alarm contractor, SecureCom, is currently installing the mass notification system in Administration, building 3 and the Public Safety annex, building 13. This will provide the capability to broadcast an emergency message campus wide from a centralized location. User training on the fire alarm is scheduled for late February or early March. Additional work remains in buildings 7, 12 and the Family and Child Education complex for the system to be completed. Contact Dave Smith, 541-463-3433.
KEYLESS ACCESS
The contractor, Allied Fire & Security, will start installing hardware on a few doors in building 5 on Tuesday. Later during the week, hardware installation will begin on building 6. Various rough in work continues in building 16 including the mounting of electronic enclosures in the crawlspace and basement locations. Four CCTV cameras were installed on Facilities, building 7, as part of a camera
evaluation. The results of the test will help us arrive at a decision as to the most appropriate cameras to install as part of the Keyless Access project. Contact Dave Smith, 541-463-3433.
SOLAR LAB STATION
Conceptual designs remain under review by FMP and program staff. Contact Mark Richardson, 541-463-3456.
TRACK AND SOCCER BOWL UPGRADES
Work in the development phase continues for the track and soccer bowl project. Contact Todd Smith, 541-463-5132.
UTILITY SUBMETERING
Final mechanical inspections are complete; final electrical inspections still to be conducted upon resolution of an Underwriter Laboratory (UL) certification of monitoring devices. UL performed a site audit and when made available, the testing reports will be reviewed. MeasureLogic is to provide requested information for UL evaluation. Contact Angela Fazio, 541-463-3428.
February 9, 2010
BOND UPDATE: BUILDING 2 REMODEL
The Board of Education has agreed to pursue the Construction Manager/General Contractor method of project delivery. An RFP for the CM/GC will go out soon, and a selection committee will submit a ranked list by March 2. Construction documents for the project are expected from the architect on Tuesday, February 9. Contact David Amundson, 541-463-3455.
BUILDING 4 REMODEL AND BUILDING 5 REMODEL/ADDITION
Project work continues in the construction document phase. On Friday, February 12, the engineering group will be doing investigation work inside the Dental Clinic and in building 4 offices 131, 133, 135, and 137. Contact Mark Richardson, 541-463-3456.
BUILDING 6 PERFORMING ARTS ELEVATOR AND REMODEL
Users have requested changes to the design. The architects are updating the design and will complete the construction documents in the next few weeks. Contact David Amundson, 541-463-3455.
BUILDINGS 10 & 11, RTEC, RECYCLE CENTER, ART & APPLIED DESIGN, AND SPECIALIZED SUPPORT SERVICES
The architects presented an updated estimate which included cost-cutting changes. The estimate shows that the project as revised is close enough to the budget that they will continue with design development. Contact David Amundson, 541-463-3455.
BUILDING 19 BUSINESS DEPARTMENT OFFICES REMODEL
Review of the construction documents continues. Contact David Amundson, 541-463-3455.
BUILDING 19 FOUNDATION AND WORKFORCE DEVELOPMENT
The architect has completed a punch list for the remodeled area in the Workforce Development Department classrooms and office space built for the Foundation staff. Work to correct items on the punch list has started and should be completed by February 19. Furniture is expected to arrive this week for the Foundation offices and FMP carpenters will do most of the installation. The assembly and installation of the furniture inside the offices is expected to cause some dust and noise at times. Contact Mark Richardson, 541-463-3456.
DOWNTOWN CAMPUS BUILDING
Work on the feasibility report is progressing nicely. The project manager, architects and consultants have been meeting with a broad group of college staff and a representative of the City of Eugene to learn about the space and other conditions each occupant needs to function. The downtown campus building project currently includes a student housing component. The team is working on the number and mix of units as well as the financial considerations. Design options for the academic, tenant and housing components are being created and evaluated and funding possibilities explored. Contact Bob Mention, 541-463-5747.
FLORENCE CENTER REMODEL AND SCIENCE LAB ADDITION
Lane's bond workforce will travel to the Florence Center several times over the next two weeks to complete minor repairs on the outside of the building. The crew will also work inside the new science classroom addition installing white boards and other small items. Contact Mark Richardson, 541-463-3456.
SOLAR LAB STATION
Conceptual designs remain under review by FMP and program staff. Contact Mark Richardson, 541-463-3456.
TRACK AND SOCCER BOWL UPGRADES
Work in the development phase continues for the track and soccer bowl project. Contact Todd Smith, 541-463-5132.
February 2, 2010
BOND UPDATE: BUILDING 2 REMODEL
Construction documents remain under review. Contact David Amundson, 541-463-3455.
BUILDING 4 REMODEL AND BUILDING 5 REMODEL/ADDITION
The project is currently in the construction document phase and with that comes the work of engineers, architects, and specialty contractors who are focusing on the buildings inside and outside gathering relevant information necessary to prepare the construction documents. Work that may include opening classroom doors and looking at the inside from windows might be distracting but this activity is not typically disruptive.
Over the next few weeks, two testing agencies will be on the site to conduct surveys for information required for new construction. PBS is currently conducting an asbestos survey of building 5 that will allow Lane to hire a contractor to remove anything that might contain asbestos. Removing the asbestos from areas recommended is expected to start in May and will take several weeks to complete. FEI will be performing soils testing that will include using large equipment on the north side of building 5 to obtain a sample from below the asphalt so engineers can determine a foundation design. This activity is not expected to start until the first week of February. Contact Mark Richardson, 541-463-3456.
BUILDING 6 PERFORMANCE HALL ELEVATOR AND REMODEL
Construction documents remain under review. Contact David Amundson, 541-463-3455.
BUILDINGS 10 & 11, RTEC, RECYCLE CENTER, ART & APPLIED DESIGN, AND SPECIALIZED SUPPORT SERVICES
The project remains in the schematic design phase and project managers continue cost estimating of the master plan. The master plan shows major renovation of building 10, as well as a moderate amount of renovation in building 11. Building 10 renovations include allocated space for the new RTEC program, a Recycling Center, and area for relocating the Art and Applied Design studio art programs from building 11. The vacated area of building 11 will be remodeled specifically for use by the Specialized Support Services program. Contact Todd Smith, 541-463-5132.
BUILDING 19 BUSINESS DEPARTMENT OFFICES REMODEL
Construction documents remain under review. Contact David Amundson, 541-463-3455.
BUILDING 19 FOUNDATION
Lane has requested that the contractor return to the project site to make some additional corrections. A complete list of corrections issued by the architect for the area is expected next week. When the list of corrections is issued, the contractor will return to the project site likely causing noise and dust for a short period of time. Window covering is scheduled to be installed in the new Foundation office on February 5 and should not take more than three days to complete. Contact Mark Richardson, 541-463-3456.
DOWNTOWN CAMPUS BUILDING
Work on the feasibility report continues. The project manager and architects will meet with the steering committee and the management team on Tuesday and Wednesday this week. The meetings have several objectives: to obtain more space programming information, to present some information about the student housing option, to present some financial information, and to look at some building massing options. Contact Bob Mention, 541-463-5747.
FLORENCE CENTER REMODEL AND SCIENCE LAB ADDITION
Bineham construction is working on a list of corrections listed by the architect who inspected their work last week. Exterior painting is on hold awaiting better weather. Invitations have been extended to the public to attend an open house at the Florence Center campus scheduled on February 26, at 10:00 a.m. This community open house gives visitors an opportunity to view the upgrades that have been made to the facility. Contact Mark Richardson, 541-463-3456.
SOLAR LAB STATION
Conceptual designs submitted by architects remain under review by FMP and program staff. Contact Mark Richardson, 541-463-3456.
TRACK AND SOCCER BOWL UPGRADES
Work in the development phase continues for the track and soccer bowl project. Contact Todd Smith, 5132.
January, 26 2010
BOND UPDATE:
BUILDING 2 REMODEL
Construction documents submitted December 18 are under review. Contact David Amundson, 541-463-3455.
BUILDING 4 REMODEL AND BUILDING 5 REMODEL/ADDITION
Design documents have been completed and the projects have moved into the construction document phase. The construction documents are expected to take several months to complete and actual construction activities should begin this summer. Last week, construction coordinators worked with building 4 occupants to determine a temporary office space location to use during the remodeling phase.
Over the next few weeks, three testing agencies will be on the site to conduct surveys for information that is required for new construction. PBS is conducting an asbestos survey of building five that will allow Lane to hire a contractor to remove anything that might contain asbestos. The removal of asbestos in areas recommended is expected to begin in May 2010 and will take several weeks to complete. GPR Data will be on the site the week of January 25 to conduct a survey on the existing brick walls to identify locations for installing steel reinforcement, and FEI will be performing soils testing that will include using large equipment on the north side of building five to obtain soil from beneath the asphalt so engineers can determine a foundation design. This activity is not expected to begin until the week of February 1. Contact Mark Richardson, 541-463-3456.
BUILDING 6 PERFORMANCE HALL ELEVATOR AND REMODEL
Construction documents were submitted on December 18 and are under review. Contact David Amundson, 541-463-3455.
BUILDING 10, RTEC, RECYCLE CENTER, SPECIALIZED SUPPORT SERVICES
The project continues in the schematic design phase and project managers are cost estimating the master plan. Contact Todd Smith, 541-463-5132.
BUILDING 19 BUSINESS DEPARTMENT OFFICES REMODEL
Review of construction documents submitted continues. Contact David Amundson, 541-463-3455.
BUILDING 19 / FOUNDATION
Foundation office construction is complete. Office furniture is expected to be delivered and assembled by FMP carpenters and electricians. Foundation staff should be allowed occupancy by the first week of February 2010. Contact Mark Richardson, 541-463-3456.
DOWNTOWN CAMPUS BUILDING
Development of the downtown campus building project will proceed in three phases: Phase 1, Feasibility Report; Phase 2, Design and Contract documents; and Phase 3, Construction and Move-in. The Phase 1-Feasibility Report has just begun. Gerding Edlen, a project management firm, was hired to work with the college to prepare the report. The feasibility report is scheduled to be completed sometime in March.
Two and a half days of intensive meetings occurred last week. On January 19, the project manager and architects met with the college steering committee and representatives from the city to conduct an Eco-charette. The following day and a half was spent in meetings of about an hour each where the leads of the various units informed the project manager and architects about the space needs and functions performed by their units. At the end of the week, the steering committee had a good idea of what a high-performing healthy building means and the architects had a good idea of the instructional space requirements. Added to this was information gained about what space the city might lease and what the student housing component might be. This week the project manager will be working on funding and tenant issues and the architects will be creating some design concepts. Contact Bob Mention, 541-463-5747.
[Editor's note: Today's Register-Guard reports, "The Eugene City Council on Monday unanimously selected Lane Community College to redevelop the half block on West 10th Avenue..." See the full story online at http://registerguard.com/csp/cms/sites/web/news/cityregion/24392090-41/lcc-college-council-spilde-building.csp ]
FLORENCE CENTER REMODEL AND SCIENCE LAB ADDITION
Last week the remodel project reached substantial completion and the new science addition is now being used as a classroom. This week, Bineham Construction is working on a list of correction items brought forward by architects during the week of January 11; all corrections items listed are nearly complete and the classroom is ready for inspection preliminary siding and roof inspection was completed on January 17 and a list of correction items were noted. The architect will distribute the list for correction this week beginning January 25. Contact Mark Richardson, 541-463-3456.
SOLAR LAB STATION
FMP and program staff continue to review conceptual designs submitted by architects. This project is being developed and set up as an interactive project for hands on instruction for students and discussions continue with the welding shop to have welding program students complete the steel stair construction. Contact Mark Richardson, 541-463-3456.
TRACK AND SOCCER BOWL UPGRADES
Progress continues on the design development phase of the track and soccer bowl project. Contact Todd Smith, 541-463-5132.
January 12, 2010
BOND UPDATE:
BUILDING 2 REMODEL
Construction documents submitted December 18 are being reviewed. Contact David Amundson, 541-463-3455.
BUILDING 4 REMODEL AND BUILDING 5 REMODEL/ADDITION
Design documents have been completed and the projects are now moving into the construction document phase. The construction documents are expected to take a few months to complete and actual construction activities should begin by summer. Construction coordinators are now working with building 4 occupants to determine a location for temporary office space to use during the remodeling phase. Contact Mark Richardson, 541-463-3456.
BUILDING 6 PERFORMANCE HALL ELEVATOR AND REMODEL
Construction documents were submitted on December 18 and are being reviewed. Contact David Amundson, 541-463-3455.
BUILDING 19 BUSINESS DEPARTMENT OFFICES REMODEL
Construction documents are being reviewed. Contact David Amundson, 541-463-3455.
BUILDING 19 FOUNDATION
Foundation office construction is complete. Office furniture is expected to be delivered the week of January 25 and will be installed by FMP carpenters and electricians. Foundation office staff should find their space furnished and occupancy allowed by the first week of February 2010. Contact Mark Richardson, 541-463-3456.
DOWNTOWN CAMPUS BUILDING
Development of the downtown campus building project will proceed in three phases: Phase 1, Feasibility Report; Phase 2, Design and Contract documents; and Phase 3, Construction and Move-in. The Phase 1-Feasibility Report has just begun. Gerding Edlen, a project management firm, has been hired to work with the college to prepare the report. In summary, the Feasibility Report will assemble a project budget, identify the occupants of the building, and prepare a concept level building design that is affordable. Occupants include all of the college instructional and service units that are currently offered in the Downtown Center and the Wildish Building plus some elements of the Energy Management program. Other potential tenants such as student housing, city agencies and/or commercial ventures are being investigated. The Feasibility Report is scheduled to be completed sometime in March. Contact Bob Mention, 541-463-5747.
FLORENCE CENTER REMODEL AND SCIENCE LAB ADDITION
The remodel project has reached substantial completion and the new science addition is now being used as a classroom. FMP electricians installed most data outlets on January 7 and expect to finish early during the week of January 11. Also scheduled this week is the installation of AV equipment. Two other items added to the project were roof and new siding installation. Both tasks have been completed and now the building is ready for a new coat of paint. Contact Mark Richardson, 541-463-3456.
SOLAR LAB STATION
The conceptual designs are complete and have been submitted by architects and are now in review by FMP and program staff. This project is being developed and set up as an interactive project for hands on instruction for students and discussions are currently underway with the welding shop to have welding program students complete the steel stair construction. Contact Mark Richardson, 541-463-3456.
December 15, 2009
BOND UPDATES:
BUILDING 1 DATA CLOSET REMODEL
LA Kersh Architects produced a design for a data closet remodel in Building 1 and bid proposals for the work will be requested from interested contractors. Contact Dave Smith, 3433.
BUILDING 2 REMODEL
The architects and engineers continue work on project construction documents. Northwest Information Services has begun work to design the remodel of the data center. Contact David Amundson, 3455.
BUILDING 4 REMODEL
A focus is on exploring the total replacement and relocation of the heating, ventilation and air conditioning system. Contact Todd Smith, 5132.
BUILDING 5 REMODEL/ADDITION
A focus is on exploring the total replacement and relocation of the heating, ventilation and air conditioning system. Contact Todd Smith, 5132.
BUILDING 6 PERFORMING ARTS ELEVATOR & DANCE STUDIO
The architect is moving into the construction document phase. Contact Todd Smith, 5132.
BUILDING 10, RTEC, RECYCLE CENTER, SPECIALIZED SUPPORT SERVICES
A master plan of the covered area between buildings 9 and 10, and the first floor of building 11 is complete. The project has moved into the schematic design phase and project managers continue cost estimating of the master plan. Contact Todd Smith, 5132.
BUILDING 18 GREEN PLUS FACULTY OFFICES
This project is on hold pending review. Lane Community College has collaborated with U of O to perform a campus wide study of building locations and future expansions. For further information, contact Mark Richardson, 3456
BUILDING 19 BUSINESS FACULTY OFFICES
Review of the architectural drawings by the users continues. Construction is expected to begin during the summer 2010. Contact David Amundson, 3455.
BUILDING 19 FOUNDATION
Construction of the Foundation office has entered into the second phase. Construction started in the new location of the Foundation a month ago with an expected completion of mid-January. Interior painting contractors are painting the office with an expected completion date of December 21. Carpet installation for phase two is scheduled for the first week in January 2010. Contact Mark Richardson, 541-463-3456.
CENTER BUILDING REROOF
All punch list items have been completed and another Carlisle inspection concluded satisfactorily this week. The final building inspection for this project is pending. Contact Angela Fazio, 3428.
DOWNTOWN CAMPUS BUILDING
Ten proposals were submitted from architectural firms in response to the Request for Proposals. The selection committee will score them and decide which firms to interview before making a recommendation. Meanwhile, the downtown campus building leads met to continue the space programming work. Gerding Edlen has met with President Spilde, college administrators and representatives of the city to discuss the primary criteria for the project. GE has also started collecting information about the site. Contact Bob Mention, 5747.
FLORENCE CENTER/SCIENCE LAB ADDITION
The Florence Campus construction completes in three separate phases. Floor covering installation expected on December 17 and will be ready for classroom furnishings by December 21. The roofing project is complete. Final inspection by the architect will take place during the next construction meeting. Siding removal and installation has proven to be a challenge in some areas of the building because of dry rot found during the removal. The architect inspected the areas and made a repair recommendation to remove the infected areas before new siding is installed. Contact Mark Richardson, 541-463-3456.
TRACK AND SOCCER BOWL UPGRADES
The track and soccer bowl project progresses in the design development phase. Contact Todd Smith, 5132.
December 8, 2009
BOND UPDATE:
BUILDING 2 REMODEL
The architects and engineers are continuing work on the project construction documents. Northwest Information Services has begun their work to design the remodel of the data center. Contact David Amundson, 3455.
BUILDING 4 REMODEL
The schematic design phase of the second floor is nearing completion. A focus is now on exploring the total replacement and relocation options for the heating, ventilation and air conditioning system. Contact Todd Smith, 5132.
BUILDING 5 REMODEL/ADDITION
The schematic design phase is nearly complete. A focus is on exploring the total replacement and relocation options for the heating, ventilation and air conditioning system. Contact Todd Smith, 5132.
BUILDING 6 PERFORMING ARTS ELEVATOR & DANCE STUDIO
Agreement on the general floor plan for the elevator addition and the remodel has been settled, and the architect is moving into the construction document phase. Contact Todd Smith, 5132.
BUILDING 10, RTEC, RECYCLE CENTER, SPECIALIZED SUPPORT SERVICES
A master plan of the covered area between buildings 9 and 10, and the first floor of building 11 is complete. The project is moving into the schematic design phase and project managers begin cost estimating of the master plan. Contact Todd Smith, 5132.
BUILDING 18 GREEN PLUS
The Bond Leadership Team has recommended that this project be placed on HOLD pending a master plan study of the site to verify the location and single floor type construction proposed. This project is now on HOLD status pending further study and review. Contact Mark Richardson, 3456
BUILDING 19 BUSINESS FACULTY OFFICES
Architectural drawings will be distributed to the users for review next week. Construction is expected to take place over the summer. Contact David Amundson, 3455.
BUILDING 19 FOUNDATION
Interior painting in the office planned to begin December 7 and fumes will be present in the area during the drying process. Carpet installation is scheduled for the first week of January 2010. Construction activity for the Foundation office was delayed slightly and completion is now expected late January 2010.
CENTER BUILDING REROOF
All punch list items are completed and the second Carlisle inspection was satisfactorily passed. Contact Angela Fazio, 3428.
DOWNTOWN CAMPUS BUILDING
The Downtown Campus building project will progress in three phases: Phase 1, Feasibility Report; Phase 2, Design and Construction Documentation; and Phase 3, Construction and Move-in. A request for proposals was issued, proposals were evaluated, and President Spilde informed Lane's Board of Education that the firm of Gerding Edlen had been selected to provide project management services to accomplish the Phase 1. Feasibility Report phase. The feasibility report is scheduled to be completed within 90 days. This will be a very fast and exciting project.
FLORENCE CENTER/SCIENCE LAB ADDITION
Completion of this project is expected January 4, 2010. Bineham Construction has pushed their crews and made up lost time encountered during the high winds. Roof installation is complete and siding installation will be completed late January 2010. Contact Mark Richardson, 541-463-3456.
TRACK AND SOCCER BOWL UPGRADES
The track and soccer bowl project has moved into the design development phase. Contact Todd Smith, 5132.
November 24, 2009
BOND UPDATE:
BUILDING 2 REMODEL
Northwest Information Services is beginning work on their design of the data center. They will coordinate work with the architect/engineer for the project. The program for the second floor has been revised to include faculty offices and additional classrooms. The architect will present the revised plans after the Thanksgiving holiday break. Contact David Amundson, 3457.
BUILDING 4 REMODEL
The schematic design phase of the second floor is nearing completion. A focus is now on exploring the total replacement and relocation options for the heating, ventilation and air conditioning system. Contact Todd Smith, 5132.
BUILDING 5 REMODEL/ADDITION
The schematic design phase is nearly complete. A focus is on exploring the total replacement and relocation options for the heating, ventilation and air conditioning system. Contact Todd Smith, 5132.
BUILDING 6 PERFORMING ARTS ELEVATOR & DANCE STUDIO
Agreement on the general floor plan for the elevator addition and the remodel has been settled, and the architect is moving into the construction document phase. Contact Todd Smith, 5132.
BUILDING 6 PERFORMING ARTS DANCE STUDIO ADDITION
The architect presented revised drawings for the Dance Studio addition north of building 6. In general, the user group was pleased with the direction of the design and offered direction for the next phase moving into schematic design. Contact David Amundson, 3457.
BUILDING 10, RTEC, RECYCLE CENTER, SPECIALIZED SUPPORT SERVICES
A master plan of the covered area between buildings 9 and 10, and the first floor of building 11 is complete. The project is moving into the schematic design phase and project managers begin cost estimating of the master plan. Contact Todd Smith, 5132.
BUILDING 18 GREEN PLUS OFFICE ADDITION
Berry Architecture will present the first schematic design of the office addition to the college on December 3. Soil testing and surveying of the grassed area south of building 18 will begin November 23. Soil and survey data collected will determine the exact location of the office addition. A closure of the sidewalk for a short time on the west side of building 17 will be necessary for placement of equipment. The equipment will create ground vibration and elevated noise levels at times. Construction of the office addition is expected to begin late January 2010. Contact Mark Richardson, 541-463-3456.
BUILDING 19 FOUNDATION
The walls of the new Foundation are complete and will be painted during the week beginning November 30. Painting of the interior will take place on off hours with ventilation fans to help prevent odors from disturbing building occupants. Contact Mark Richardson, 541-463-3456.
CENTER BUILDING FIRST FLOOR CLASSROOM
McKenzie Construction will begin making minor corrections on the ventilation system on the problems that were detected during the system test. The ventilation system is located above the ceiling and work to correct the problem is not expected to cause disruption. The general contractor is scheduled to make corrections next week to lighting issues apparent in the hallway and bathroom nearby. Contact Mark Richardson, 541-463-3456.
CENTER BUILDING ROOF
Weather permitting; Umpqua will continue their work on punch list items noted by the Carlisle inspection. Contact Angela Fazio, 3428.
DOWNTOWN CAMPUS BUILDING PROJECT
Planning for the phase 1 feasibility report is about to begin. The selection process to hire a project management firm and an architectural firm to do this work is underway. The schedule calls for a project management firm to be hired early December and the architectural firm early January. The feasibility report is scheduled to be completed by late March 2010 and presented to the board for consideration and approval before moving forward. Contact Bob Mention, Project Manager at 5747.
FLORENCE CENTER SCIENCE LAB ADDITION
McKenzie Commercial completed installation of wallboard inside the new addition that will be ready for painting by next week beginning Nov 30. Cabinets for the science lab will be installed on December 2. The siding installation continues on the east side of the building is expected to be completed by January 30, 2010. Bineham Construction has one small section of metal roof to complete before installing the remaining trim pieces. Contact Mark Richardson, 541-463-3456.
TRACK & SOCCER BOWL UPGRADES
The track and soccer bowl project has moved into the design development phase. Contact Todd Smith, 5132.
November 17, 2009
BOND UPDATE:
BUILDING 4 REMODEL & BUILDING 5 REMODEL/ADDITION
Programming work with PUGs on building 4 continues. PUG members in building 5 continue discussion around options for the building addition. Options for HVAC and ducting replacement necessary in both buildings 4 and 5 continue being explored.
BUILDING 10, RECYCLE CENTER, TEST CELL REPLACEMENT AND KILN
Programming work with the PUG for building 10 continues.
BUILDING 18 GREEN PLUS OFFICE ADDITION
A floor plan has been selected allowing the architect to proceed with the process of an initial design of the office building. The building has some exciting futures built in allowing staff members to feel more comfortable in their surroundings. This building will have radiant floor heat to keep the office comfortable year round and a ventilation system that will be using 100 percent filtered outside air. Some other features added to the new offices are no VOC material, natural lighting, and polished concrete floors with no floor covering material. The first set of initial drawings is expected to be handed to LCC on Dec. 3 showing some ideas of a building design and outlining some of the satiability features. Contact Mark Richardson, 541-463-3456.
BUILDING 19 WORKFORCE TRAINING & FOUNDATION
WORKFORCE TRAINING--
Construction of the new rooms are complete and now being used by workforce training staff. One of the rooms is being used as a classroom and the other as a resource room. Podiums have been ordered for the new classroom 263B and it is expected to arrive on campus during the week of Dec 7. AV equipment is being reviewed and may be ordered mid-Dec for room 263B. Completion of a new functioning classroom and new resource room enables staff to better serve the community affected by high unemployment and a struggling economy.
FOUNDATION OFFICE SUITE--
Demolition and new wall framing is complete for the new Foundation office. An electrical contractor is expected to start installation on Monday, Nov 16. This area has been designed to accommodate four full-time and two part-time staff members. A PUG meeting is scheduled for Nov 17 to talk about window coverings and other room décor options; insuring special attention is given in creating a welcoming atmosphere for clients and others who visit the new Foundation office.
CENTER BUILDING CLASSROOM
The classroom is completed and is currently being used by students. AV equipment is being reviewed for the classroom and should be order within the next two weeks. The staff bathroom continues to be under construction and is expected to be complete by the end of the week. An air balance check of HVAC system for the area is currently under review as minor issues of air balance were detected and require correction. Work to correct the balance of air flow in the classroom is expected to begin soon, and will not cause disruption to classroom activities. The result of the necessary repairs will make a more comfortable environment for students and staff who occupy the location.
CENTER BUILDING REROOF
Umpqua continues work on punch list items identified by the Carlisle inspection. A permit to construct and install the roof access stairs has been issued. Contact Angela Fazio, 3428.
DOWNTOWN CAMPUS BUILDING PROJECT
Thirty-seven people attended the mandatory pre-proposal meeting held on Tuesday, Nov 10. Those in attendance represented project management firms, architects, engineers, and real estate firms. The purpose of the meeting was to review the basic requirements of the Phase 1 feasibility report and to respond to feedback from potential proposers. The deadline for submitting proposals is Friday, Nov 20.
FLORENCE CENTER SCIENCE LAB ADDITION
Wood framing is complete for the new classroom and all the mechanical and plumbing rough-in has been installed. Sunset Electrical is working on finishing the electrical rough-in and expect to finish Monday, Nov 16. Insulation and wall board installation is expected to start on Nov 13 and should only take a few days to complete. The new roofing installation project is almost complete. The finished project is going to add a new look to the Florence campus with energy savings from added insulation on the roof surface. Metal roofing work is expected to be complete Dec 15. Though, Bineham is working hard to make up for lost time from a recent storm with wind gusts up to 70 mph, weather has and may continue to hinder the installation of the new siding causing the expected completion date to be pushed out to late Dec or even early Jan 2010. However, the extra time required to complete the siding is not expected to cause interference to staff or students.
SOLAR LAB STATION
gLAs is currently working on a study that will allow a solar panel system to be installed on the lower flat roof section of building 16. This lab will allow students studying energy management an opportunity for hands on training on installing solar panels. The study will determine if the location selected can be used and if it is a location suitable for consideration as a quality learning environment for the students. The study results compiled by gLAs Architecture are expected to be provided for the FMP planning team and the user groups by mid-Dec determine what steps will be taken next. Construction activities are projected to begin by late Jan 2010.
TRACK & SOCCER BOWL UPGRADES
Schematic design phase of the project continues.
November 10, 2009
BOND UPDATE:
BUILDING 18 GREEN PLUS OFFICE ADDITION
Lane has received a schematic design showing the footprint of the new offices. The drawings are currently being reviewed by the FMP planning team and comments are expected to be returned by Tuesday, Nov. 10. Design development is expected to start Nov. 12 and will be placed on a fast track so construction can start right away. Currently, the design shows a group of six offices with a specialized ventilation system to improve air quality. These sets of offices are specially designed to accommodate staff members that are sensitive to indoors and out door air quality.
BUILDING 19 WORKFORCE TRAINING & FOUNDATION
Work force Training: Classrooms are completed and crews are moving furnishings into the rooms to get ready for classes scheduled for Tuesday, Nov. 10. Final inspection is expected Friday, Nov. 6. This area now complete has two upgraded smart classrooms, storage closets with oak shelves and a new employee break room. The podiums were ordered for the classrooms last month and are expected to arrive on site the Dec. 1. LCC staff members are working to obtain completive price quotes for the AV equipment so an order can be placed this month. Installation of the equipment is not expected to start until spring term due to the high demand that is being placed on the AV staff members.
Foundation Office: Beginning on Monday, Nov. 9, FMP crews will be moving furniture out of the office, building 19, room 270 into Building 10 storage and afterwards, demolition will begin and is expected to last two or three days. The levels of noise will be increased during that time but is not expected to be disruptive to students. When demolition is completed, construction of the new foundation office will begin and should be completed by January 1, 2010.
CENTER BUILDING FIRST FLOOR CLASSROOM
Center building classroom addition is complete. The podium was installed under the deferred maintenance work this summer and the AV equipment is expected to be ordered this month. This classroom is one of the first classrooms that are currently under construction for the new access control system. Currently, the doors will lock automatically in the evening time and reopen for classes first thing in the morning. This system is one of many installed to protect the new smart classroom equipment that will be installed in the spring.
CENTER BUILDING REROOF
Umpqua working to complete the punch list items noted by Carlisle inspection.
DOWNTOWN CAMPUS BUILDING
The request for proposals from project management firms was published last Monday and the pre-proposal meeting is scheduled for Nov. 10. Proposals are due Nov. 20. Meanwhile, the RFPs from Architectural firms are being prepared. The first phase of work is for the successful project manager and architect to prepare a feasibility report.
SOLAR LAB STATION
This project is being reviewed by gLAs for location and accessibility. A feasibility study is expected to start late next week and should only take a total of two weeks to complete the study. FMP in conjunction with the Science department is working to select a location that is accessible to students to learn about solar energy. After a location has been determined a concept design will be completed by the architect and installation activities are expected to start in mid-January 2010.
FLORENCE CENTER
Construction activities are running on a tight schedule and are expected to be completed by January 1, 2010. Bineham construction is working with the subcontractors to complete the mechanical, electrical, and plumbing for the new science room addition. Interior insulation is expected to be completed by Nov. 9, followed by the wall board installation that is expected to start Nov. 11. Bineham construction is pushing forward trying to complete the new roof but is running into some weather related issues. The roofing project is expected to take longer than expected but should be finished mid-Dec.. The science lab is going to be equipped with smart classroom features. The podium was ordered last month and is expected to be delivered Dec. 1. Electronics for the smart classrooms will be ordered next week and installation of the AV equipment for the new science lab will be scheduled when the equipment is on site. Staff members are scheduled to return to the Florence campus on Nov. 12 to complete the installation of equipment previously installed during the deferred maintenance work this summer.
November 2, 2009
BOND UPDATE:
BUILDING 2 REMODEL
A PUG meeting has been scheduled for November 18.
BUILDING 4 REMODEL & BUILDING 5 REMODEL/ADDITION
Work with PUG members in building 4 continues on the programming of existing and new spaces. Work with PUG members in building 5 continues in looking at options for the building addition. Discussions continue around details on the first floor remodel and elevator installation. Exploring options for HVAC and ducting replacement necessary in both 4 and 5 buildings.
CENTER BUILDING FIRST FLOOR CLASSROOM
Center building classroom addition is complete. The contractors will be performing some additional owner requested punch list items but work identified is not expected to cause interruption in classroom schedules.
CENTER BUILDING REROOF
Umpqua is working on punch list items noted by Carlisle inspection.
DOWNTOWN CAMPUS BUILDING
The Request for Proposals (RFP) from project management firms to provide services has been advertised and issued. The RFP has already been sent to several firms and the deadline for submitting proposals is November 20. The schedule calls for the Board of Education to award a contract to the successful proposer at the board's December meeting.
BUILDING 6 PERFORMANCE HALL ELEVATOR & DANCE STUDIO
Another PUG meeting is planned for November 18. The architect is working on revisions to the Dance Studio.
FLORENCE CENTER
Room Addition: Construction activities are running on schedule and are expected to be completed by January 1, 2010.
TRACK & SOCCER BOWL UPGRADES
Work with the architects is complete in the development of the master plan. Projects within the master plan have been prioritized and the plan moves into the schematic design phase beginning with the red with architects in developing a master plan; next to move into the schematic design phase of the project.
BUILDING 10, RECYCLE CENTER, TEST CELL REPLACEMENT AND KILN
Work continues on the programming for RTEC, Art, Recycling Center, and SSS projects. An application for a grant for seismic upgrades for buildings 9 and 10 will be submitted for consideration.
BUILDING 18 GREEN PLUS OFFICES
A conceptual design is expected to be presented to Lane this week showing a basic footprint of the offices and their location. Information on the building design is expected to be presented with additional information on requested special features to improve air quality.
BUILDING 19 WORKFORCE TRAINING & FOUNDATION
Workforce Training: The workforce training remodel is scheduled to be completed this week ending November 6.
Foundation: Construction of the Foundation office has been delayed by a few days to allow the moving crew access to relocate the classroom furnishing that is currently in use. The relocation is expected to take place on Friday, November 6 and construction to begin November 9.
October 27, 2009
BOND UPDATE:
BUILDING 2 REMODEL
Architects are moving forward with schematic designs and will meet with the Project User Group this week.
DOWNTOWN CAMPUS BUILDING
A Request for Proposals (RFP) from interested, qualified Project Management firms is being prepared for release. The RFP is expected to be published within the next couple of weeks.
PERFORMANCE ARTS ELEVATOR AND DANCE STUDIO
The architect has begun schematic design and will meet with the project user group this week.
CENTER BUILDING FIRST FLOOR CLASSROOM
All of the parts and pieces have been located to place the classroom back into service. The contractor should be working on that area in the near future. The door operators, access control, and the lock sets are currently being adjusted to alleviate the issues with the classroom access. The activities are not expected to cause classroom disturbance and should be at a minimal noise level.
BUILDING 18 GREEN PLUS OFFICE ADDITION
A design meeting is scheduled to be held on October 23 to talk about the design and sustainability aspects of the project. Currently the new office addition will be located in the grass area south of building 18.
BUILDING 19 WORKFORCE TRAINING & FOUNDATION
Work force training - Construction for the classroom remodel in the workforce training area is nearing completion. The project is expected to be complete by October 30. When the classrooms are completed, a moving crew will start relocating furniture from the hallways and storage to furnish the classroom. This activity could start as early as October 28 and will result in outside doors being left open and drafty conditions inevitably in the front lobby area. Currently the mechanical subcontractor is completing work above the ceiling area which may cause some smells and dust. This phase of the construction in that area should be done soon and the contractor will be moving on the second part of the construction for the new Foundation office.
Foundation Office -
Design for the new foundation office is complete and construction is scheduled to start on November 2. Construction and demolition is expected to be noisy and cause dusty conditions in the area. The contractor will do their best to contain the dust and muffle the noise but everyone should expect a little of both. This is expected to last about 30 days with the construction being completed around December 11.
FLORENCE CENTER
Bineham Construction has completed the foundation and exterior framing for the new science room addition. Mechanical, electrical and plumbing is expected to start on Monday, October 26. In addition to the room construction, Bineham is also installing new metal roofing, exterior siding, and outside lights around the building. Starting next week contractor parking is expected to increase as the trades come to the site to complete their part of the project. This might cause some pressure on the parking but is not expected to cause complication for students and staff.
October 20, 2009
BOND UPDATE:
BUILDING 19 WORKFORCE TRAINING AND FOUNDATION
Phase 1 of the project in the Workforce Development area will be complete this week. The contractor will start next on the Foundation offices.
DOWNTOWN CAMPUS
The college continues to work towards acquiring the 10th and Charnelton site, and on a strategy for hiring consultants to assist the college with this project.
FLORENCE CENTER
Framing on the new classroom will be complete by the end of the week, sheathing, siding and roofing will follow. The roofing materials for the existing building arrived last week and installation will begin this week. Siding installation on the existing building continues.
September 1, 2009
BOND UPDATE:
BUILDING 2, PERFORMANCE HALL ELEVATOR & DANCE STUDIO
Architects and PUG continue to develop program material for the building 2 remodel and schematic design for elevator. Contract negotiations between the architect and college to add a Dance Studio to building 6 are underway.
CENTER BUILDING FIRST FLOOR CLASSROOM
Still on schedule for a September 15 completion. Light fixtures, doors and ductwork scheduled to be installed
BUILDING 19 WORKFORCE TRAINING & FOUNDATION
Remodeling of the Workforce Training area is continuing.
CENTER BUILDING REROOF
Contractor is continuing to install new roofing.
DOWNTOWN CAMPUS BUILDING
Nothing new to report.
PERFORMANCE HALL SEAT REPLACEMENT
New seats scheduled to be delivered to the college the week of September 7. Installation to follow.
FLORENCE CENTER
Contract is being finalized. Construction kick-off meeting scheduled for September 1. Addition scheduled to be complete for beginning of winter term.
TRACK & SOCCER BOWL UPGRADES
Eco-charrette scheduled Tuesday, September 1.
BUILDING 10, RECYCLE CENTER, TEST CELL REPLACEMENT AND KILN
Architect selection process is nearing completion. Board of Education is scheduled to award a contract for architectural services at its September meeting.
BUILDING 4 REMODEL & BUILDING 5 REMODEL/ADDITION
Architect selection process not yet started.
August 25, 2009
BOND UPDATE:
BUILDING 2 & PERFORMANCE HALL ELEVATOR
College administrators have been working for months on the question of where to locate the two new dance studios. They have come to the conclusion that two dance studios should be added to the north side of the Performance Hall and the other added to the northeast corner of PE building 5. The architects have been asked to present a fee proposal for this work. Eco-charette and updated design presentations by architects are scheduled for Wednesday, August 26.
CENTER BUILDING FIRST FLOOR SE CLASSROOM
Light fixtures, doors and ductwork are scheduled to be installed this week.
BUILDING 19 WORKFORCE TRAINING & FOUNDATION
Demolition in Workforce Training rooms began last Friday. Work on the Foundation suite is scheduled to begin as soon as Workforce Training remodel is complete. The entire project is scheduled to be complete by December.
CENTER BUILDING REROOF
New roofing has been installed on about a third of the building. The project is on schedule.
DOWNTOWN CAMPUS BUILDING
Discussions between the college and city officials are continuing.
PERFORMANCE HALL SEAT REPLACEMENT
New seats are scheduled to be delivered for installation during the week of September 7.
FLORENCE CENTER
The construction contract is being finalized. All work is scheduled to be completed by the beginning of winter term.
TRACK & SOCCER BOWL UPGRADES
A formal agreement between the college and landscape architect is expected to be executed this week.
BUILDING 10, RECYCLE CENTER, TEST CELL REPLACEMENT, AND KILN
Architect selection committee is expected to conclude interviews this week with a recommendation to the board.
BUILDING 4 REMODEL AND BUILDING 5 REMODEL/ADDITION
Advertisement for an RFP for architectural services is expected to be published later this week.
August 18, 2009
BOND UPDATE:
Building 2 & Performance Hall Elevator
Architects continue to work with Project User Groups (PUGs) on preliminary designs.
Center Building First Floor SE Classroom
Quotes were received and were lower than the estimated amount. Contractor is working on project and is scheduled to complete work in time for fall term classes.
Building 19 Workforce Training & Foundation
Once again, the bids for the project came in under the estimate. A contractor has been awarded the contract and is expected to begin work shortly.
CENTER BUILDING REROOF
Center Building re-roof project is on schedule and is expected to be completed by mid-September. The metal roofing for the top of the building is on site and installation scheduled for around August 20. Occupants on the Center fourth floor might experience an odor from the hot glue system being used. Contact Mark Richardson, 3426.
Downtown Campus Building
The college and city officials continue to discuss the site options for the project.
Performance Hall Seat Replacement
Project is still on target to be completed by start of Fall Term
Florence Center
At a special meeting, the Board of Education awarded a contract to Bineham Construction Co. for the work on the Florence Center. Low bid was below estimate
August 4, 2009
BOND UPDATE:
For more information about bond projects, contact Bob Mention, (541) 463-5747. In general, Bond projects are moving ahead on-schedule. The following specifics are worth noting:
1. The bids for the remodel of Workforce training & Foundation suite came in at about half of the estimated construction cost. McKenzie Commercial was the low bidder and will start work shortly after the contract is signed, perhaps as early as next week.
2. The contract with Cameron McCarthy Gilbert & Scheibe Landscape Architects for design services in connection with the Track & Soccer Bowl upgrades should be executed this week. This would permit design work to commence next week.
3. The bids for the work on the Florence Center are due August 6.
4. A pre-proposal conference for all firms interested in submitting proposals for design services in connection with the building 10, recycle center, test cell replacement and kiln projects is scheduled for August 4.
5. "Scoping" work for the Downtown Campus building continues. In this context "scoping" means identifying the basic facilities the new building needs to address. This preliminary work is being done by the chairs/directors of the various units planned to occupy the building.
6. Preliminary design work continues on the remodel of building 2 and the Performance Hall elevator. Architects and project user groups (PUGs) are working together.
CENTER BUILDING RE-ROOF
Umpqua Roofing is currently installing the new single ply roofing on the top of the Center building. Installation of the material requires the roofing company to use glue that is sprayed on the existing roof surface. This material is going to give off a strong odor that might be detected on the Center fourth floor. Crane activities are scheduled to continue every Friday through the month of August.
July 23, 2009
BOND UPDATE:
For more information about bond projects, contact Bob Mention, 5747.
PERFORMANCE HALL SEAT REPLACEMENT
Bids from contractors to build the new ADA platforms were received and were below estimated cost. Everything is still on schedule.
BUILDING 2 AND PERFORMANCE HALL ELEVATOR PROJECT
Architects and the Project User Group (PUG) met and began the programming phase.
CENTER BUILDING CLASSROOM REMODEL
Bids from contractors to do this work were received and were below estimated amount. A purchase order is being prepared and work should start thereafter.
FLORENCE CENTER PROJECT
Bid documents scheduled to go out for bids this Wednesday. Bids due on August 6.
DOWNTOWN CAMPUS
A Board of Education work session on July 21 will explore this matter.
TRACK & SOCCER BOWL UPGRADES
A special Board of Education meeting on July 21 will act on awarding a contract for design services.
FOUNDATION OFFICE SUITE
Bids for this work are due on July 28.
BUILDING 10, RECYCLE CENTER & TEST CELL REPLACEMENT
Request for Proposals from design firms is scheduled to be published this weekend, July 26.
CENTER BUILDING ROOF
Beginning Friday, July 17 and for the next several Fridays, materials will be lifted onto the top of the Center building by a crane that is set up at the southeast corner of the building on the first floor level. During crane activities access to the upper walkways around the Center building will be limited and controlled by the Facilities staff. The lower access road will be blocked off to thru traffic to allow the crane to rig and lift loads safely. Selected office locations on the southeast side of the Center building will have to be vacated when the crane is loading materials overhead. A member of the Facilities staff will be assist in asking staff to not occupy this area while materials are being lifted. If a staff member is occupying this area during crane activities, they should expect to be asked to leave for short periods of time and this may occur often. The project is expected to be completed by August 31. Contact Mark Richardson, 3426.
July 14, 2009
BOND UPDATE:
For more information about bond projects, contact Bob Mention, 5747.
PERFORMANCE HALL SEAT REPLACEMENT
The old seats have been removed and concrete work to install wheelchair accessible platforms will be complete in the next few weeks. The work is still on target to be completed by the start of fall term.
BUILDING 2 REMODEL & PERFORMANCE HALL ELEVATOR PROJECTS
Architects are gathering material in advance of the July 15 Project User Group (PUG) meeting.
CENTER BUILDING RE-ROOF
The project is on schedule to be completed by end of summer.
CENTER BUILDING SE CLASSROOM REMODEL
Asbestos abatement and demolition of existing rooms is underway. Quotes from contractors to remodel the area will be submitted next week.
FLORENCE CENTER PROJECT
Contract documents are scheduled to go out for bids next week to re-side, re-roof and add to the original building.
DOWNTOWN CAMPUS
A special work session by the Board of Education will be held July 21 to discuss site options for the proposed building.
TRACK AND SOCCER BOWL UPGRADES
The board is expected to approve a contract award for a design firm at a special meeting July 21.
FOUNDATION OFFICE SUITE
Contractor bid opening for the remodel of the southwest corner of building 19 for the Foundation is scheduled for July 28.
June 23, 2009
BOND UPDATE:
BOND PROJECT 09-1972 CENTER BUILDING ROOFING PROJECT
Umpqua Roofing was awarded the roofing contract on June 15 and is expected to start construction activities on July 20. Materials for the roofing project is expected to show up on site and will be loaded on the roof used a large crane on the southwest corner of the Center building. The only day of the week cranes might be loading materials would be on Fridays so students and staff will not be affected. Contact Mark Richardson, 3426.
June 16, 2009
BOND UPDATE:
Building 2 and Performance Hall elevator project starts with a kick-off meeting with the architect June 18. This meeting has to do with the "mechanics" of the project. PUG members will not be needed at this meeting. Performance Hall seats have been ordered and the architect working on drawings for ADA platforms. Center building re-roof project is scheduled to start this week. Asbestos abatement work scheduled to be done this week in the Center first floor classroom project. New siding is scheduled to be purchased this week for the Florence project. Thirty-five design firms requested copies of the request for proposals for the Track and Soccer Bowl upgrades project. A pre-proposal conference scheduled for Wednesday, June 17 and proposals are due June 24. The architect for the remodel of room 19/270 for Foundation offices is planning to go out for bids by the end of June. Space assignment request is being prepared for the renewable energy project. Bond project manager hire committee has made a recommendation and reference checks will be done as soon as time permits. Contact Bob Mention, 463-5747.
June 9, 2009
BOND UPDATE:
An agreement between the college and architect is expected to be completed this week for the building 2 remodel and Performance Hall elevator project. Bids for the Performance Hall replacement seats came in under budget and the lowest bid was the preferred seat. Work on the Center building re-roof project is expected to begin after spring term finals. Center building first floor classroom project demolition of existing rooms will be done by college workers starting June 15. Architects are continuing work on the Florence Center and the bond office has requested a conditional use permit from the city of Florence. Request For Proposals from landscape architects and/or architects in connection with design services for the Track & Soccer Bowl Upgrades project will be distributed early this week. Deadline for submittal of proposals is June 24. Design work is continuing for the remodel of building 19 room 270 for Foundation offices. A space assignment request is being prepared for two photo-voltaic arrays for the renewable energy project. The arrays are proposed to feed energy into the campus grid and electric car charging stations. A grant from EWEB will help fund this project. The Bond Project Manager hiring committee plans to make a recommendation by June 12. Contact Bob Mention, 463-5747.
June 2, 2009
BOND UPDATE:
The Owner-Architect Agreement for design of Building 2 & Performance Hall elevator remodels is expected to be completed this week and Project User Group (PUG) meetings will be scheduled for the following week. Bids to reroof the Center building were opened and the low bid was below estimate. A PUG will review the schematic drawing of remodel of building 19, room 270 to accommodate the Foundation. A PUG will review a schematic drawing of Center building first floor classroom this week. The Bond Management office is scheduled to begin preparing a Request for Proposals (RFP) for design services in connection with the Track & Soccer bowl improvements. A request for quotes from theater seat manufacturers has gone out and the deadline to receive quotes is Wednesday, June 3. Architectural work on the Florence Center is continuing. Contact Bob Mention, 5747.
May 27, 2009
BOND UPDATE:
Florence Center design work is going forward on two options for the biology lab and specifications are being prepared for the new siding, roof insulation and finish roof. Quotes will be solicited for the Performance Hall seating and the board of education awarded the contract for the elevator upgrade to Solarc Architecture and Engineering. Solarc will also do the elevator upgrade for building 2. The Center building re-roof bids for construction are due May 27 with work scheduled for the summer. A Project User Group will be formed for the Track & Soccer Bowl Improvements project so a scope of work statement can be prepared and the design team selection process can begin. Bob Mention, 5747.
May 19, 2009
BOND UPDATE:
Design work is progressing on the Florence Center, Performance Hall seat replacement and Center building first floor classroom projects. The Board of Education is expected to name an architect for the remodel of the Business building and for installing an elevator in the Performance Hall at a special meeting on May 20. Submitted by Bob Mention, (541) 463-5747.
May 12, 2009
BOND UPDATE:
-Florence Center: Project orientation and mobilization is occurring for siding and the classroom addition.
- Performance Hall seat replacement: Seat layout plan and new seat criteria being prepared by the architect.
-Building 2 Business and Performance Hall remodels: The architect selection committee interviewed two firms and made a recommendation.
- Center Building first floor classroom: Construction documents are being prepared.
- Downtown: Nothing new to report.
- Contact: Bob Mention, bond project manager, (541) 463-5747.
May 5, 2009
BOND UPDATE:
ARCHITECTS CHOSEN FOR FIRST BOND PROJECTS
The firm of Affolter, West and Jones Architects has been chosen to design the Florence Center project. They have met with the Florence project user group (PUG) and are starting work. The firm of Gerald McDonnell & Associates has been chosen to design the Performance Hall seat replacement project and they have started working with the seat replacement PUG. The next meeting of seat replacement PUG is scheduled for May 7, 11:30 a.m. -12:30 p.m., in the Performance Hall theater. The architect for the building 2 and Performance Hall remodels has not been chosen yet. The selection committee is scheduled to arrive at a short list of firms to interview by May 8.
The projects are the first to be funded by Lane’s $83 million construction bond approved by voters in November 2008.
For more information contact Senior Bond Project Manager Bob Mention at (541) 463-5747.
April 28, 2009
BOND UPDATE:
ARCHITECT BEGINS WORK ON FLORENCE, THEATER, AND CLASSROOM PROJECTS
David Amundson, a local architect, was hired as a bond project coordinator and began work April 28. He will start with the Florence Center, Performance Hall seat replacement, and Center building classroom projects. He will meet with the respective project user groups (PUGs) this week.
The architect selection process for the Business building and Performance Hall remodel projects continues.
The design of the Center building classroom continues.
Contact: Bob Mention, (541) 463-5747.
April 21, 2009
BOND UPDATE:
ARCHITECTURAL SELECTION UNDERWAY; STAFF USER GROUPS FORMED
The process for selecting architectural firms for the first group of projects to be funded by Lane’s $83 million capital construction bond is moving forward. The deadline for submitting proposals for the business building and performance hall remodels was Monday, April 20. Architectural firms for the Florence Center and the performance hall seat replacement projects are scheduled to be on the job by the end of this week.
The Project User Group for the business building and performance hall remodels has been established and a subgroup (architectural selection committee) will start its work this week.
The Project User Group for the performance hall seat replacement project has been formed and will start work shortly.
The Project User Group for the Florence Center project has been formed and has met several times. They will be scheduled to meet with the architect as soon as possible after the architect is under contract. Contact: Bob Mention, 463-5747.
April 14, 2009
BOND UPDATE:
BOND PROJECT ATTRACTS BIDS FROM 23 ARCHITECTURAL FIRMS
The Request for Proposal for architectural services in connection with the remodel of building 2 and the Performance Hall elevator has gone out to architects. A pre-proposal conference held on April 7 was attended by representatives from 23 firms, far more than was expected. Proposals are due April 20.
A roster of architectural firms is being developed to speed up the architectural selection process for projects whose design fees are less than $100,000. When finalized, Facilities, Management and Planning can choose qualified firms from the roster to submit proposals for specific projects. The roster is scheduled to be formed by mid-April.
A preliminary list of instructional space needs is being developed for the Downtown Center. For more information contact Bob Mention at (541) 463-5747.
March 24, 2009
BOND UPDATE:
The first group of bond architectural projects consists of Florence Center improvements, Performance Hall improvements, Business building remodel, and the Downtown Center. A Project User Group (PUG) has been formed for the Florence Center project and PUGs are being formed for the remaining projects. The design team selection process for these projects will commence shortly. Contact: Bob Mention, 463-5747.
March 3, 2009
BOND UPDATE:
BOARD APPROVES GROUP 1 PROJECTS
At it's meeting last week, Lane's Board of Education approved moving ahead with Group 1 bond projects. This will allow planning for those projects to move forward. Project User Groups for some of those projects will be formed within the next few weeks.
A communications strategy is being developed to meet the needs of both campus communications and that of the larger public community. For a list of Group 1 bond projects or for more information, contact Dave Willis at willisd@lanecc.edu or 463-5566.
February 3, 2009
BOND UPDATE: BOND UPDATE: FIRST PROJECTS SELECTED
The first group of bond projects consists of the Downtown Center, the remodel of the Business building, installing an elevator and replacing the seats in the Performance Hall, replacing the siding and creating a science lab at the Florence Center, and some major maintenance projects.
The first steps of forming Project User Groups and selecting design teams for the first group of bond projects will start this month.
Construction of all of these projects, except the Downtown Center and Business building, is scheduled to start in June and complete in September 2009.
Planning for the Downtown Center and Business building is scheduled to begin in March 2009.
Remodel of the Business building is scheduled to begin in September 2009 and be completed by August 2010. Contact Bob Mention, 541-463-5747.
For additional information about the bond, contact Lane's Bond Project Managers, Bob Mention or Todd Smith. Contact information for Bob and Todd can be found at Contacts .
If you have comments, questions or feedback concerning Lane's Bond, please e-mail bond@lanecc.edu .