Services to Students Organization
Organizational structure that utilizes cross-functional teams to promote one-stop and student self-service approaches to service delivery.
Due Date: 12/98
Task |
By Whom |
By When
Start--End Dates |
Resources
Required |
Review pilot team job classifications
Review current job classifications to determine what, if any, changes are necessary for members of the following pilot teams:
Information Planning Team
Information Support Team
Career and Work Information Center Team
Advising Teams |
Sue Colvin,
Applicable Classification Teams,
Joint Review Committee
Affirmative Action Director |
11/96 - 1/97 |
|
Inform applicable employee group of any changes in job classification for pilot team members. |
Sue Colvin |
1/97 - 2/97 |
|
Develop job classifications - all teams
Develop job classification and recommend compensation levels for services to students team in the following order:
1. process owner managers
2. team leader managers
3. Students First! Center mobile unit resource representatives
4. individual team members |
Sue Colvin,
Applicable Classification Teams,
Joint Review Committee Affirmative Action Director |
1/97 - 12/97 |
|
Inform applicable employee group of job classification and recommend compensation level changes, as changes are made. |
Sue Colvin |
1/97 - 12/97 |
|
Negotiate wages for new job classifications
Negotiate wages for new job classifications, if applicable |
Applicable Bargaining Unit Groups |
2/97 - 6/97 |
|
Process owner manager selection
Review process owner manager skills, characteristics, and responsibilities and refine to develop job classification. |
Sue Colvin,
Applicable Classification Teams,
Joint Review Committee
Affirmative Action Director |
3/97 - 4/97 |
|
Task |
By Whom |
By When
Start--End Dates |
Resources
Required |
Conduct search and identify process owner manager candidates. |
Sue Colvin,
Linda Waddell |
4/97 - 6/97 |
|
Inform applicable employee group of job classification and recommend compensation level changes for process owner managers. |
Sue Colvin |
4/97 - 5/97 |
|
Select process owner managers. |
Redesign Project Management Implementation Team |
4/97 - 6/97 |
|
Team selection criteria and process
Develop team selection criteria and process |
Sue Colvin,
Linda Waddell
Process Owner Managers,
Affirmative Action Director |
5/97 - 7/97 |
|
Determine number of teams required and number of individuals for each team. |
Process Owner Managers,
Redesign Coaches,
Redesign Project Management |
5/97 - 7/97 |
|
Team leader manager selection
Review team leader manager skills, characteristics, and responsibilities and refine to develop job classification. |
Sue Colvin,
Applicable Classification Teams,
Joint Review Committee Affirmative Action Director,
Process Owner Managers |
6/97 - 7/97 |
|
Inform applicable employee group of job classification and recommend compensation level changes for team leader managers. |
Sue Colvin |
7/97 - 8/97 |
|
Conduct search and identify team leader manager candidates. |
Sue Colvin,
Linda Waddell |
6/97 - 8/97 |
|
Select team leader managers. |
Process Owner Managers,
Redesign Coaches,
Redesign Project Management |
6/97 - 8/97 |
|
Identify and select team members
Identify and select individual team members (beginning with the Students First! Center mobile unit resource representatives). |
Process Owner Managers,
Team Leader Managers |
6/97 - 12/97 |
|
Task |
By Whom |
By When
Start--End Dates |
Resources
Required |
SF! Ctr. Mobile Unit Resource Representative selection
Review Students First! Center mobile unit resource representative skills, characteristics, and responsibilities and refine to develop job classification. |
Sue Colvin,
Applicable Classification Teams,
Joint Review Committee Affirmative Action Director,
Process Owner Managers |
6/97 - 7/97 |
|
Inform applicable employee group of job classification and recommend compensation level changes for Students First! Center mobile unit resource representatives. |
Sue Colvin |
7/97 - 8/97 |
|
Conduct search and identify Students First! Center mobile unit resource representative candidates. |
Sue Colvin,
Linda Waddell |
6/97 - 8/97 |
|
Select Students First! Center mobile unit resource representatives. |
Process Owner Managers,
Redesign Coaches,
Redesign Project Management |
6/97 - 8/97 |
|
Identify and select individual team members for services to students teams. |
Process Owner Managers,
Team Leader Managers |
6/97 - 12/97 |
|
Inform applicable employee group of job classification and recommend compensation level changes for individual team members. |
Process Owner Managers,
Team Leader Managers |
6/97 - 12/97 |
|
Team evaluation criteria and process
Develop team evaluation criteria and process. |
Sue Colvin,
Applicable Classification Teams,
Joint Review Committee
Affirmative Action Director
Process Owner Managers,
Team Leader Managers,
Individual team members |
10/97 - 3/98 |
|
Task |
By Whom |
By When
Start--End Dates |
Resources
Required |
Establish training requirements
Establish training requirements for services to students team including:
technical knowledge
team interaction
customer service |
Process Owner Managers,
Team Leader Managers,
SF! Ctr. Mobile Unit Resource Representative,
Redesign Coaches
Implementation Team |
2/97 - 3/98 |
|
Determine training providers
Determine training providers dependent on type of training being delivered. |
Patti Lake,
Redesign Coaches,
Implementation Team |
2/97 - 4/97 |
|
Establish training schedule
Establish training schedule. |
Process Owner Managers,
Team Leader Managers,
SF! Ctr. Mobile Unit Resource Representative,
Patti Lake |
3/97 - 5/97 |
|
Conduct initial training sessionsConduct initial training sessions. |
Applicable providers
SF! Ctr. Mobile Resource Representatives |
4/97 - 10/97 |
|
Extend service hours
Plan extended hours for services to students and determine signage needs. |
Process Owner Managers,
Team Leader Managers,
Team members |
1/97 - 3/97 |
|
Inform applicable employee group of changes in work conditions. |
Process Owner Managers,
Team Leader Managers |
1/97 - 3/97 |
|
Implement extended service hours. |
Team Leader Managers |
3/97 - 4/97 |
|
Bond facilities planning
Work with the Student Service Bond Facilities Planning Group and Facilities Management Committee to plan space requirements for Students First! Center and other teams. |
selected members of Implementation Team,
Process Owner Managers,
Facilities Planner |
10/96 - 12/98 |
|
Determine equipment needed for Students First! Center and other teams. |
selected members of Implementation Team,
Process Owner Managers,
Team Leader Managers |
11/97 - 6/98 |
|
Relocate to Students First! Center
Relocate to Students First! Center and CELEBRATE! |
|
8/98 - 12/98 |
|
|