Bond Project Management Team
March 12, 2003
Bond 1995 Projects Status Report
Main Campus Projects
- The Welding Technology Building, Addition to Campus Services Building, Parking Lot Improvements, Child Care Center, Math-Science Addition, Bus Station, Student Services Building, Central Plant Upgrade, Health Tech., P.A.-P.E. ramp, Addition to Performing Arts, Center Building, 2nd floor N. remodel, Library remodel, and temporary space for Archives have all been completed.
- Workforce Training Center: The mediation process discussed at the last Board meeting is continuing.
Construction of the Preparation kitchen is complete.
- Center Building, 4th floor remodel: Demolition is about 95% complete. Light metal framing is about 85% complete. The electricians and HVAC subcontractor are about 60% complete with their rough-in work. Drywall is about 50% complete. Painters are about 25% complete. About 85% of the casework has been fabricated. Suspended ceiling grid is scheduled to be started March 3rd. The two rooftop air handlers are on site. Weather permitting, they are scheduled to be lifted by helicopter onto the Center building roof on March 9th. We are still within our original time schedule and budget.
- Sewer Lagoon Upgrade: One of the significant milestones of the DEQ Mutual Agreement Order is the approval of the college's Facilities Plan and we have just received that approval. The next step in the process is for our engineers to prepare and submit a "Preliminary Engineering Report" to DEQ. This document outlines the processes, various pieces of manufactured equipment and their location on our property. Submittal of this document should occur early this summer.
|  |