WELDING TECH. PROJECT

February 16, 2000 Update

WELDING BUILDING:
code problems have been resolved in principal and an occupancy permit is expected soon. Lane tradespeople are installing some owner-supplied items in the meantime. Fireproofing painting should take about wwo weeks. Welding and jewelry programs should be operational in the new building by the start of spring term.

Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.