November 6, 2000 Update
STUDENT SERVICES MOVING ALONG AT FAST PACE.
On the first floor, painting is completed in a large portion of office and lab space. Restrooms are having tile applied to portions of the walls and floor. Generally, electrical outlets for lights and clocks are in place. On the second floor, seventy-five percent of drywall activity is complete. Steel stud framing is being applied to sections of the main lobby stairway. On the exterior of the building, the main entrance has had the ADA ramp footings poured allowing development of the passageway.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |