September 18, 2000 Update
SKYBRIDGE TIED TO APPRENTICESHIP BUILDING.
Chambers Construction workers have sawed through the brick on the north wall of the Apprenticeship building where the sky bridge meets the building. Currently, insulation and wall covering work is underway to provide a temporary exterior wall for Apprenticeship classrooms that are adjacent to the sky bridge intersection. Drywall activities begin this week on the first floor of the building. Installation of metal roofing that will cover the barrel trusses will also begin this week. The large air handlers that were stored on the passageway between Student Services and the Apprenticeship building are now installed atop the Student Services facility.