July 24, 2000 Update
STUDENT SERVICES GAINS GREATER DEFINITION AS LCC'S 'FRONT DOOR'
with continued erection of curved steel and barrel trusses. Steel studwork progresses on the sides of building. The remainder of the second floor slab has been poured. Installation of infrastructure on both floors continues.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |