STUDENT SERVICES GAINS GREATER DEFINITION AS LCC'S 'FRONT DOOR'
with continued erection of curved steel and barrel trusses. Steel studwork progresses on the sides of building. The remainder of the second floor slab has been poured. Installation of infrastructure on both floors continues.