May 2, 2000 Update

Student Services:
Business Technologies staff including Georgia Nissen and others deserve very special thanks for providing ADA access to the first floor of their building via their storage room, conference room and reception area, while the west sidewalk to the building was torn up for Student Services project access to the utility tunnel. Sidewalk access was restored Friday.

Also at the project, 118 yards of concrete was poured Monday. Plans are forming up for a skybridge from the new building to Workforce/Apprenticeship. Classrooms on the north side of Apprenticeship probably will be vacated this summer to facilitate the skybridge connection. Overall, the college, the contractor, the architects and the engineers are all pleased with the smooth and rapid progress the Student Services project.

AN EXTERIOR ELEVATOR to improve ADA access to the Business and Administration buildings will be built as part of the Student Services contract. The elevator will be on the west side of the buildings and a focal point for people entering campus from the west. The elevator will rise up near the existing breezeway and will have four stops serving the upper and lower levels of the two buildings.

Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.