November 30, 2000 Update

SCIENCE/MATH ADDITION ON SCHEDULE FOR FIRST QUARTER COMPLETION.
Hyland Construction continues to make steady progress toward the March 2001 completion of the Science/Math addition. Sheet rock is complete on the second floor of the west addition. The south labs continue to take shape as PVC webbing is installed over concrete floor slabs. The plastic webbing is comprised of caps approximately 2" in height connected to one another by plastic tabs. The webbing will allow data lines to be run underneath flooring, which will be installed shortly.

Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.