SCIENCE ADDITION
October 23, 2000 Update
PRELIMINARY WORK ON ADA RAMP ESTABLISHED AT SCIENCE ADDITION.
On the west side of the Science addition, a sloping passageway has been created. Once finished, the passageway will be an ADA compliant ramp providing main campus access for individuals who park in Lot L. The ramp will have overhead lighting installed at various locations and will intersect established sidewalks adjacent to the Forum. Infrastructure work has proceeded to the point in the south addition that wall coverings will be applied shortly. The south addition's four labs will be ready for winter term classes.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |