SCIENCE ADDITION

August 21, 2000 Update

HYLAND'S SCIENCE REMODEL CREW HARD AT WORK.

Hyland Construction has 75 to 100 individuals putting in extra hours to stay ahead of the initial schedule thus allowing furniture and equipment to be moved this week. Installers for Rubensteins, the floor covering sub-contractor, are also busy laying floor tiles in the remodel area in anticipation of an early move-in. The south side of the West Addition is shaping up nicely as the ADA ramp and adjacent west steps have been completed. Window frames have been installed and brickwork continues.

Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.