Goto Lane Main   Lane Community College  |   Search Lane    
Bond 1995 Archives 
  Bond 1995 Archives  |  Current Bond Work  |

Bond 1995
 
Archives

SCIENCE ADDITION

May 2, 2000 Update

Science/Math:
Steel erection is going up smoothly. This will continue for several weeks (work will be halted during finals). So far, noise levels have been mostly moderate and bearable. The south side slab and entrance should be poured this week, weather permitting. Some interior work is being done in the chem labs and duct systems, and some underslab work is continuing during off-hours.

Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
CURRENT PROJECT PICTURES


2011 Site Archive