May 2, 2000 Update
Science/Math:
Steel erection is going up smoothly. This will continue for several weeks (work will be halted during finals). So far, noise levels have been mostly moderate and bearable. The south side slab and entrance should be poured this week, weather permitting. Some interior work is being done in the chem labs and duct systems, and some underslab work is continuing during off-hours.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |