 |

Bond 1995
Archives |
 |
|
 |
 |

SCIENCE ADDITION
April 11, 2000 Update
Science/Math:
Hyland Construction has agreed to a regular shift of 6 a.m. to 3 p.m. (daylight permitting) at no overtime cost, to lessen the impact of construction on college business. Upcoming work includes pouring the south slab, and erecting some steel. The major steel erection date is set for April 24. Underslab work is beginning to wrap up. Last week¿s hot water shut-off was insufficient and another will have to be scheduled; a Sunday may be selected instead of a weekday evening, as both hot and cold water may have to be interrupted to part or all of campus. A shut-off notice will be e-mailed and run in The Daily as soon as this challenge is worked out.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |