Bond 1995
Archives |
 |
|
 |
 |

SCIENCE ADDITION
April 5, 2000 Update
Science/Math:
A small dynamite drilling hole with some wires showing was discovered at the site on Friday. Project liaison Todd Smith halted work and sought assistance. Public Safety Director Mike Mayer cleared the area and conducted an examination. The hole and wires were found to be safe. Last week, 359 cubic yards of concrete were poured for the floor slab. This week, back-filling of the south wall of the addition will begin. A domestic hot water shut-off is anticipated so a new valve for Science can be installed; an all-staff e-mail will be issued as soon as details are settled. In other work, framing of steel studs on the east side is in progress, and underslab work in the existing building continues from 3 a.m. to 7 a.m.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |