SCIENCE ADDITION

March 8, 2000 Update

Science/Math:
Interior asbestos removal is scheduled for finals week between the hours of 10 p.m. and 7 a.m. Exterior asbestos removal will be held Thursday and Friday of finals week when no exams are scheduled for the building. During spring break, some interior work remodeling will be done such as drilling for electrical conduit and possibly X-raying more concrete beams to locate prestressed cables. Outside, the main portion of the highest wall on the new addition is complete. General contractor John Hyland is preparing for a slab pour.

Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.