September 5, 2000 Update
WORK IN CENTER BASEMENT PROCEEDS IN FULL FORCE.
With permits secured, LCC Trades wasted no time in commencing work on the Center basement remodel. Painters, carpenters, and electricians are working at such a pace that framing inspection can take place this week, enabling the remodel to be completed by September 20th. As soon as furnishings for the ASLCC Co-op are moved into Childcare #4, remodeling activities will be able to commence in Modular #30. Electrical work in Modular #31 has passed inspection. Bond Management and LCC Trades are dedicated to providing remodeled facilities in both modulars in time for fall classes.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |