HEALTH REMODEL
September 12, 2000 Update
SEISMIC & HVAC UPGRADE UNDERWAY IN HEALTH TECH.
The noisy but necessary work of installing steel anchor bolts has begun in the Health Tech facility. If all goes well, seismic work should be completed by the end of the week. Groundwork continues within the remodel area as Essex Construction focuses on preparation of infrastructure. HVAC work is front and forward as new ducts are installed and intermittent shutdowns allow for improvement of the system. On the exterior of the building, the large, unsightly vent pipes and dryer exhaust structures have been removed from the building.