CENTER BUILDING REMODEL
April 22, 2002 Update
ALS STOREFRONT REVEALED SHORTLY.
Within the next couple weeks the temporary construction wall in the main lobby of the Center second floor will come down to reveal the inviting storefront entrance to the new Academic Learning Skills and Tutoring Services area. The glass entrance will allow you to see the main reception area, portions of Tutoring Services, and until completion of the project, installation of HVAC components, carpet, and casework within these spaces. Currently, electricians are finishing up running conduit and electrical wire, installation of sheetrock continues to define greater portions of the project, and classrooms adjacent to the second floor lobby are being taped and textured.
Questions and comments about any bond construction activity may be directed to 463-5027 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team.
|  |