LAUNDRY SERVICES NEARS COMPLETION.
As installation of the exhaust system for the booster boiler is completed, a call for inspection is expected shortly. For all practical purposes, once the boiler passes inspection, bond responsibility for Laundry Services is complete.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |