 |

Bond 1995
Archives |
 |
|
 |
 |

CAMPUS SERVICES ADDITION
June 19, 2000 Update
LAUNDRY SERVICES COMPLETE MOVE-IN IS DELAYED
due to insufficient storage of hot water that resulted from an engineering error. The insufficiency was discovered only when the washing machines were tested.
The Bond Management Team is working with the engineers to remedy the hot water deficiency ASAP because this situation directly influences activity on the remodel of Health Tech, as well as Laundry's heavy work load during summer months.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |