CAMPUS SERVICES ADDITION
May 22, 2000 Update
Laundry and Printing/Graphics near completion.
With over 90% of work completed and in anticipation of a June 1st startup date, two new washers have been delivered to the Campus Services Addition. Facilities Management & Planning staff are coordinating installation of the washers, one of which weighs 10,000 pounds. The Printing and Graphics project, which has 95% of the work completed, began portions of its move last week and will continue moving through the 31st of this month. Exterior concrete has been poured allowing asphalt paving to begin the 23rd.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |