CAMPUS SERVICES ADDITION
April 11, 2000 Update
Campus Service Addition:
Acoustical ceiling tile is being installed and case work is underway on the second floor. Exterior stairs and an ADA ramp are under construction. Paving of the north side access road should begin in a couple of weeks. The Laundry¿s boiler is in place on the first floor and will be running in about three weeks. Two new computerized washing machines have been ordered. The machines pose complex plumbing challenges. Printing/Graphics has been rescheduled to move in sometime in early June when they have a lull in their schedule. This will provide more time for completion of some fire alarm system details. Laundry¿s moving date has not been finalized.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |