CAMPUS SERVICES ADDITION
April 5, 2000 Update
Campus Service Addition:
Printing/Graphics staff have visited their future quarters on the second floor of the addition and like what they see. Graphic designer Shirley Nagy says, "I'm going to spend my first three days as comp time, just so I can sit and look out the windows." The new quarters are being painted and the ceiling grid is being installed. A slight fire alarm and sprinkler systems problem has delayed P/G's expected move-in date to early May. P/G's old space in the Center Building basement will be remodeled into classrooms. On CSA first floor, the complex job of installing a new boiler for the laundry is picking up steam. The Laundry also is expected to move in sometime in May.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |