CAMPUS SERVICES ADDITION

March 23, 2000 Update

Campus Service Addition:
The boiler for the laundry arrived Friday. It will take a week or more to install. Laundry will move in at the end of April or possibly in May. On the second floor, thinwall plaster is about 70 percent complete and painting will begin later this week. Printing/Graphics should be able to move in about mid-April. The access drive on the north side of the building has been paved at the west end. "It's the first time in 20 years that we have no potholes outside the mailroom," says job project liaison Lynn Atkins.