Campus Service Addition:
Masonry is 90% complete. Glu-lam floor beams have been set and floor joists are being installed. Project should be completed by end of April 2000.

Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.