Goto Lane Main   Lane Community College  |   Search Lane    
Bond 1995 Archives 
 Bond 1995 Archives  |   Current Bond Work

Bond 1995
 
Archives

CHILD CARE FACILITY

September 5, 2000 Update

BOND MANAGERS RESPOND TO EXTERIOR WATERLINE BREAK AT CHILDCARE SITE.
What started out a minor leak in piping to the east of the Childcare facilities quickly escalated to a major problem when a break in the line occurred. The break resulted in a vast amount of topsoil being washed out and work on the irrigation system disrupted. However, after sizing up the situation early Wednesday morning, the Bond Management Team in conjunction with the Grounds department, took decisive action. By the end of the day, the disrupted areas around the Childcare facilities had been cleaned up and the site was ready to have additional soil brought in and landscaping activities to begin once again. Turning to occupancy of the facilities, Building #2 now contains significant articles for operation of the program by the beginning of fall classes. Final approval of the building is expected this week. Building #3 has been giving a temporary occupancy allowing the move in of furniture and equipment. Building #4, which will house the ASLCC Childcare Co-op, has also received a temporary permit, allowing moving activities to proceed. Oregon Fencing will be constructing fencing around the facilities. Hyland Construction's job shack will remain at the Childcare site until September 25th, at which time it will be moved to accommodate work on the LTD Bus Station.

Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
CURRENT PROJECT PICTURES


2011 Site Archive