CHILD CARE FACILITYJuly 24, 2000 UpdateCHILDCARE OCCUPANCY WAITING ON COMPLETION OF ALL ASPECTS OF FIRELANES.LCC's landscaping staff are working to establish a subsurface in the main, fire lane access route that will not only be able to support the weight of fire equipment, but provide a suitable base for ground covering. Tricycle paths have been poured at each of the four buildings. Building #3 Cabinetry continues to be installed. Floor covering work is complete. Building #4 The fire alarm system and cabinetry is being installed. Floor covering work is complete. Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
| |||||||||||||||||
|
|
||||||||||||||||||