![]() CHILD CARE FACILITYJuly 17, 2000 UpdateCHILDCARE FACILITIES TAKE ON A MORE FINISHED LOOKas tricycle paths are poured and general landscaping activities begin. Within the boundaries of the fire lane, various flowerbeds are being seeded with a variety of thyme that will produce beautiful, low-growing red flowers. The thyme will make an excellent addition to the fire lane located between the Childcare due to the fact that it will soften the look of the central area and requires low maintenance. Building #2 continues to wait on occupancy permits. Building #3 cabinetry work is progressing. Building #4 contractors continue to make progress with floor coverings. Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
| ![]() |
|||||||||||||
![]() ![]() |