![]() CHILD CARE FACILITYJuly 10, 2000 UpdateTHE FIRE LANE FOR CHILDCARE CENTER has been poured. Tricycle paths adjacent to Buildings #2 & #4 have been staked out and excavation will commence this week. Landscaping of the Childcare Center will begin the latter part of this month. Building #2 is generally completed and waiting on final occupancy permits. Installation of cabinetry is taking place in Building #3 while floor covering is being laid down in Building #4. Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
| ![]() |
|||||||||||||
![]() ![]() |