CHILD CARE FACILITY

July 10, 2000 Update


THE FIRE LANE FOR CHILDCARE CENTER has been poured.

Tricycle paths adjacent to Buildings #2 & #4 have been staked out and excavation will commence this week.

Landscaping of the Childcare Center will begin the latter part of this month.

Building #2 is generally completed and waiting on final occupancy permits.

Installation of cabinetry is taking place in Building #3 while floor covering is being laid down in Building #4.

Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.