CHILD CARE FACILITYMay 30, 2000 UpdateCHILD CARE FACILITY:All Child Care Buildings Have Patios Poured Buiilding #1 remains on target with an inspection conducted this past Friday. Lane Family Connections is poised to move to its new location today and Tuesday. Building #2 has had the cabinetry installation completed. Building #3 is being prepared for interior painting Building #4 has had the exterior work completed while dry wall activity continues. Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
| |||||||||||||||||
|
|
||||||||||||||||||