CHILD CARE FACILITY

May 2, 2000 Update

CHILD CARE FACILITY:
Building 1 has most of the SteelCase furniture, interior signage and lockers installed. Toilet accessories will be installed this week.

In Building 2, ceiling lights and floor coverings are being installed.

Building 3 exterior siding is complete and interior drywall is 25 percent complete.

Building 4 framing and roofing are done, 85 percent of the siding is on, and rough-in electrical should finish up soon.