 |

Bond 1995
Archives |
 |
|
 |
 |

CHILD CARE FACILITY
April 24, 2000 Update
Child Care Center:
Steelcase furniture will be installed in Building 1. The first occupant, Lane Family Connections, should move in about mid-May. Building 2 ceiling grid installation is finishing up and floor coverings should be going in this week. Building 3 insulation is being installed. Building 4 roofing is on. A question has arisen as to whether some of the sidewalks will be subject to sagging over the trenches dug and filled last summer for the geothermal system; various reinforcements or the use of asphalt are being debated.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |