CHILD CARE FACILITY
March 23, 2000 Update
Child Care Center:
Building 1 casework is installed and floor coverings will be put down this week. It should be ready for occupancy about May 1. Building 2 is finishing up drywall and mechanical work is continuing. It should be finished by the end of June. Building 3 has composition roof shingles going up. Building 4 roof framing is in progress. Some sidewalks have been poured. The complex is about six weeks late due to the innovative but complex geothermal energy system which includes mechanical rooms in each of the four buildings.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |