CHILD CARE FACILITY
February 23, 2000 Update
Child Care Center:
Building 1 interior walls are being primed for texture. Building 2 interior mechanical equipment is being installed; roofing, siding and windows are installed; insulation is being installed. Building 3 plywood roof sheeting is being installed. Building 4 walls are set and roof trusses are being installed. Sidewalks for Buildings 1 through 3 are being set-up for pouring.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |