Bond Highlights - November 5, 1999

Background:
Voters passed a $42.8 million construction bond for Lane Community College in 1995. Funds were used to build a new center in Cottage Grove, add to the center in Florence, and to build learning centers at eight county high schools. Bond construction began on main campus in Eugene summer 1999 and is expected to last about two years.

Current construction on main campus as of November 1999

Welding Technology Building

Construction schedule: June 1999-December 1999
Area: 19,000 square-feet
Budget: $1,568,000
Location: Northeast campus
Occupants: Fabrication and Jewelry programs
Architect: gLAs Architectural Group
General contractor: Dorman Construction


Campus Services Addition

Construction schedule: October 1999-May 2000
Area: 6,000 square feet
Budget: $903,000
Location: Northeast campus
Occupants: To house the Laundry and Printing/Graphics shops.
Architect: WEGROUP
General contractor: McKenzie Commercial Contractors


Child Care Buildings

Construction schedule: July 1999-April 2000
Area: 17,449 square-feet including four buildings
Budget: $2,050,000
Location: Southwest campus
Occupants: Early Childhood Education, Infant Toddler Center, ASLCC Child Care Co-op, Lane Family Connections
Architect: gLAs Architectural Group
General contractor: John Hyland Construction


Parking Lot Improvements

Construction schedule: July 1999-November 1999
Budget: $450,000
Location: Southwest campus
550 parking stalls were completed, including handicapped stalls.


Science/Math Building Addition

Site preparation completed for $327,000 by Gary Burnett Earthmoving.
Building construction schedule: November 1999-April 2000
Area: 36,700 square feet
Budget: $7,820,046
Location: South campus
Occupants: Science and Math programs
Architect: gLAs Architectural Group
General contractor: Contract to be awarded November 10, 1999.


Upcoming projects

Student Services Building beginning February 2000 and ending Summer 2001.
Health Technology Remodel beginning June 2000 and ending February 2001.
Workforce Training Center beginning June 2000 and ending August 2001.
Center Building Basement Remodel beginning June 2000 and ending September 2000.
Center Building Second Floor North Remodel beginning January 2001 and ending May 2001.
Center Building Fourth Floor Remodel beginning June 2001 and ending October 2001.
Performing Arts Remodel beginning September 2001 and ending February 2002.
Business Technology Remodel beginning June 2001 and ending September 2001.


Tidbits

Plans will increase current facilities by 55 classrooms, 11 computer and other labs, 15 conference and seminar rooms, and 237 offices.
Hundreds of staff have participated in planning and design through Project User Groups.
A memorial grove is planned for trees displaced by construction. The grove will be built just west of Science and include a wetlands pond.
Eldon Schafer Drive is the main construction route. A former logging road at the south perimeter of campus was upgraded summer 1999 for construction traffic to improve safety in regular parking lots and driveways.


For more information, contact the Bond Management Team:

Bob Mention, Bond Project Manager, Ext. 2747
Mike Hopkinson, Bond Communications Specialist, Ext. 2027
  (user group meetings, department meetings, individual project questions, moving/relocation questions)
Joan Aschim, Bond Communications Specialist, Ext. 2027
  (Daily, webpage, media)
Susan Tatar, Bond Administrative Support Specialist, Ext. 2727
Ginny Martin, Bond Office Support Specialist, Ext. 2727
Bond Project Office: Campus Services Room 202
Bond Communications E-Mail: bond@lanecc.edu
Bond Web Page: http://2011sitearchive.lanecc.edu/campsvcs/ie/ns_bond.htm



Last Updated: November 15, 1999