Bond Update - October 11, 1999
Board Update
The following Bond 1995 Projects Status Report was presented at the Oct. 6 Lane Community College Board of Education meeting.
COMMUNITY LEARNING CENTERS
Centers at Churchill, Oakridge, Thurston and Willamette have been completed.
The center at McKenzie is 99% complete.
Center at Harrisburg doesn't require new construction.
The Junction City center contracts have been awarded and mobilization is underway. Estimated time of completion is spring 2000.
Construction of the center at Elmira is approximately 30% complete. Substantial completion is planned for spring 2000.
FLORENCE CENTER ADDITION
The new building is complete and in operation. The new boiler in the existing building is being installed. Covered roof between existing and new buildings has been approved and will be under construction shortly.
MAIN CAMPUS PROJECTS
Welding Building: Construction started May 27. Building slab has been poured and 99% of metal building frame has been erected. Contractor is forming for exterior slabs. Contractor continues to think building will be completed by December 31 per original schedule.
Contract for Parking Lot Improvements is approximately 99% complete. Lights and handrails need to be installed.
Contract for Science Site Preparation has been completed.
Child Care Center: Construction started in early July. Perimeter footings have been poured for the Office Building and Infants and Toddlers building. Concrete slabs for those buildings are scheduled to be poured tomorrow. Project is scheduled to be completed by March 2000.
Excavation for the Campus Services Addition has started and rock was encountered as well as two electrical conduits. Project should be completed by end of April 2000.
Math-Science Building is scheduled to go out for bid October 11, and bids will be opened November 9.
Student Services Building is scheduled to go out for bids around mid-November. Bids would be opened mid December with construction start date of mid-January 2000.
Workforce Training Building has been rescheduled to go out for bid April 1, 2000.
Remodel of the Health Tech. Building is planned to go out for bids April 1, 2000 with a construction start date in mid-June.
WILDISH BUILDING AND COTTAGE GROVE CENTER
have been completed and are operating.
SEWAGE LAGOON UPGRADE
DEQ has not issued it's final approval of the engineers proposal for improvements to the lagoon as incorrectly stated in last month's status report. Previous report should have said that DEQ issued preliminary approval.
GENERAL COMMENTS
Campus Services forces moved the Art Department kilns from the yard behind the Campus Services Building to one of the test cells for storage while another site is prepared for their permanent location.
The President, Facilities Management Committee and Bond Management Team have recently reviewed and updated the bond project budget. The result confirms that there are sufficient funds to do the scheduled projects including normally accepted levels of change order contingencies.
Construction has reached the point where the Bond Management Team is coordinating with Campus Facilities and Curriculum and Scheduling to work out procedures for the moves which various functions will have to make.
Questions and comments
about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu
. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.