Bond Update - July 23, 1999

Bus Rerouting and General Traffic Detours Due to Excavation on Gonyea Rd.
Construction work on sewage and storm sewers running beneath Gonyea Road necessitates the following, temporary traffic changes.

Monday, July 26th through Wednesday, July 28th,
LTD will be using a temporary route and loading zone due to excavation on Gonyea Road.

Temporary LTD Route:
Gonyea Road to the WEST parking lot where the disabled parking spaces are located. Three of the disabled spaces will be clearly marker off and designated as a loading zone.

Monday, July 26th
general traffic accessing southern parts of LCC's main campus via Gonyea Road can expect a detour or delay at the juncture of Gonyea Road and LTD's exclusive drive. Those wishing to access the south side of campus are encouraged to utilize Eldon Schafer Drive on the 26th. The south side of campus is the area adjacent to the back, wooded hill and upper parking lots. PARKING SPACE IS AVAILABLE IN ALL PARKING LOTS. The only temporary changes are the LTD route/loading zone on July 26th, 27th and 28th, and a detour or delay on Gonyea Road on July 26th.

Main Campus Construction Status
In a sequential construction project such as is taking place on LCC's main campus, attention is generally directed toward those projects that have the greatest amounts of activity taking place. While it is with anticipation that individuals watch parking lot preparation and site development on the Science Addition and the Childcare Center unfold, other Bond 1995 Projects continue to develop. Therefore, an update on the status of all the individual projects on LCC's main campus is important. The following list shows the percentage of work that has been completed on specific projects. Individual projects move through the construction process in the following order: schematic design, design development, construction documents, bidding, awarding of contracts, and construction.

Campus Services Addition II 95% Construction Document Phase
Center 2nd Floor North Remodel Schematic Design Phase Complete
Center 4th Floor Remodel Schematic Design Phase Complete
Center Basement Remodel Schematic Design Phase Complete
Center Seismic Upgrade Not yet started
Childcare Center Construction begun 7/19/99
Health Technology Remodel 50% Design Development Phase
Parking Expansion Construction begun 7/19/99
Math & Art Remodel Schematic Design Phase Complete
Performing Arts Addition 10% Design Development Phase
Science Addition 25% of Construction Document Phase
Science Site Preparation Construction begun 7/21/99
Student Services Building 30% Construction Document Phase
Welding Technologies Building 15% Construction Phase
Workforce Training Center 40% Construction Document Phase
Infrastructure Upgrade 30% Design Development Phase


Additional Increase in Parking Lot Space
When pavement of the west parking lots is completed, two undeveloped lots will be available for additional development. Budget authorizations for parking lot improvements will allow the two lots to be developed with all-weather gravel. These lots are directly south of the parking space currently being improved by Delta Sand and Gravel. All-weather gravel development will provide approximately seventy-five new parking spaces.

Temporary Archive Storage
Current construction activities on campus will soon take place in the area in which archives are stored. Consequently, a portion of the records will have to be moved. Since no additional, permanent space is available on campus at this time, the Facilities Management Committee has approved using temporary, off-campus storage. Storing portions of the archives off-campus allows critical classroom space to remain at current levels rather than be utilized as storerooms for records.

The Bond Project Management Team(BPMT) will be available during summer hours to provide information and answer any questions that may arise. All communication received by the BPMT during summer months will be reviewed regularly by the team, the architects, and the Facilities Management Committee. The BPMT can be reached at 744-4154, Email to Nancy Nichols, or on the web at http://2011sitearchive.lanecc.edu/campsvcs/main.html



Last Updated: July 23, 1999