Summary of current bond activity as of July 2, 1999
- Board Approval of Bids
On June 30, 1999, the Board of Education approved the bids for three main campus projects. Delta Construction Company was awarded the parking lot improvement project, John Hyland Construction was awarded construction of the Child Care Center and Gary Burnett Earthmoving was awarded site preparation for the Science/Math project.
- Main Construction Route
Development of the south access road running between Eldon Schafer Drive and Gonyea Road has been completed. Construction traffic entering the campus will now access the west side of campus via this access road. The south access road is restricted to construction vehicles and equipment only. Moreover, in anticipation of increased construction traffic on Eldon Schafer Drive, gravel shoulders have been built up on both sides of the curve adjacent to Oak Hill School. Shoulder improvement will allow regular and construction traffic to navigate safely on this portion of the drive. In-house production is currently underway on cautionary and construction area restriction signs that will be located at strategic junctures.
- Project Signs
Funk & Associates Marketing Communications has been retained in the development of Bond Construction Project signs for LCCís major entrances and individual projects. Specific project signs will allow campus users to identify construction sites and provide general project information. Current discussion regarding the major entrance signs revolves around providing information pertinent to the general project, progress and taxpayer participation.
The Bond Management Team (BMT) will be available at 744-4154 during summer hours to answer any questions and give information. All communication received by the BMT during the summer months will be reviewed regularly by the team, the architects and the Facilities Management Committee.
|  |