Summary of current bond activity as of June 25, 1999
- Acceptance of Bids
The Bond Project Management Team accepted bids last week for three main campus projects. The recommended bid awards are up for approval at a Board of Education meeting on June 30, 1999.
Recommended are Delta Construction Company for the parking lot improvement project with a base bid of $284,825 and total alternative bids of $121,450;
John Hyland Construction for construction of the Child Care Center project with a base bid of $1,774,729 and alternative bids of $121,647;
Gary Burnett Earthmoving for site preparation for the Science/Math project with a base bid of $97,890 and a unit price for rock removal of $56.97.
Delta and Hyland bids were within budget. As a component part of the total Science/Math bid, the site preparation did not have a specific dollar figure assigned to it. However, by having the site preparation portion of the project bid separately and prior to the main Science/Math project, considerable expense was saved. Excavation work undertaken during summer months when weather conditions are more apt to be optimal results in overall lower costs. Construction of the science/Math project is scheduled to begin December 1999.
- Development of South Access Road
Eldon Schafer Drive will be the main construction route used during Bond Construction. Within the next two weeks, Delta Sand and Gravel will begin development of the access road beyond the south parking lot. Development of the south access road will allow construction traffic passage to the west side of campus with the least amount of campus disruption. Signs are being developed to notify those individuals traveling on Eldon Schafer Drive and Gonyea Road as to the presence of construction trucks and equipment.
- Parking Space
LCC Main Campus will see an overall increase in parking spaces by fall í99. More efficient use of space in the west parking lot will result when the two existing gravel lots are paved and lined. Additional new parking will be developed adjacent to the new Early Childhood Education building. Between the two sites, 10 disabled and 242 regular parking stalls will be provided.
The Bond Management Team (BMT) will be available at 744-4154 during summer hours to answer any questions and give information. All communication received by the BMT during the summer months will be reviewed regularly by the team, the architects and the Facilities Management Committee.
|  |