Archive of Bond 1995 - Bond Status Report - 10/11/2000

The following Bond 1995 Projects Status Report was presented to the Lane Community College Board of Education at its October 11, 2000 meeting.

Community Learning Centers:
All Community Learning Centers have been essentially completed and are in operation. Additional air conditioning is planned for the Willamette High School CLC and some vinyl tile will be laid in the Junction City High School CLC as soon as the concrete floor slab drys sufficiently.

Main Campus Projects:

Welding Technology Building:
The building is complete and in operation.

Child Care Center:
The contractor is substantially complete and work done by LCC facilities is 85% complete. The Center is operational.

Campus Service Addition:
The building is complete and in operation.

Science/Math:
The remodel portion of the Science building has been completed and is operational. The east and south additions are scheduled to be completed in time for use starting Winter Term. The entire project is on schedule to be completed in March, 2001.

Student Services:
The project is on schedule to be completed by March, 2001.

Health Tech. Remodel:
Demolition is complete. Interior ductwork, plumbing, electrical and framing is well under way.

Sewage Lagoon Upgrade
Project is waiting for Response from DEQ to proposed upgrade plan.

LTD Bus Station
Project is operational. Construction of shelters and clock tower are scheduled to be completed by January.

Workforce Training:
The site excavation package has been completed. The construction documents for the building itself are 85% complete. Bid documents are scheduled to go to bidders late this month or early next month.

Infrastructure Upgrade:
This work continues on schedule.

LCC Facilities Projects:
Remodel of Center building basement, ASLCC Co-op modular and ECE modular were not fully operational for the start of Fall Term. The current schedule shows them being completed in early October.
Remodel of Center Building 1st floor: Starting planning process with Food Service and Culinary Arts.

Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.