Archive of Bond 1995 - Bond Status Report - March 8, 2000

The following Bond 1995 Projects Status Report was presented to the Lane Community College Board of Education at its January 12, 2000 meeting.

Community Learning Centers
All Community Learning Centers have been completed and are in operation except the Junction City Center.
At the Junction City CLC, the exterior building envelope is 80% complete, interior ductwork and electrical has been roughed-in, interior framing has passed inspection and sheet rock is being installed. Project is a little ahead of schedule.
The Elmira CLC is now in operation. A Grand Opening celebration is planned for March 16th.

Florence Center Addition
The new building is complete and in operation. The contract for the construction of a breeze way between the old and new buildings has been executed and construction is underway. Completion of the breezeway is scheduled for early April.

Main Campus Projects:
Welding:
Contractor has lots of cleaning and small items to finish. LCC trades people are moving and hooking up equipment, painting fire protection paint, installing cabinet doors, etc. The plan is to move the welding and jewelry departments during spring break so that they can be operational by the start of spring term.

Parking Lot Improvements:
Contract for Parking Lot Improvements is 100% complete. Lights are operational.

Child Care Center:
Bldg #1: Exterior envelope is 95% complete, interior work is roughed in and finishes are being applied. Cabinets are being installed.
Bldg #2: Exterior envelope is 80% complete, interior work is 90% roughed in, interior finishes will start soon.
Bldg #3: Exterior envelope is 50% complete, interior work is 40% roughed in.
Bldg #4: Exterior envelope is 40% complete, interior work is 30% roughed in.

Campus Service Addition:
Masonry is 99% complete. Floor and roof framing is complete. Roofing has been laid. Lower level floor slab has been poured. Metal fascia panels are 90% in place. Heating ductwork, plumbing and electrical are roughed in. Project scheduled to be completed by end of April 2000.

Science/Math:
Retaining walls at west addition are 60% poured. Under slab plumbing is complete, under slab electrical is 90% complete at west addition. Steel columns are being fabricated. Project is still behind schedule.

Student Services:
Bids for the Student Services Building were opened January 13.

Workforce Training:
Rescheduled to go out for bid June 1, 2000.

Health Tech. Remodel:
Remodel is planned to go out for bids about April 15, 2000 with a construction start date in mid-June.

Infrastructure Upgrade
The Welding Building portion of the infrastructure project has been completed. Cabling for the other buildings is continuing.

Sewage Lagoon Upgrade
Representatives of the Bond project and the Oregon Military Department (OMD) met with Abiqua engineers again to receive their final report. All present agreed that the first priority is to add tertiary treatment equipment to the Lagoon. The second priority is to pipe the outfall to the coast fork of the Willamette River. Before work can begin we need DEQ review and approval of the final upgrade plan and an interagency agreement between the OMD and LCC. Negotiations on the interagency agreement will commence soon. A preliminary draft of the agreement will be presented for your input and the final document will require your approval. Bill Spoja of the OMD told us they might receive some funds from the National Guard Bureau which could be used within certain conditions for Off-site improvements. Bill will be at the Board meeting to discuss his agency's intentions with you.

LTD Bus Station
Design Development drawings are complete and an updated cost estimate has been done. The current cost estimate is $662,496. LTD and the Bond Management Team are reviewing the estimate to see if any reductions are possible. Actual construction of the station is scheduled for this summer.

General Comments
HVAC CONTROL SYSTEMS
Bids for the HVAC control systems for the Student Services and Science-Math buildings are scheduled to be opened on March 8. If all the bid requirements are met I hope to bring a contract award recommendation to you at your meeting.

Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to
bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.