Archive of Bond 1995 - Bond Status Report - January 12, 2000
The following Bond 1995 Projects Status Report was presented to the Lane Community College Board of Education at its January 12, 2000 meeting.
Community Learning Centers
All Community Learning Centers have been completed and are in operation except those at Junction City and Elmira.
The floor slab has been poured and wall framing has started at the Junction City Center.
Construction of the center at Elmira is 90% complete. Casework (made by LCC) will be installed shortly. Operations are expected to begin February 1.
Florence Center Addition
The new building is complete and in operation. More pressing bond project responsibilities prevented LCC personnel from building the covered roof between existing and new building. As a result LCC is bidding the project. Bids have been called for mid January with a construction completion date of February.
Main Campus Projects:
Welding:
Construction started May 27. Contractor did not finish the project by December 31 per original schedule and the Bond Team continues to think that the completion date will be mid to late January. The County Building Department has imposed some additional requirements on the project. We are in the process of working with the County to resolve these matters.
Parking Lot Improvements:
Contract for Parking Lot Improvements is 100% complete. Lights are operational.
Child Care Center:
Construction started in early July. Foundations and slabs have been poured for all 4 of the buildings which make up the center. Wood framed walls have been erected at the Office Building and Infants and Toddlers Building. The Office Building roof trusses have been set in place, the sheathing laid and a dry roofing sheet installed. Roof trusses for the Infants and Toddlers Building have been set in place. Exterior doors and windows have been installed in the Office Building.
Campus Service Addition:
Masonry is 90% complete. Glu-lam floor beams have been set and floor joists are being installed. Project should be completed by end of April 2000.
Science/Math:
Roofs over exterior walkways and walkways have been removed. Final rock excavation is complete. Elevator casings have been drilled. Forming for foundation pads has started and excavation for subgrade drain lines has been completed. X-rays were delayed until spring break.
Student Services:
Bids for the Student Services Building were opened January 13.
Workforce Training:
Rescheduled to go out for bid April 1, 2000.
Health Tech. Remodel:
Remodel is planned to go out for bids April 1, 2000 with a construction start date in mid-June.
Infrastructure Upgrade
Equipment included in the upgrade is being purchased and cabling for the Welding Building is scheduled to begin in January. The Welding Building portion of the project should be completed by March 2000. Cabling for the other buildings will follow.
Sewage Lagoon Upgrade
Representatives of the College and the Oregon National Guard met with engineers to review options for upgrading the Lagoon. The engineers presented 4 options with their respective cost estimates. Those present agreed that only 2 of the options should be pursued further. Briefly, these are option 1) add tertiary treatment which would enable us to discharge effluent year round and option 2) build a large holding pond to hold effluent until it can be safely released or used.
LTD Bus Station
The Handicapped parking stalls have been relocated at the west parking lot and a Bus lane has been created at the LTD Bus Station. Temporary shelters have been installed and concrete boarding platforms poured. The site is fully operational.
General Comments
The Bond Project Management Team continues to work with Personnel and others to create a process to deal with students, administrators, faculty, or classified personnel who find that they can not function adequately because of construction related causes.
The Bond Management Team is planning to set up a meeting in January with the occupants of the 2nd floor of the Apprentiship building to discuss the construction phasing of the Workforce Training Building.
Questions and comments about any bond construction activity may be directed to 744-4154 or e-mailed to bond@lanecc.edu. All communication received will be regularly reviewed by the Bond Project Management Team (BPMT), the architects, and the Facilities Management Committee.
|  |